Question 71 Choose 1

Scenario: Intrepid Space Industries
Please read this scenario prior to answering the question
Intrepid Space Industries is the prime contractor for the Telesto Unmanned Spacecraft program.
Over the course of this contract, the company has grown rapidly by acquisition and has inherited
numerous different procurement processes and related IT systems. Intrepid is moving
aggressively to consolidate and reduce redundant procurement processes and systems. The CEO
has announced that the company will seek to leverage higher volume discounts and lower related
IT support costs by instituting a preferred supplier program.
To achieve this goal, Intrepid needs to define Baseline and Target Architectures. These
architectures must address key stakeholders concerns such as:
1. What groups of people should be involved in procurement-related business processes?
2. What current applications do those groups use?
3. Which procurement-related business processes are supported by zero, one, or many existing
applications?
4. What are the overall lifetimes of the Request for Proposal and Purchase Order business
objects? What non-procurement applications will need to be integrated with any new procurement
applications?
5. What data will need to be shared?
At present, there are no particularly useful architectural assets related to this initiative, so all
assets need to be acquired and customized or created from scratch. The company prefers to
implement existing package applications from systems vendors with little customization.
The architecture development project has just completed its Architecture Context iteration cycle
and is about to begin the Architecture Definition iteration cycle. Intrepid is using TOGAF for its
internal Enterprise Architecture activities. It uses an iterative approach for executing Architecture
Development Method (ADM) projects.
The architecture development project has just completed its Architecture Context iteration cycle
and is about to begin the Architecture Definition iteration cycle.
Refer to the Intrepid Space Industries Scenario.
You are serving as the Lead Architect.
You have been asked to identify the most appropriate architecture viewpoints for this situation.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: C

 In the early iterations of the Architecture Definition:
Describe the Target Business Architecture with a Business Service/Function catalog and an
Organization/Actor catalog
Describe the key business objects with Data Lifecycle diagrams
Describe the Target Application Architecture with Application Communication diagrams and an
Application Interaction matrix
Describe the Target Data Architecture with a System/Data matrix
In the later iterations of the Architecture Definition:
Describe the Baseline Business Architecture with a Business Service/Function catalog and a
Business Interaction matrix
Describe the Baseline Application Architecture with an Application and User Location diagram and
a System/Function matrix
Describe the Baseline Data Architecture with a Data Entity/Data Component catalog

Question 72 Choose 1

Scenario: Sollace Manufacturing
Please read this scenario prior to answering the question
Sollace Manufacturing is a major supplier in the automotive industry, headquartered In Cleveland,
Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of
these plants has been operating its own planning and production scheduling systems, as well as
custom developed applications that drive the automated production equipment at each plant.
Sollace Manufacturing is implementing lean manufacturing principles to minimize waste and
improve the efficiency of all of its production operations. During a recent exercise held for internal
quality improvement, it was determined that a significant reduction in process waste could be
achieved by replacing the current planning and scheduling systems with a common Enterprise
Resource Planning (ERP) system located in the Cleveland data center. This central system would
provide support to each of the plants replacing the functionality in the existing systems. It would
also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT
staff could support the remaining applications. In some cases, a third-party contractor could
provide those staff.
The Sollace Manufacturing Enterprise Architecture department has been operating for several
years and has mature, well-developed architecture governance and development processes that
are strongly based on TOGAF 9.
At a recent meeting, the Architecture Review Board approved a Request for Architecture Work
from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The
request covered the initial architectural investigations and the development of a comprehensive
architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project
team has been asked to develop an Architecture Vision that will achieve the desired outcomes and
benefits. Some of the plant managers have expressed concern about the security and reliability of
driving their planning and production scheduling from a central system located in Cleveland. The
Chief Engineer wants to know how these concerns can be addressed.
Refer to the Sollace Manufacturing Scenario
You are serving as the Lead Enterprise Architect for the Common ERP Deployment architecture
project.
One of the earliest initiatives in the Enterprise Architecture program at Sollace Manufacturing was
the definition of a set of IT principles and architecture principles that are well aligned with the
overall enterprise principles. These now need to be updated to address the concerns raised.
You have been asked to select a set of principles most appropriate for guiding the team to define a
robust solution.
[Note: You should assume that Sollace Manufacturing has adopted the example set of principles
that are listed and defined in TOGAF 9, Section 23.6.]
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: D

Information Management is Everybodys Business, IT Responsibility, Data Trustee, Technology
Independence, Responsive Change Management

Question 73 Choose 1

Scenario: Acme Widgets Inc.
Please read this scenario prior to answering the question
Acme Widgets Inc. manufactures a variety of small electromechanical devices. As part of a
corporate-wide Lean Manufacturing initiative, it has defined a strategic architecture to improve its
ability to meet consumer demand and improve its ability to manage its supply chain. The strategic
architecture called for the consolidation of multiple Enterprise Resource Planning (ERP)
applications that have been operating independently in several of the divisions production
facilities. The goal is to replace the functionality of the existing applications with a new ERP
product running as a single instance in the company's primary data center.
Acme has a mature enterprise architecture practice and uses TOGAF 9 for the basis of its
architecture framework, [n addition to the EA program, Acme has a number of management
frameworks in use, including business planning, portfolio/project management, and operations
management. The EA program is sponsored by the CIO.
Each division has completed the Architecture Definition documentation required to tailor and
configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation
constraints. A consolidated gap analysis has been completed which has identified the gaps across
the Business, Data, Application, and Technology domains. Based on the results of the gap
analysis, the architects have reviewed the functional requirements and interoperability
requirements needed to integrate the new ERP environment into the existing environment.
Based on all of these factors, the architects have assessed the organizations readiness to
conduct the business transformation and have produced a risk assessment.
Because of the risks posed by the complexity of the current environment, it has been determined
that a phased approach is needed to implement the target architectures. The overall
implementation process is estimated to take several years.
Refer to the Acme Widgets Scenario
Your role is consultant to the Lead Architect.
The Implementation and Migration Plan v.0.l, the Transition Architectures v1.0, and the Capability
Assessment deliverables are now complete. You have been asked to recommend the next steps
to prepare the final Implementation and Migration Plan.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: D

You would place the strategic Architecture Definition and Transition Architectures under
configuration control as part of the ongoing evolution cycle. This will ensure that the architecture
remains relevant and responsive to the needs of the enterprise. You would then produce an
Implementation Governance Model to manage the lessons learned prior to finalizing the plan. You
recommend that lessons learned be accepted by the Architecture Board as changes to the
architecture without review.

Question 74 Choose 1

Scenario: Global Traders Inc.
Please read this scenario prior to answering the question
Global Traders is a large, global commodities trading company which has been growing rapidly
through a series of acquisitions.
Each new business is performing well in its markets. However, the lack of integration between
headquarters and the business units has increasingly caused problems in the handling of
customer and financial information. The inability to share information across businesses has
resulted in lost opportunities to "leverage the synergies" that had been intended when the
businesses were acquired. At present, each business unit maintains its own applications. Despite
an earlier initiative to install a common application to manage customer, products, supplier, and
inventory information, each business unit has different ways of defining each of these core
elements and has customized the common application to the point where the ability to exchange
information is difficult, costly, and error-prone.
As a result, Global Traders has begun implementing a single Enterprise Resource Planning (ERP)
system to consolidate information from several applications that exist across the lines of business.
The Corporate Board is concerned that the new ERP system must be able to manage and
safeguard customer information in a manner that meets or exceeds the legal requirements of the
countries in which the company operates. This will be an increasingly important capability as the
company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its
charter is to coordinate efforts between the ERP implementation team and the business unit
personnel who will be involved in the migration process. The CIO has also formed a crossfunctional
Architecture Review Board to oversee and govern the architecture.Global Traders has
selected TOGAF 9 as the basis for its Enterprise Architecture program. The CIO has endorsed this
choice with the full support of top management.
Refer to the Global Traders Inc. Scenario
You are serving as the Chief Architect.
You have been asked to recommend the approach to take in the Preliminary Phase to ensure that
the Corporate Board's concern is addressed.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: D

You evaluate the implications of the Boards concern by examining the potential impacts on
business goals and objectives. Based on your understanding, you then update the current Global
Traders security policy to include an emphasis on the Boards concern.
In addition, you allocate a security architect to ensure that security considerations are included in
the architecture planning for all domains.

Question 75 Choose 1

Scenario: St. Christopher Consulting
Please read this scenario prior to answering the question
St. Christopher Consulting started as an accounting and financial services company. It has
expanded over the years and is now a leading North American IT and Business Services provider.
With numerous practice areas and a multitude of diverse engagements underway at any given
time, overall engagement management has become challenging. The company does not want to
risk its outstanding reputation or its international certifications and CMM ratings. Senior partners
must become team players, working to support the broader needs of the company and its
shareholders.
The Enterprise Architecture team has been working to create St. Christophers Enterprise
Architecture framework to address these issues. The team has defined a preliminary framework
and held workshops with key stakeholders to define a set of principles to govern the architecture
work. They have completed an Architecture Vision at a strategic level and laid out Architecture
Definitions for the four domains. They have set out an ambitious vision of the future of the
company over a five-year period.
An Architecture Review Board has been formed comprised of IT staff executives and executives
from the major practice areas.
The Chief Executive Officer and Chief Information Officer have co-sponsored the creation of the
Enterprise Architecture program. The Enterprise Architecture framework is based en TOGAF 9.
As the EA team prepare to formulate an Implementation plan, they have been asked by the CIO to
assess the risks associated with the proposed architecture. He has received concerns from senior
management that the proposed architecture may be too ambitious and they are not sure it can
produce sufficient value to warrant the attendant risks.
Refer to the St Christopher Consulting Scenario
You have been assigned to the role of Chief Enterprise Architect.
You have been asked to recommend an approach to satisfy the concerns raised.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: A

An interoperability analysis should be applied to evaluate any potential issues across the
Solution Architecture. Once all of the concerns have been resolved, the EA team should finalize
the Architecture Implementation Roadmap and the Migration Plan

Question 76 Choose 1

Scenario: Sollace Manufacturing
Please read this scenario prior to answering the question
Sollace Manufacturing is a major supplier in the automotive industry, headquartered in Cleveland,
Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of
these plants has been operating its own planning and production scheduling systems, as well as
custom developed applications that drive the automated production equipment at each plant.
Sollace Manufacturing is implementing lean manufacturing principles to minimize waste and
improve the efficiency of all of its production operations. During a recent exercise held for internal
quality improvement, it was determined that a significant reduction in process waste could be
achieved by replacing the current planning and scheduling systems with a common Enterprise
Resource Planning (ERP) system located in the Cleveland data center. This central system would
provide support to each of the plants replacing the functionality in the existing systems. It would
also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT
staff could support the remaining applications. In some cases, a third-party contractor could
provide those staff.
The Sollace Manufacturing Enterprise Architecture department has been operating for several
years and has mature, well-developed architecture governance and development processes that
are strongly based on TOGAF 9.At a recent meeting, the Architecture Review Board approved a
Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is
the project sponsor. The request covered the initial architectural investigations and the
development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project
team has been asked to develop an Architecture Vision that will achieve the desired outcomes and
benefits. Some of the plant managers have expressed concern about the security and reliability of
driving their planning and production scheduling from a central system located in Cleveland. The
Chief Engineer wants to know how these concerns can be addressed.
Refer to the Sollace Manufacturing Scenario
You are serving as the Lead Enterprise Architect of the newly-formed Common ERP Deployment
architecture project team.
As the Common ERP Deployment architecture project team assembles for its initial meeting, many
of the participants have voiced concerns about the sweeping scope of the initiative. Others are
confident that they know a solution that will work. During the meeting, a number of alternative
recommendations for how to proceed are put forward by members of the team.
You have been asked to select the most appropriate recommendation to ensure that the team
evaluates different approaches to the problem and clarifies the requirements for the architecture.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: C

The team should create Baseline and Target Architectures for each of the manufacturing
plants. A gap analysis between the architectures will then validate the approach, and determine
the Transition Architecture needed to achieve the target state.

Question 77 Choose 1

Scenario: MedInc Products Ltd.
Please read this scenario prior to answering the Question.
MedInc Products Ltd. is a leading medical device manufacturer in the highly competitive market for
Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are
implanted in the brain and can deliver a precise electric shock when the wearable Pain Control
Unit (PCU) detects an increase in stress induced by the onset of a migraine headache. This
technology will be a breakthrough in the treatment of this condition, and several competitors are
striving to be the first to introduce a product into the market. However, all of them must
demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy
the regulatory requirements of the countries in the target markets.
The Enterprise Architecture group at MedInc Products has been engaged in an architecture
development project to create a secure networked collaboration system that will allow researchers
at its product development laboratories worldwide to share information about their independent
clinical trials. The Enterprise Architecture group is a mature organization that has been utilizing
TOGAF for several years. The MedInc Architecture Development Method is strictly based on
TOGAF 9 with extensions required to support current good manufacturing practices and good
laboratory practices in their target markets. The project team has now completed the Business,
Information Systems, and Technology Architecture phases and has produced a complete set of
deliverables for each phase. Due to the highly sensitive nature of the information that is managed,
special care was taken to ensure that each architecture domain included an examination of the
security and privacy issues that are relevant for each domain. A corresponding Security
Architecture has been defined.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture
activity. He has stated that the changes to the enterprise architecture for the new system will need
to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials. The
work will need to be done in stages and rolled out in geographical regions.
Refer to the Medlnc Products Ltd. Scenario
You are serving as the Lead Architect for the project team.
You have been asked to recommend the approach to identify the work packages that will be
included in the Transition Architecture(s).
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: C

Use a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool. For each gap
classify whether the solution is either a new development, purchased solution, or based on an
existing product. Group the similar solutions together to define the work packages. Regroup the
work packages into a set of Capability Increments to transition to the Target Architecture taking
into account the schedule for clinical trials.

Question 78 Choose 1

Scenario: Mobile Telco
Please read this scenario prior to answering the Question.
Mobile Telco is a mobile telecommunications company formed through a series of mergers and
acquisitions. They are yet to fully integrate the customer service systems for the most recent
acquisitions, and as result, customer service has been a major concern for the Chief Technology
Officer. Results for the last two quarters have shown that Average Revenue Per User (ARPU) and
the customer retention (Churn) rate have fallen below the industry average.
The Corporate Marketing group has published some new findings about customer satisfaction.
The customers appear to be switching to AirLight, a competitor, because of superior customer
service. Mobile Telco actually has better coverage in nearly all markets than AirLight, and good
roaming agreements that keep rates low for business travelers. But, customer satisfaction has
remained low. The Business Strategy group and the Enterprise Architecture group have
conducted a high-level project to develop the enterprise-wide strategic plan.
They have developed a business scenario which contains a good conceptual model of what needs
to be done, and also identifies the key requirements. This was used in preparing the proposal
presented to the Executive Council and the Corporate Board. The planning for the program has
been underway for several months. Mobile Telco has selected TOGAF 9 as the basis for its
Enterprise Architecture. The Corporate Board has approved funding for a multi-million Euro
conversion to transition to a packaged Customer Service System. It is anticipated that the overall
program will take five years to complete, but there are some tactical projects that can commence
immediately to address the situation.
The Executive Council has stated that the program should define specific initiatives to enable each
regional business unit to create an implementation of the Customer Service System. The
implementation must meet the needs of the business unit and still provide the information needed
to enable major improvements to the customer.
Refer to the Mobile Telco Scenario
You are serving as the Lead Architect for the Performance and Integrity project of the Customer
Service System program.
The project has been chartered to address the architecture(s) required to support the Customer
Service System from an infrastructure perspective. At the present time, the project team is
conducting an architecture development project that is focused on the customer self-service
capability, which was defined as part of the earlier strategic planning activities. This capability will
enable customers to access their accounts, pay bills, request account reviews, and provision
services from any web-enabled device.
The project team has gathered information about the self-service capability, developed a business
scenario, and used the results to define an Architecture Vision for achieving the capability.
You have been asked to recommend the course of action to complete the project.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: D

The remaining architecture definition work should be focused en mapping out the technology
and infrastructure capability in the Technology domain. In Phases E and F, the capability should
be broken down into a set of Solution Building Blocks that will be implemented to realize the
Target Architecture.
The Solution Building Blocks will provide the basis for the completed Architecture Definition
Document that will be submitted for approval. Upon approval, the implementation team will
conduct Compliance Assessments to ensure that the self-service capability is compliant with the
overall Enterprise Architecture

Question 79 Choose 1

Scenario: Reveille Bugle
Please read this scenario prior to answering the question
For over 100 years, Reveille Bugle has been manufacturing brass bugles and other musical
instruments. North America has been the primary market for Reveilles products. However, the
firm has now expanded into European markets and will soon establish a market in Latin America.
A future expansion into the Asia Pacific region is also planned.
The firm is organized into several business units that each focus on manufacturing particular
families of instruments such as brass, woodwind, and percussion. Each business unit has
acquired other producers to create its manufacturing capacity. This has resulted in a complex
environment with a high diversity of business and manufacturing systems.
The Enterprise Architecture (EA) program at Reveille Bugle has been functioning for several
years. It has made significant progress in consolidating the technology portfolio and establishing
key standards. The CIO and the COO are joint sponsors of the EA program. By all measures, the
EA program is mature, with an active Architecture Board and a well-defined architecture process
and standard content templates based on the TOGAF 9 Architecture Content Framework. The EA
process framework is well coordinated with the PMO, Systems Development, and Operations
functions.
The firm has completed a strategic plan to reorganize its Sales & Marketing organization
according to four geographic market sectors: North America; Europe, Africa, and Middle East;
Latin America; and Asia-Pacific. One of the goals of this reorganization is to improve the ability of
Marketing to collect more meaningful market analytics that will enable each sector to better
address market needs with effective marketing campaigns and global product presence.
A Request for Architecture Work has been approved. As the architecture team commences its
work, the CIO has expressed a concern about whether the firm will be able to adapt to the
proposed architecture and how to manage the associated risks.
Refer to the Reveille Bugle Scenario
Your role is consultant to the Lead Architect.
You have been asked how to address the concerns of the CIO.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: C

In Phase A the team should analyze their risk by completing an Implementation Factor
Assessment and Deduction Matrix to identify the particular risks associated with the
implementation and deployment. These factors can then used to assess the initial risks associated
with the proposed architecture.

Question 80 Choose 1

Scenario: Global Traders Inc.
Please read this scenario prior to answering the question
Global Traders is a large, global commodities trading company which has been growing rapidly
through a series of acquisitions. Each new business is performing well in its markets. However,
the lack of integration between headquarters and the business units has increasingly caused
problems in the handling of customer and financial information. The inability to share information
across businesses has resulted in lost opportunities to "leverage the synergies" that had been
intended when the businesses were acquired. At present, each business unit maintains its own
applications. Despite an earlier initiative to install a common application to manage customer,
products, supplier, and inventory information, each business unit has different ways of defining
each of these core elements and has customized the common application to the point where the
ability to exchange information is difficult, costly, and error-prone.
As a result, Global Traders has begun implementing a single Enterprise Resource Planning (ERP)
system to consolidate information from several applications that exist across the lines of business.
The Corporate Board is concerned that the new ERP system must be able to manage and
safeguard customer information in a manner that meets or exceeds the legal requirements of the
countries in which the company operates. This will be an increasingly important capability as the
company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its
charter is to coordinate efforts between the ERP implementation team and the business unit
personnel who will be involved in the migration process. The CIO has also formed a crossfunctional
Architecture Review Board to oversee and govern the architecture.
After reviewing the available alternatives, and based on recommendations from the ERP vendor,
Global Traders has selected TOGAF 9 as the basis for its Enterprise Architecture program. The
CIO has endorsed this choice with the full support of top management.
Refer to the Global Traders Inc. Scenario
You are serving as the Chief Architect.
As part of the process for establishing the Enterprise Architecture department, you have decided
to create a set of principles to guide the activities.
You have been asked to recommend the best approach for this work.
Based on TOGAF 9, which of the following is the best answer

Show answerHide answer

Correct answer: B

You examine the mission statements for Global Traders and each of its businesses, together
with the corporate value statements. Based on that, you work with the Architecture Review Board
to define the principles.
When developing the principles you ensure that they actively promote the alignment of IT with the
Global Traders business strategies. You then run a series of reviews with all the relevant
stakeholders, including senior management, ensuring their support.

Full mock exam

Sit the OG0-093 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real OG0-093 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full OG0-093 mock exam
  • 65questions per mock
  • 105 mintime limit
  • 360questions in the bank