PMI certification · Exam PMI-200

PMI-200 Mock Exam Page 2

PMI Agile Certified Practitioner (PMI-ACP)�

Free PMI-200 mock exam questions 11–20, each with the answer and an explanation.

20 questions · 33 minutes · free, no sign-up

Free PMI-200 questions

11–20 of 43 free
Question 11 Choose 1

A development team has finished identifying the tasks they will be accountable for during
the next sprint.Which of the following tools best provides transparency into the progress
throughout the sprint?

Show answerHide answer

Correct answer: A

Burndown chart

Question 12 Choose 1

The purpose of the iteration retrospective is to: 

Show answerHide answer

Correct answer: D

Identify what worked well, what did not work well, and what actions should be taken to
improve the process.

Question 13 Choose 1

For the best results in an Agile project, customers should:

Show answerHide answer

Correct answer: A

set priorities and identify product features.

Question 14 Choose 1

Which best describes the attributes of the IN VEST criteria in a user story?

Show answerHide answer

Correct answer: D

Independent, Negotiable, Valuable, Estimable, Small, and Testable

Question 15 Choose 1

Which technique is used by a project team to estimate the amount of work that can be
done per iteration? 

Show answerHide answer

Correct answer: A

Velocity measurement

Question 16 Choose 1

A common reason that a story may not be estimable is that the:

Show answerHide answer

Correct answer: A

team lacks domain knowledge.

Question 17 Choose 1

Applying the Pareto rule when prioritizing the Product Backlog means that:

Show answerHide answer

Correct answer: D

a small percentage of the work will provide a large percentage of the value.

Question 18 Choose 1

When is the ideal time to hold a retrospective?

Show answerHide answer

Correct answer: B

Just before iteration planning

Question 19 Choose 1

The process of reviewing, testing, and accepting implemented features is called:

Show answerHide answer

Correct answer: C

Scope verification.

Question 20 Choose 1

What is one of the main benefits that Lean portfolio management provides to a business?

Show answerHide answer

Correct answer: C

Line of sight to business needs

Full mock exam

Sit the PMI-200 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMI-200 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMI-200 mock exam
  • 65questions per mock
  • 105 mintime limit
  • 145questions in the bank
  • Newmock on every attempt