Question 91 Choose 1

Scenario:
Please read this scenario prior to answering the Question
You are serving as the Lead Architect for an enterprise architecture project team within a leading
medical device manufacturer that specializes in miniature devices. The latest product under
development is a tiny wireless device that can be implanted in the brain and can deliver a precise
electric shock when the wearable Pain Control Unit (PCU) detects an increase in stress induced
by the onset of a migraine headache.
This technology will be a breakthrough in the treatment of this condition, and several competitors
are striving to be the first to introduce a product into the market. However, all of them must
demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy
the regulatory requirements of the countries in the target markets.
The Enterprise Architecture group within the company has been engaged in an architecture
development project to create a secure networked collaboration system that will allow researchers
at its product development laboratories worldwide to share information about their independent
clinical trials.
The Enterprise Architecture group is a mature organization that has been utilizing TOGAF for
several years. They use the TOGAF 9 ADM with extensions required to support current good
manufacturing practices and good laboratory practices in their target markets. Due to the highly
sensitive nature of the information that is managed, special care was taken to ensure that each
architecture domain included an examination of the security and privacy issues that are relevant
for each domain. A corresponding Security Architecture has been defined.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture
activity. She has stated that the changes to the enterprise architecture for the new system will
need to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials.
The work will need to be done in stages and rolled out in geographical regions.
Refer to the Scenario
You have been asked to recommend the approach to identify the work packages that will be
included in the Transition Architecture(s).
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: D

Use a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool. For each gap
classify whether the solution is either a new envelopment, purchased solution, or based on an
existing product. Group the similar solutions together to define the work packages. Regroup the
work packages into a set of Capability Increments to transition to the Target Architecture taking
into account the schedule for clinical trials

Question 92 Choose 1

Scenario:
Please read this scenario prior to answering the Question
You are the Lead Architect for a firm that manufactures ball bearings used in industrial equipment
applications. They have manufacturing operations in several cities in the United States, Germany,
and the United Kingdom.
The firm has traditionally allowed each manufacturing plant to drive its own production planning
systems. Each plant has its own custom Materials Requirements Planning, Master Production
Scheduling, Bill of Materials, and Shop Floor Control systems.
"Just In Time" manufacturing techniques are used to minimize wastes caused by excessive
inventory and work in process. The increasingly competitive business environment has compelled
the firm to improve its business capability to be more responsive to the needs of industrial
customers. To support this capability, the firm has decided to implement an Enterprise Resource
Planning (ERP) solution that will enable it to better coordinate its manufacturing capacity to match
the demands for its products across all plants. In addition, there are also new European
regulations coming into force to which their manufacturing processes must conform in the next six
months.
As part of the implementation process, the Enterprise Architecture (EA) department has begun to
implement an architecture process based on TOGAF 9. The CIO is the sponsor of the activity. The
Chief Architect has directed that the program should include formal modeling using the
Architecture Content Framework and the TOGAF Content Metamodel. This will enable support for
the architecture tooling that the firm uses for its EA program.
The Chief Architect has stated that in order to model the complex manufacturing process it will be
necessary to model processes that are event-driven. Also, in order to consolidate applications
across several data centers it will be necessary to model the location of IT assets. In particular, the
end goal is to have the single ERP application running in a single data center.
Currently the project is in the Preliminary Phase, and the architects are tailoring the Architecture
Development Method (ADM) and Architecture Content Framework to fit into the corporate
environment.
Refer to the Scenario
You have been asked to recommend a response to the Chief Architects request to tailor the
TOGAF Content Metamodel.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: B

You recommend that the architecture team incorporate the Process Modeling and Governance
extensions into their tailored Content Metamodel. This is suitable as this is a significant IT change
that will impact its operational models. This will ensure that they include specific entities and
attributes that will allow them to model the event-driven nature of the manufacturing processes
more precisely.

Question 93 Choose 1

Scenario:
Please read this scenario prior to answering the Question
You are serving as the Chief Architect for a large, global commodities trading company which has
been growing rapidly through a series of acquisitions.
Each business is performing well in its markets. However, the lack of integration between
headquarters and the business units has increasingly caused problems in the handling of
customer and financial information. The inability to share information across businesses has
resulted in lost opportunities to "leverage the synergies" that had been intended when the
businesses were acquired. At present, each business unit maintains its own applications. Despite
an earlier initiative to install a common application to manage customer, products, supplier, and
inventory information, each business unit has different ways of defining each of these core
elements and has customized the common application to the point where the ability to exchange
information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a single enterprise-wide application
to consolidate information from several applications that exist across the lines of business. The
application will be used by all business units and accessed by suppliers through well defined
interfaces.
Refer to the Scenario
As part of the process for establishing the Enterprise Architecture department, you are developing
a set of architecture principles to guide the activities.
You need to specify the best approach for this work.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: D

You examine the mission statements for the company and each of its businesses, together with
the corporate value statements. Based on that, you work with the Architecture Board to define the
principles. When developing the principles you ensure that they actively promote the alignment of
IT with the corporate business strategies. You then hold a series of review meetings with all the
relevant stakeholders, including senior management, ensuring their support.

Question 94 Choose 1

Scenario:
Please read this scenario prior to answering the Question
You are serving as the Lead Enterprise Architect at a major supplier in the automotive industry.
The company is headquartered in Cleveland, Ohio with manufacturing plants across the United
States, Brazil, Germany, Japan and South Korea. Each of these plants has been operating its own
planning and production scheduling systems, as well as custom developed applications that drive
the automated production equipment at each plant.
The company is implementing lean manufacturing principles to minimize waste and improve the
efficiency of all of its production operations. During a recent exercise held for internal quality
improvement, it was determined that a significant reduction in process waste could be achieved by
replacing the current planning and scheduling systems with a common Enterprise Resource
Planning (ERP) system located in the Cleveland data center. This central system would provide
support to each of the plants replacing the functionality in the existing systems. It would also
eliminate the need for full data centers at each of the plant facilities. A reduced number of IT staff
could support the remaining applications. In some cases, a third-party contractor could provide
those staff.
The Enterprise Architecture department has been operating for several years and has mature,
well-developed architecture governance and development processes that are strongly based on
TOGAF 9.
At a recent meeting, the Architecture Board approved a Request for Architecture Work sponsored
by the Chief Engineer of Global Manufacturing Operations. The request covered the initial
architectural investigations and the development of a comprehensive architecture to plan the
transformation.
The Common ERP Deployment architecture project team has now been formed, and the project
team has been asked to develop an Architecture Vision that will achieve the desired outcomes and
benefits. Some of the plant managers have expressed concern about the security and reliability of
diving their planning and production scheduling from a remote centralized system. The Chief
Engineer wants to know how these concerns can be addressed.
Refer to the Scenario
During the initial meeting of the Common ERP Deployment architecture project team, a number of
alternative recommendations for how to proceed are put forward by members of the team.
You have been asked to select the most appropriate recommendation to ensure that the team
evaluates different approaches to the problem and clarifies the requirements for the architecture.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: A

A. The team should develop Baseline and Target Architectures for each of the manufacturing
plants, ensuring that the views corresponding to selected viewpoints address key concerns of the
stakeholders. A consolidated gap analysis between the architectures will then be used to validate
the approach, and determine the capability increments needed to achieve the target state.

Question 95 Choose 1

Scenario
Please read this scenario prior to answering the Question
You have been appointed as a consultant to the Chief Enterprise Architect of a multinational
pharmaceutical corporation. The corporation includes 30 subsidiary companies with operations in
over 60 countries and products sold in over 125 countries. It has major research and development
sites in over 45 locations worldwide.
The management team is deeply committed to ensuring that the corporation is a world leader in
socially responsible pharmaceutical development with a business strategy that focuses on
profitability through environmentally friendly operating processes as well as a commitment to
disease eradication.
The operations of the corporation are subject to legal and regulatory requirements for each
country where they operate. The production of prescription pharmaceutical products has
governmental controls that are strictly enforced and compliance is critical. Recently a competitor
was heavily fined for violating the regulations in a country where it was conducting a clinical trial
for a new regulated drug.
The Governing Board is concerned about the risks posed in this complex global environment. As a
result the Chief Executive Officer (CEO) has appointed a Chief Compliance Officer (CCO) to be
responsible for overseeing and managing compliance issues for the corporation. The CCO reports
directly to the CEO.
The CCO has approved the expenditure of resources to establish an Enterprise Architecture
program. He has requested to be informed about the status of projects that could impact
regulatory compliance. He also wants the corporate legal staff and auditors to analyze all
proposed architectures to ensure that they are within the legal guidelines for each country. In
addition, the research organization should be able to see that the architecture is appropriate for its
needs.
TOGAF 9 has been mandated as the framework for the development and evolution of the
Enterprise Architecture practice. The Preliminary Phase has been completed to establish the
enterprise architecture capability for this project.
Refer to the Scenario
You have been asked to recommend an approach that would enable the development of an
architecture that addresses the needs of the Chief Compliance Officer, legal staff, auditors and the
research organization.
Based on TOGAF, which of the following is the best answer?

Show answerHide answer

Correct answer: A

You recommend that a stakeholder map be developed. This will allow the architects to define
groups of stakeholders that share common concerns. A set of views should be defined to address
the concerns for each group of stakeholders. Architecture models should then be created for each
view to address the stakeholders concerns.

Question 96 Choose 1

Scenario
Please read this scenario prior to answering the Question
Your role is that of a consultant to the Lead Enterprise Architect in a company that develops
photovoltaic technologies for use in large-scale solar power farms. The company has three
manufacturing facilities, two in the United States, and one in Southern France. Each of these
facilities supplies a different manufacturer that assembles and sells complete systems. The solar
panels and photovoltaic arrays are custom engineered to meet each manufacturer's design
specifications.
A challenge that the solar power industry has faced is the efficiency of energy conversion. When a
conventional solar panel overheats, it becomes inefficient and generates less energy. In response
to this, the research arm of the company has pioneered the development of a new solar panel
design that will produce up to 50% more energy than standard solar panels when operating at
elevated temperatures. This will allow the production of significantly more useable energy per
square meter than from standard solar technology. This new design is ready to go into production.
The company has a mature Enterprise Architecture practice that is supported by a cross-functional
Architecture Board. TOGAF 9 is used for developing the automated manufacturing process and
systems used to design, manufacture and test the solar power technologies they produce. The
Chief Information Officer and the Chief Operating Officer co-sponsor the Enterprise Architecture
program.
As part of putting the new solar panel design into production, a pilot architecture project at a single
location has defined an updated standard approach for controlling the automated test systems
used to perform final quality assurance. The Chief Engineer, sponsor of the activity, and the
Architecture Board have approved the plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy
the new automated test system controller for each location. The Chief Engineer has expressed
concern that a uniform process be employed at each location to ensure consistency and high
yields.
Refer to the Scenario
The Lead Enterprise Architect has asked you to recommend the best approach to address the
Chief Engineers concern.
Based on TOGAF, which of the following is the best answer?

Show answerHide answer

Correct answer: A

 You review the applicable Architecture Contract for each location, ensuring that it addresses
the project objectives, effectiveness metrics, acceptance criteria, and risk management. In cases
where the contract is issued to an external party, you ensure that it is a legally enforceable
contract. You schedule compliance reviews at key points in the implementation process to ensure
that the work is proceeding in accordance with the Architecture Definition. You ensure that the
Architecture Board reviews all deviations from the Architecture Contract, and considers whether or
not to grant a dispensation to allow the implementation organization to customize the process to
meet their local needs.

Question 97 Choose 1

Scenario
Please read this scenario prior to answering the Question
You have been assigned the role of Chief Enterprise Architect within a leading outsourcing
services company. The company has over 20,000 outsourcing professionals and works on some
of the world's largest outsourcing projects. Outsourcing services include business processes,
infrastructure, and service management. The company also provides business consulting
services.
With numerous service areas and a large number of diverse engagements in progress at any
given time, overall engagement management within the company has become challenging. The
company does not want to risk Its outstanding reputation or its international certifications and
CMM ratings.
The company has an established an Enterprise Architecture program based on TOGAF 9,
sponsored jointly by the Chief Executive Officer and Chief Information Officer. An Architecture
Board has been formed comprised of IT staff executives and executives from the major service
areas and consulting practice.
The Enterprise Architecture (EA) team has been working with the Strategic Planning team to
create a strategic enterprise architecture to address these issues. The EA team has defined a
framework and held workshops with key stakeholders to define a set of architecture principles to
govern the architecture work. They have completed an Architecture Vision at a strategic level and
laid out Architecture Definitions for the four domains. They have set out an ambitious vision of the
future of the company over a five-year period. This includes a solution architecture including three
distinct transformations.
The CIO has made it clear that prior to the approval of the detailed Implementation and Migration
plan, the EA team will need to assess the risks associated with the proposed architecture. He has
received concerns from some of the vice presidents across the company that the proposed
architecture may be too ambitious and they are not sure it can produce sufficient value to warrant
the attendant risks.
Refer to the Scenario
You have been asked to recommend an approach to satisfy these concerns.
Based on TOGAF, which of the following is the best answer?

Show answerHide answer

Correct answer: D

The EA team should apply the Business Transformation Readiness Assessment technique.
This will allow the risks associated with the transformations to be identified and mitigated for. It will
also identify improvement actions to be worked into the Implementation and Migration Plan. The
Business Value Assessment technique should then be used to determine the business value and
associated risks for the transformation.

Question 98 Choose 1

Scenario
Please read this scenario prior to answering the Question
You are serving as the Lead Architect for a chain of convenience stores, operating as a franchise,
which has over 5000 retail outlets throughout the Asia-Pacific region. The stores operate 24 hours
a day and 7 days a week and rely on point-of-sale technology to manage their inventory.
Stores place all orders on-line. The back-office systems collect realtime data to support ordering
and product selection decisions including the tailoring of product assortment based on sales
history, customer demographics as well as the next days weather forecast. In many cases,
several stores are located in neighboring areas. This strategy makes distribution to each store
cheaper, as well as making multiple deliveries per day possible.
An Enterprise Architecture practice exists within the company, with the CEO and CIO as joint
sponsors. They have decided to adopt TOGAF 9 within the practice and the first project is to
restructure the Enterprise Architecture so that it can better accommodate the changing strategies
within the company and also better respond to changes in economic and technical environments.
The CIO has stated that the following issues need to be addressed in the restructuring:
The systems should be able to withstand any unforeseen disruptions which might affect day to
day operations. This is highly critical for ensuring high levels of customer satisfaction and
maintaining and growing revenue.
Dependencies between the application components, the application platform, and technology
infrastructure should be minimal and well defined. This will facilitate scalability and ease of

enhancement of the service offerings.
The company is adopting the ARTS Operational Data Model and Data Warehouse Model from
the National Retail Federation. This will address past problems with data quality and inconsistent
data.
To remain competitive, new products and promotions must undergo market trials and if these
are successful, deployed across the retail chain. Information systems must be able to manage
changes and updates without undue delays.
Refer to the Scenario
[Note: You should assume that the company has adopted the example set of principles that are
listed and defined in TOGAF, Section 23.6. You may need to refer to Chapter 23 of the reference
text in order to answer this question.]
You have been asked to identify the most relevant architecture principles for the current situation.
Based on TOGAF, which of the following is the best answer? [Note: The ordering of the principles
listed in each answer is not significant.]

Show answerHide answer

Correct answer: B

 Technology Independence, Business Continuity, Common Vocabulary and Data Definitions,
Data Trustee, Responsive Change Management

Question 99 Choose 1

Scenario
Please read this scenario prior to answering the Question
You are serving as the Lead Architect for the enterprise architecture team at a large multinational
aerospace and defense company. The company has grown rapidly by acquisition and has
inherited numerous different procurement processes and related IT systems. Several procurement
processes have had problems related to the timing of purchases, which has led to excess
inventory. The Vice President in charge of Supply Chain Management has made the decision to
consolidate and reduce redundant procurement processes and systems. The company will move
to a "Just-in-time" procurement system so as to keep inventory costs low.
TOGAF 9 is used for internal Enterprise Architecture activities. This project is using an iterative
approach for executing the Architecture Development Method (ADM).
At present, there are no particularly useful architectural assets in the Architecture Repository that
are related to this initiative. All assets will need to be acquired, customized, or created from
scratch. The company prefers to implement commercial off the shelf package applications with
little customization. The CIO, who is the project sponsor, has stated that she is not concerned
about preserving the existing procurement processes or systems.
The architecture development project has completed the Preliminary Phase and has started a
number of iteration cycles to develop the Architecture. As a packaged application is being
considered, the next iteration will include both the Business and Application Architectures. Key
stakeholder concerns that should be addressed by these architectures include:
1. What groups of people should be involved in procurement-related business processes?
2. What are the overall lifetimes of the Request for Proposal and Purchase Order business
objects?
3. What non-procurement applications will need to be integrated with any new procurement
applications?
Refer to the Scenario
[Note: You may need to refer to Chapter 35 of the reference text in order to answer this question.]
You have been asked to identify the most appropriate catalogs, matrices, and diagrams to support
the next iteration of Architecture development.
Based on TOGAF, which of the following is the best answer?

Show answerHide answer

Correct answer: C

In the next iteration of Architecture development, you would describe the Target Business
Architecture with a Business Service/Function catalog, a Business Interaction matrix, and Product
Lifecycle diagrams. You would describe the Target Application Architecture with Application
Communication diagrams and an Application Interaction matrix.

Explanation

Explanation: Figure 35-3 Artifacts Associated with the Core Content Metamodel and Extensions

Question 100 Choose 1

Scenario
Please read this scenario prior to answering the Question
Your role is that of Lead Enterprise Architect within the staff headquarters of a large hotel chain.
The chain manages over 500 hotels across North America and Canada, with another 230 hotels
internationally in the United Kingdom, Europe, Australia and New Zealand. Unlike other hotel
chains, which are often a mix of company-owned and franchised units, each hotel in the chain is
an independently owned and operated franchise. Many of the hotels use the same internal IT
systems that they used before they joined the franchise. Until recently, the only requirement that
has been placed on each hotel is that they use a standard financial reporting system to report their
financial results to the headquarters on a weekly basis.

The CEO of the chain has stated his concerns about the inefficiencies of the current approach and
identified the need to change. He has defined a new strategic vision that will enhance the business
by providing its franchisees new support services including worldwide reservations, global,
national and regional marketing as well as consolidated financial, logistics, and yield management.
This strategy is part of the long-term commitment to enhance the brand image and drive superior
revenue for the chain. He has also stated that he expects improved financial results by the end of
the current fiscal year.
These changes will provide the chain with improved utilization of its capacity and more efficient
operations. The addition of a corporate-wide data warehouse will provide analytics that will enable
the marketing group to improve its ability to target advertising into key national and regional
markets to improve yields.
The chain has a mature enterprise architecture practice based in its headquarters and uses
TOGAF 9 as the method and guiding framework. The CIO is the sponsor of the activity.
In planning this change, the Chief Architect engaged the services of a well-known consulting firm
that specializes in business strategy. An initial study has been conducted to identify the strategic
changes needed to implement the CEO's vision. This recently completed with approval of a
strategic architecture encompassing the entire chain, including detailed requirements and
recommendations.
Based on the recommendations from the initial study, the chain has taken the decision to adopt a
packaged suite of integrated applications that is tailored to the needs of the hospitality industry.
Refer to the scenario
You have been asked by the Chief Architect to propose the best approach for architecture
development to realize the CEO's vision.
Based on TOGAF, which of the following is the best answer?

Show answerHide answer

Correct answer: B

You propose that the target architecture is defined first, followed by transition planning. This is
because the vision is well understood and the strategic architecture agreed. The target first
approach will ensure that the current problems and inefficiencies of the baseline architecture are
not carried forward, and that the proposed solution addresses the requirements identified in the
initial study.

Full mock exam

Sit the OG0-093 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real OG0-093 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full OG0-093 mock exam
  • 65questions per mock
  • 105 mintime limit
  • 360questions in the bank
  • Newmock on every attempt