Question 1 Choose 1

Scenario: Turbonix Enterprises

Please read this scenario prior to answering the question
Turbonix Enterprises specializes in the development of wind turbine blades for use in large-scale
commercial wind energy production systems. Turbonix has manufacturing facilities located in Palm
Springs, California, Omaha, Nebraska, and Winnipeg, Manitoba. Each of these plants supplies a
different manufacturer that builds and sells complete systems. The turbine blades are custom
engineered to meet each manufacturer's design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics.
However, recent improvements in composite materials, coupled with enhanced automated
methods for precision application of materials during the molding process, have led to significant
reduction in weight, increase in strength, and greatly improved blade longevity. Turbonix has
pioneered the development of a proprietary automated process for continuous extrusion of the
turbine blades. Patents have been filed to protect the process, but certain trade secrets must be
closely guarded.
Turbonix has a mature Enterprise Architecture organization that is supported by a cross-functional
Architecture Review Board. The Chief Information Officer and the Chief Operating Officer cosponsor
the Enterprise Architecture program.
Turbonix has used T0GAF and its Architecture Development Method (ADM) to develop its
automated manufacturing processes and systems that are used to design, manufacture, and test
the blade assemblies. They have adapted their Enterprise Architecture to closely follow the
TOGAF 9 framework. All of Turbonix's enterprise architects have been trained and certified on
TOGAF 9.Recently, an architecture project was completed that defined a standard approach for
controlling the Automated Test System that is used at each plant to perform final quality assurance
tests on each completed blade assembly. The Manufacturing Architecture Board approved the
plan for immediate implementation at each plant.
An Architecture Contract was developed that detailed the work needed to implement and deploy
the new Automated Test System controller. The Chief Engineer, sponsor of the activity, has
expressed concern that a uniform process be employed at each site to ensure consistency.
Refer to the Turbonix Enterprises Scenario
You are the Lead Architect for this activity.
You have been asked to recommend the best approach to adopt to address the Chief Engineer's
concern.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: D

You create an Architecture Contract to govern the implementation and migration process at
each site. If the contract is issued to an external party, you ensure that it is a fully enforceable
legal contract. You ensure that the contract addresses the project objectives, effectiveness
metrics, acceptance criteria, and risk management. You then schedule compliance reviews at key
points in the implementation process to ensure that the work is proceeding in accordance with the
Architecture Definition. Based on the results, you ensure that the Manufacturing Architecture
Board reviews all deviations from the Architecture Contract, and considers whether or not to grant
a dispensation to allow the implementation organization to customize the process to meet their
local needs.

Explanation

Explanation:
Incorrect:
Not C: correct, but missing contract see 49.2.2..
Note:
* Dispensations
A dispensation is used as the mechanism to request a change to the existing architectures,
contracts, principles, etc. outside of normal operating parameters; e.g., exclude provision of
ser vice to a subsidiary, request for unusual service levels for specific business reasons, deploy
non-standard technology or products to support specific business initiatives.
Dispensations are granted for a given time period and set of identified services and operational
cr iter ia that must be enforced during the lifespan of the dispensation. Dispensations are not
granted indefinitely, but are used as a mechanism to ensure that service levels and operational
levels, etc. are met while providing a level flexibility in their implementation and timing. The
timebound
nature of dispensations ensures that they are a trigger to the Architecture Compliance
activity

Question 2 Choose 1

Scenario: Glacier Ridge LLC
Please read this scenario prior to answering the question
Glacier Ridge LLC is a vacation property management firm that is growing through acquisition. It
manages over 200 resort properties across North America. Many of the resort properties use the
same internal IT systems that they used before they were acquired. Until recently, the only
requirement that has been placed in each property is that they use a standard financial reporting
system to report their financials ID the headquarters on a weekly basis.
The CEO has stated his concerns about the inefficiencies of the current approach and identified
the need to change. He has defined a new strategic vision that will enhance the Glacier Ridge
property business by standardizing its operations across the network to provide consolidated
financial, human resources, logistics, sales and marketing, and yield management. He has also
stated that he expects results by the end of the current fiscal year.
These changes will provide the company with improved utilization of its capacity and more efficient
operations. The addition of a corporate-wide data warehouse will provide analytics that will enable
the marketing group to improve its ability to target advertising into key markets to improve yields.
Glacier Ridge has a mature enterprise architecture (EA) practice and uses TOGAF 9 as the
method and guiding framework. The CIO is the sponsor of the activity.
In planning this change, the Chief Architect engaged the services of a well-known consulting firm
that specializes in business strategy. An initial study has been conducted to identify the strategic
changes needed to implement the CEO's vision. This recently completed with approval of a
strategic architecture encompassing the entire firm, including detailed requirements and
recommendations.
Based on the recommendations from the initial engagement, Glacier Ridge has embraced an
Architecture Vision to adopt an enterprise application that is tailored to the needs of the hospitality
industry.
Refer to the Glacier Ridge scenario
Your role is that of Chief Architect. You have been asked to recommend the best approach to take
in this architecture engagement to realize the CEO's vision.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: C

You recommend that this engagement define the Technology Architecture first in order to
assess the current infrastructure capacity and capability. Then the focus should be on transition
planning and architecture deployment. This will identify requirements to ensure that the projects
are sequenced in an optimal fashion so as to realize the vision.

Question 3 Choose 1

Scenario: Summer Seeds BV
Please read this scenario prior to answering the question
Summer Seeds BV is an international agricultural company exporting bulbs, flowers and seeds
worldwide. It is headquartered in Rotterdam in the Netherlands, and has sales and distribution
centers in over 60 countries worldwide. Several of these centers include administrative,
manufacturing, and research facilities.
To achieve full integration of their research capabilities with their development centers located in
various climate zones, the company wants to develop strong self-directed teams in each location.
It also wants to define new business models that are profitable while reducing their impact on the
environment. The management is deeply committed to ensuring that the company is a world
leader in socially responsible seed development with a business strategy that focuses on
profitability through environmentally friendly operating processes.
Summer Seed's international operations are subject to various legal and regulatory requirements.
In areas such as genetically modified seeds, governmental controls are strictly enforced and
compliance is critical. Recently a competitor was heavily fined for violating the regulations in a
country where it was developing pest-resistant seeds.
The Governing Board is concerned, and as a result has approved the expenditure of resources to
establish an Enterprise Architecture program. They have requested information about the status of
projects that could impact regulatory compliance. They also want to enable the corporate legal
staff and auditors to analyze proposed architectures to ensure that they are within the legal
guidelines for a given location. In addition, the research organization should be able to see that the
architecture is appropriate for its needs. TOGAF 9 has been mandated as the guiding framework
for the development and evolution of the Enterprise Architecture practice.
Refer to the Summer Seeds BV Scenario
You have been appointed as the Lead Consultant.
You have been asked to recommend an approach that would enable the development of an
architecture that addresses the needs of all these parties.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: D

For those groups that have sufficient power and level of interest, a special report should be
created that summarizes the key features of the architecture with respect to the particular location.
Each of these reports should reflect the stakeholders requirements

Question 4 Choose 1

Scenario: Intrepid Space Industries
Please read this scenario prior to answering the question
Intrepid Space Industries is the prime contractor for the Telesto Unmanned Spacecraft program.
Over the course of this contract, the company has grown rapidly by acquisition and has inherited
numerous different procurement processes and related IT systems. Intrepid is moving
aggressively to consolidate and reduce redundant procurement processes and systems. The CEO
has announced that the company will seek to leverage higher volume discounts and lower related
IT support costs by instituting a preferred supplier program.
To achieve this goal, Intrepid needs to define Baseline and Target Architectures. These
architectures must address key stakeholders concerns such as:
1. What groups of people should be involved in procurement-related business processes?
2. What current applications do those groups use?
3. Which procurement-related business processes are supported by zero, one, or many existing
applications?
4. What are the overall lifetimes of the Request for Proposal and Purchase Order business
objects? What non-procurement applications will need to be integrated with any new procurement
applications?
5. What data will need to be shared?
At present, there are no particularly useful architectural assets related to this initiative, so all
assets need to be acquired and customized or created from scratch. The company prefers to
implement existing package applications from systems vendors with little customization.
The architecture development project has just completed its Architecture Context iteration cycle
and is about to begin the Architecture Definition iteration cycle. Intrepid is using TOGAF for its
internal Enterprise Architecture activities. It uses an iterative approach for executing Architecture
Development Method (ADM) projects.
The architecture development project has just completed its Architecture Context iteration cycle
and is about to begin the Architecture Definition iteration cycle.
Refer to the Intrepid Space Industries Scenario.
You are serving as the Lead Architect.
You have been asked to identify the most appropriate architecture viewpoints for this situation.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: C

 In the early iterations of the Architecture Definition:
Describe the Target Business Architecture with a Business Service/Function catalog and an
Organization/Actor catalog
Describe the key business objects with Data Lifecycle diagrams
Describe the Target Application Architecture with Application Communication diagrams and an
Application Interaction matrix
Describe the Target Data Architecture with a System/Data matrix
In the later iterations of the Architecture Definition:
Describe the Baseline Business Architecture with a Business Service/Function catalog and a
Business Interaction matrix
Describe the Baseline Application Architecture with an Application and User Location diagram and
a System/Function matrix
Describe the Baseline Data Architecture with a Data Entity/Data Component catalog

Question 5 Choose 1

Scenario: Sollace Manufacturing
Please read this scenario prior to answering the question
Sollace Manufacturing is a major supplier in the automotive industry, headquartered In Cleveland,
Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of
these plants has been operating its own planning and production scheduling systems, as well as
custom developed applications that drive the automated production equipment at each plant.
Sollace Manufacturing is implementing lean manufacturing principles to minimize waste and
improve the efficiency of all of its production operations. During a recent exercise held for internal
quality improvement, it was determined that a significant reduction in process waste could be
achieved by replacing the current planning and scheduling systems with a common Enterprise
Resource Planning (ERP) system located in the Cleveland data center. This central system would
provide support to each of the plants replacing the functionality in the existing systems. It would
also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT
staff could support the remaining applications. In some cases, a third-party contractor could
provide those staff.
The Sollace Manufacturing Enterprise Architecture department has been operating for several
years and has mature, well-developed architecture governance and development processes that
are strongly based on TOGAF 9.
At a recent meeting, the Architecture Review Board approved a Request for Architecture Work
from the Chief Engineer of Global Manufacturing Operations who is the project sponsor. The
request covered the initial architectural investigations and the development of a comprehensive
architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project
team has been asked to develop an Architecture Vision that will achieve the desired outcomes and
benefits. Some of the plant managers have expressed concern about the security and reliability of
driving their planning and production scheduling from a central system located in Cleveland. The
Chief Engineer wants to know how these concerns can be addressed.
Refer to the Sollace Manufacturing Scenario
You are serving as the Lead Enterprise Architect for the Common ERP Deployment architecture
project.
One of the earliest initiatives in the Enterprise Architecture program at Sollace Manufacturing was
the definition of a set of IT principles and architecture principles that are well aligned with the
overall enterprise principles. These now need to be updated to address the concerns raised.
You have been asked to select a set of principles most appropriate for guiding the team to define a
robust solution.
[Note: You should assume that Sollace Manufacturing has adopted the example set of principles
that are listed and defined in TOGAF 9, Section 23.6.]
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: D

Information Management is Everybodys Business, IT Responsibility, Data Trustee, Technology
Independence, Responsive Change Management

Question 6 Choose 1

Scenario: Acme Widgets Inc.
Please read this scenario prior to answering the question
Acme Widgets Inc. manufactures a variety of small electromechanical devices. As part of a
corporate-wide Lean Manufacturing initiative, it has defined a strategic architecture to improve its
ability to meet consumer demand and improve its ability to manage its supply chain. The strategic
architecture called for the consolidation of multiple Enterprise Resource Planning (ERP)
applications that have been operating independently in several of the divisions production
facilities. The goal is to replace the functionality of the existing applications with a new ERP
product running as a single instance in the company's primary data center.
Acme has a mature enterprise architecture practice and uses TOGAF 9 for the basis of its
architecture framework, [n addition to the EA program, Acme has a number of management
frameworks in use, including business planning, portfolio/project management, and operations
management. The EA program is sponsored by the CIO.
Each division has completed the Architecture Definition documentation required to tailor and
configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation
constraints. A consolidated gap analysis has been completed which has identified the gaps across
the Business, Data, Application, and Technology domains. Based on the results of the gap
analysis, the architects have reviewed the functional requirements and interoperability
requirements needed to integrate the new ERP environment into the existing environment.
Based on all of these factors, the architects have assessed the organizations readiness to
conduct the business transformation and have produced a risk assessment.
Because of the risks posed by the complexity of the current environment, it has been determined
that a phased approach is needed to implement the target architectures. The overall
implementation process is estimated to take several years.
Refer to the Acme Widgets Scenario
Your role is consultant to the Lead Architect.
The Implementation and Migration Plan v.0.l, the Transition Architectures v1.0, and the Capability
Assessment deliverables are now complete. You have been asked to recommend the next steps
to prepare the final Implementation and Migration Plan.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: D

You would place the strategic Architecture Definition and Transition Architectures under
configuration control as part of the ongoing evolution cycle. This will ensure that the architecture
remains relevant and responsive to the needs of the enterprise. You would then produce an
Implementation Governance Model to manage the lessons learned prior to finalizing the plan. You
recommend that lessons learned be accepted by the Architecture Board as changes to the
architecture without review.

Question 7 Choose 1

Scenario: Global Traders Inc.
Please read this scenario prior to answering the question
Global Traders is a large, global commodities trading company which has been growing rapidly
through a series of acquisitions.
Each new business is performing well in its markets. However, the lack of integration between
headquarters and the business units has increasingly caused problems in the handling of
customer and financial information. The inability to share information across businesses has
resulted in lost opportunities to "leverage the synergies" that had been intended when the
businesses were acquired. At present, each business unit maintains its own applications. Despite
an earlier initiative to install a common application to manage customer, products, supplier, and
inventory information, each business unit has different ways of defining each of these core
elements and has customized the common application to the point where the ability to exchange
information is difficult, costly, and error-prone.
As a result, Global Traders has begun implementing a single Enterprise Resource Planning (ERP)
system to consolidate information from several applications that exist across the lines of business.
The Corporate Board is concerned that the new ERP system must be able to manage and
safeguard customer information in a manner that meets or exceeds the legal requirements of the
countries in which the company operates. This will be an increasingly important capability as the
company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its
charter is to coordinate efforts between the ERP implementation team and the business unit
personnel who will be involved in the migration process. The CIO has also formed a crossfunctional
Architecture Review Board to oversee and govern the architecture.Global Traders has
selected TOGAF 9 as the basis for its Enterprise Architecture program. The CIO has endorsed this
choice with the full support of top management.
Refer to the Global Traders Inc. Scenario
You are serving as the Chief Architect.
You have been asked to recommend the approach to take in the Preliminary Phase to ensure that
the Corporate Board's concern is addressed.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: D

You evaluate the implications of the Boards concern by examining the potential impacts on
business goals and objectives. Based on your understanding, you then update the current Global
Traders security policy to include an emphasis on the Boards concern.
In addition, you allocate a security architect to ensure that security considerations are included in
the architecture planning for all domains.

Question 8 Choose 1

Scenario: St. Christopher Consulting
Please read this scenario prior to answering the question
St. Christopher Consulting started as an accounting and financial services company. It has
expanded over the years and is now a leading North American IT and Business Services provider.
With numerous practice areas and a multitude of diverse engagements underway at any given
time, overall engagement management has become challenging. The company does not want to
risk its outstanding reputation or its international certifications and CMM ratings. Senior partners
must become team players, working to support the broader needs of the company and its
shareholders.
The Enterprise Architecture team has been working to create St. Christophers Enterprise
Architecture framework to address these issues. The team has defined a preliminary framework
and held workshops with key stakeholders to define a set of principles to govern the architecture
work. They have completed an Architecture Vision at a strategic level and laid out Architecture
Definitions for the four domains. They have set out an ambitious vision of the future of the
company over a five-year period.
An Architecture Review Board has been formed comprised of IT staff executives and executives
from the major practice areas.
The Chief Executive Officer and Chief Information Officer have co-sponsored the creation of the
Enterprise Architecture program. The Enterprise Architecture framework is based en TOGAF 9.
As the EA team prepare to formulate an Implementation plan, they have been asked by the CIO to
assess the risks associated with the proposed architecture. He has received concerns from senior
management that the proposed architecture may be too ambitious and they are not sure it can
produce sufficient value to warrant the attendant risks.
Refer to the St Christopher Consulting Scenario
You have been assigned to the role of Chief Enterprise Architect.
You have been asked to recommend an approach to satisfy the concerns raised.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: A

An interoperability analysis should be applied to evaluate any potential issues across the
Solution Architecture. Once all of the concerns have been resolved, the EA team should finalize
the Architecture Implementation Roadmap and the Migration Plan

Question 9 Choose 1

Scenario: Sollace Manufacturing
Please read this scenario prior to answering the question
Sollace Manufacturing is a major supplier in the automotive industry, headquartered in Cleveland,
Ohio with manufacturing plants in Chicago, Sao Paulo, Stuttgart, Yokohama, and Seoul. Each of
these plants has been operating its own planning and production scheduling systems, as well as
custom developed applications that drive the automated production equipment at each plant.
Sollace Manufacturing is implementing lean manufacturing principles to minimize waste and
improve the efficiency of all of its production operations. During a recent exercise held for internal
quality improvement, it was determined that a significant reduction in process waste could be
achieved by replacing the current planning and scheduling systems with a common Enterprise
Resource Planning (ERP) system located in the Cleveland data center. This central system would
provide support to each of the plants replacing the functionality in the existing systems. It would
also eliminate the need for full data centers at each of the plant facilities. A reduced number of IT
staff could support the remaining applications. In some cases, a third-party contractor could
provide those staff.
The Sollace Manufacturing Enterprise Architecture department has been operating for several
years and has mature, well-developed architecture governance and development processes that
are strongly based on TOGAF 9.At a recent meeting, the Architecture Review Board approved a
Request for Architecture Work from the Chief Engineer of Global Manufacturing Operations who is
the project sponsor. The request covered the initial architectural investigations and the
development of a comprehensive architecture to plan the transformation.
The Common ERP Deployment architecture project team has now been formed, and the project
team has been asked to develop an Architecture Vision that will achieve the desired outcomes and
benefits. Some of the plant managers have expressed concern about the security and reliability of
driving their planning and production scheduling from a central system located in Cleveland. The
Chief Engineer wants to know how these concerns can be addressed.
Refer to the Sollace Manufacturing Scenario
You are serving as the Lead Enterprise Architect of the newly-formed Common ERP Deployment
architecture project team.
As the Common ERP Deployment architecture project team assembles for its initial meeting, many
of the participants have voiced concerns about the sweeping scope of the initiative. Others are
confident that they know a solution that will work. During the meeting, a number of alternative
recommendations for how to proceed are put forward by members of the team.
You have been asked to select the most appropriate recommendation to ensure that the team
evaluates different approaches to the problem and clarifies the requirements for the architecture.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: C

The team should create Baseline and Target Architectures for each of the manufacturing
plants. A gap analysis between the architectures will then validate the approach, and determine
the Transition Architecture needed to achieve the target state.

Question 10 Choose 1

Scenario: MedInc Products Ltd.
Please read this scenario prior to answering the Question.
MedInc Products Ltd. is a leading medical device manufacturer in the highly competitive market for
Migraine Headache Pain Management (MHPM) devices. These tiny wireless devices are
implanted in the brain and can deliver a precise electric shock when the wearable Pain Control
Unit (PCU) detects an increase in stress induced by the onset of a migraine headache. This
technology will be a breakthrough in the treatment of this condition, and several competitors are
striving to be the first to introduce a product into the market. However, all of them must
demonstrate the effectiveness and safety of their products in a set of clinical trials that will satisfy
the regulatory requirements of the countries in the target markets.
The Enterprise Architecture group at MedInc Products has been engaged in an architecture
development project to create a secure networked collaboration system that will allow researchers
at its product development laboratories worldwide to share information about their independent
clinical trials. The Enterprise Architecture group is a mature organization that has been utilizing
TOGAF for several years. The MedInc Architecture Development Method is strictly based on
TOGAF 9 with extensions required to support current good manufacturing practices and good
laboratory practices in their target markets. The project team has now completed the Business,
Information Systems, and Technology Architecture phases and has produced a complete set of
deliverables for each phase. Due to the highly sensitive nature of the information that is managed,
special care was taken to ensure that each architecture domain included an examination of the
security and privacy issues that are relevant for each domain. A corresponding Security
Architecture has been defined.
The Executive Vice President for Clinical Research is the sponsor of the Enterprise Architecture
activity. He has stated that the changes to the enterprise architecture for the new system will need
to be rolled out on a geographic basis that will minimize disruptions to ongoing clinical trials. The
work will need to be done in stages and rolled out in geographical regions.
Refer to the Medlnc Products Ltd. Scenario
You are serving as the Lead Architect for the project team.
You have been asked to recommend the approach to identify the work packages that will be
included in the Transition Architecture(s).
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: C

Use a Consolidated Gaps, Solutions and Dependencies Matrix as a planning tool. For each gap
classify whether the solution is either a new development, purchased solution, or based on an
existing product. Group the similar solutions together to define the work packages. Regroup the
work packages into a set of Capability Increments to transition to the Target Architecture taking
into account the schedule for clinical trials.

Full mock exam

Sit the OG0-093 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real OG0-093 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full OG0-093 mock exam
  • 65questions per mock
  • 105 mintime limit
  • 360questions in the bank
  • Newmock on every attempt