You close the inventory period for July 2020. You set the value of the Allow Posting From field in General Ledger Setup to August 1, 2020.
You receive and post a purchase invoice for freight charges on August 8, 2020 against a purchase invoice that was posted on July 15, 2020. You run the Adjust cost – Item entries batch job for August.
You need to identify the adjustment entry related to July after running the batch job.
Which date is automatically selected for the value entry by batch job?
Show answerHide answer
Correct answer: C August 1, 2020
Explanation
Explanation:When an inventory period is closed, cost adjustments for that period are prevented. A freight charge posted in August against a July purchase is an additional direct cost that must be allocated to the original item cost. However, because the July period is closed, the system must post the adjustment to the earliest allowable date in the next open period.
Correct Option:
C. August 1, 2020
Explanation:
The Allow Posting From date in General Ledger Setup (Aug 1, 2020) defines the start of the next open period. The Adjust Cost – Item Entries batch job is aware of the closed July period and therefore backdates the resulting value entry to the last day of the previous closed period. Since July is closed and August is open, the adjustment is posted to the first day of the new open period, which is August 1, 2020.
Incorrect Options:
A. July 15, 2020:
This is the date of the original purchase, but the inventory period for July is closed. The system cannot post new entries to a closed period.
B. August 8, 2020:
This is the actual posting date of the freight charge invoice. However, cost adjustments that relate to items received in a closed period are automatically backdated to the boundary of the open period (August 1) to maintain period-based inventory valuation accuracy.
D. July 1, 2020:
This is the first day of the closed July period. No new postings are allowed on this date.
Reference:
Microsoft Learn documentation "Adjust Item Costs" and "Work with Inventory Periods." It states that when you run cost adjustment for a later period, and additional costs are assigned to items received in a closed period, the resulting value entry is dated the first day of the period for which you are adjusting costs (i.e., the start of the next open period, defined by "Allow Posting From").