A LEED Building Design and Construction: New Construction office building's HVAC
system includes hot water from a central utility plant. The central utility plant is owned and
operated by a management company. The office pays a flat fee for hot water, included as
part of the leas. The management company does not meter or invoice for actual hot water
consumption. For the project to meet the requirements for Energy and Atmosphere
Prerequisite, Building-Level Energy Metering, an energy meter must be installed for
Show answerHide answer
Correct answer: Bhot water at the main service point
Explanation
Explanation:
An energy meter must be installed for hot water at the main service point for the project to
meet the requirements for Energy and Atmosphere Prerequisite, Building-Level Energy
Metering. According to the LEED v4 BD+C Reference Guide, this prerequisite requires that
“all energy sources used by the building must be metered or submetered” 1. The hot water
from the central utility plant is an energy source used by the building, even if it is not
directly paid by the office. Therefore, it must be metered at the point where it enters the
building. The other options are incorrect because natural gas is not an energy source used
by the building in this case, and the flat fee or the ownership of the energy source do not
exempt the project from the metering requirement.References: LEED v4 BD+C Reference
Guide, Energy and Atmosphere Category, EAp Building-Level Energy Metering, page 569.
Question 12Choose 1
A contractor is building a retirement community project. 30% of the building's product costs
were derived from reused/salvaged materials or met recycled content criteria. Which of the
following credits can the LEED AP submit towards certification?
Show answerHide answer
Correct answer: AMaterials and Resources Credit, Building Product Disclosure and Optimization -
Sourcing of Raw Materials
Question 13Choose 1
The Sustainable Sites Credit, Heat Island Reduction takes into account both new and
three-year aged Solar Reflectance Index (SRI) values for roofing material because
Show answerHide answer
Correct answer: BSRI generally decreases with age
Explanation
Explanation:
SRI generally decreases with age
The Solar Reflectance Index (SRI) is a measure of the ability of a surface to reflect solar
heat, as shown by a small temperature rise. It is calculated using the values of solar
reflectance and thermal emittance of the surface. The higher the SRI, the lower the heat
island effect. However, SRI generally decreases with age due to factors such as
weathering, dirt accumulation, and biological growth. Therefore, the Sustainable Sites
Credit, Heat Island Reduction takes into account both new and three-year aged SRI values
for roofing material to ensure that the material maintains a high level of reflectance over
time.
Question 14Choose 1
Under Energy and Atmosphere Prerequisite, Fundamental Commissioning and Verification,
a current facilities requirements and operations and maintenance plan must contain which
information necessary to operate the building efficiently?
Show answerHide answer
Correct answer: AAny changes in schedules or setpoints for different seasons, days of the week, and
times of day
Explanation
Explanation:
A current facilities requirements and operations and maintenance plan must contain any
changes in schedules or setpoints for different seasons, days of the week, and times of
day. This is to ensure that the building systems are operating efficiently and according to
the design intent. The other options are too limited or too specific and do not cover all the
possible variations in schedules or setpoints.References: LEED v4 BD+C Reference
Guide, Energy and Atmosphere Category, EAp Fundamental Commissioning and
Verification, page 569.
Question 15Choose 1
What is the basis of energy consumption in determining the percentage of green power or
carbon offsets?
Show answerHide answer
Correct answer: BQuantity
Question 16Choose 1
When a project team sustainably develops a project site, the design should
Show answerHide answer
Correct answer: Cremediate sites already in decline
Explanation
Explanation: remediate sites already in decline
When a project team sustainably develops a project site, the design should aim to
remediate sites already in decline, such as brownfields, degraded lands, or abandoned
properties. By doing so, the project can restore the environmental quality, ecological
functions, and social value of the site, as well as reduce the pressure on undeveloped lands and natural habitats. LEED offers credits for projects that choose to locate on and
remediate sites already in decline, such as the Sustainable Sites Credit, Site Assessment
and the Sustainable Sites Credit, Brownfields Remediation1.
Question 17Choose 1
A project has total waste of 20 tons (18.1 tonnes) that includes the following:
· 8 tons (7.3 tonnes) of recycled demolition steel and concrete
· 2 tons (1.8 tonnes) of trees cleared from the site
. 3 tons (2.7 tonnes) of commingled scrap with 40% diverted
. 6 tons (5.4 tonnes) of used furniture donated to a non-profit organization
· 1 ton (0.9 tonnes) of removed carpet and ceiling tiles sent back to the manufacturer
What is the percentage of diverted waste for Materials and Resources Credit, Construction
and Demolition Waste
Management?
Show answerHide answer
Correct answer: B75%
Explanation
Explanation:
The percentage of diverted waste for Materials and Resources Credit, Construction and
Demolition Waste Management is calculated by dividing the total weight of diverted
materials by the total weight of waste generated1. Diverted materials are those that are
reused, recycled, salvaged, or donated2. In this case, the total weight of diverted materials
is:
8 tons (7.3 tonnes) of recycled demolition steel and concrete
6 tons (5.4 tonnes) of used furniture donated to a non-profit organization
1 ton (0.9 tonnes) of removed carpet and ceiling tiles sent back to the
manufacturer
40% of 3 tons (2.7 tonnes) of commingled scrap, which is 1.2 tons (1.1 tonnes)
The sum of these weights is 16.2 tons (14.7 tonnes). The total weight of waste generated is 20 tons (18.1 tonnes). Therefore, the percentage of diverted waste is:
(16.2 / 20) x 100 = 81%
However, the credit allows for a 10% adjustment for vegetative waste, which is not
considered a building material3. Therefore, the percentage of diverted waste after
adjustment is:
(81 - 10) = 71%
The closest answer option to this value is B. 75%.
Question 18Choose 1
What are the Storage and Collection of Recyclables requirements for only Retail projects
under the Materials and Resources Prerequisite?
Show answerHide answer
Correct answer: AWhat are the Storage and Collection of Recyclables requirements for only Retail projects
under the Materials and Resources Prerequisite?
Explanation
Explanation:
Retail projects must conduct a waste stream audit for the duration of the project in an
existing location or make projections based on historical data for similar establishments.
Identify the top-five recyclable waste streams while stating the top-four waste streams
where both collection and storage space will be provided. This is the requirement for Retail projects under the Materials and Resources Prerequisite, Storage and Collection of
Recyclables, according to the LEED v4 BD+C Reference Guide1. The purpose of this
prerequisite is to facilitate the reduction of waste generated by building occupants that is
hauled to and disposed of in landfills1. The prerequisite applies to all LEED BD+C projects,
but Retail projects have a different approach than other project types because of their
unique waste streams and operational characteristics1. Retail projects must conduct a
waste stream audit for the duration of the project in an existing location or make projections
based on historical data for similar establishments. The audit or projection must identify the
top-five recyclable waste streams by weight or volume using consistent metrics
throughout1. The waste stream study period must be a minimum of 24 hours1. Retail
projects must also provide dedicated areas that serve the entire building and are
accessible to waste haulers and building occupants for the collection and storage of
materials for recycling for at least four of the top-five recyclable waste streams identified by
the audit or projection1.
Question 19Choose 1
Which is a benefit of earning Regional Priority credits?
Show answerHide answer
Correct answer: AThe LEED project can achieve more sustainable outcomes by recognizing the issues
that are a priority in the project's location
Explanation
Explanation:
A benefit of earning Regional Priority credits is that the LEED project can achieve more
sustainable outcomes by recognizing the issues that are a priority in the project’s location.
Regional Priority credits are not new LEED credits, but instead are existing credits that
USGBC regional councils and chapters have designated as being particularly important for
their areas1. The incentive to achieve the credits is in the form of a bonus point. If an RP
base credit is earned, then a bonus point is awarded to the project’s total points1. This way,
the project can address the geographically specific environmental, social equity and public health priorities of its location2.
Question 20Choose 1
A project attempting to meet the preferred parking requirements for Location and
Transportation Credit, Green Vehicles may provide what incentive to meet the
requirements and highlight the project sustainable vehicle strategy?
Show answerHide answer
Correct answer: CA permanent discounted parking rate of at least 20% for all green vehicles
Explanation
Explanation: The Location and Transportation Credit, Green Vehicles aims to reduce
transportation-related greenhouse gas emissions by promoting the use of low-emitting,
fuel-efficient, and alternative-fuel vehicles1. One of the requirements for this credit is to
provide preferred parking for green vehicles for 5% of the total vehicle parking capacity of
the project1. Preferred parking is defined as parking that is clearly marked and located in
the most convenient spaces available to the driver or nearest to the main entrance of the
project2. In addition to providing preferred parking, the project may also offer one or more
incentives to encourage the use of green vehicles, such as a discounted parking rate, free
parking passes, or rebates for parking fees3. The question asks what incentive may be
provided to meet the requirements and highlight the project sustainable vehicle strategy.
The correct answer is C. A permanent discounted parking rate of at least 20% for all green
vehicles, because this incentive meets the minimum threshold of 20% discount suggested
by the LEED Reference Guide for Building Design and Construction3, and it also
demonstrates the project’s commitment to supporting green vehicles in the long term. The
other options are either not sufficient or not relevant for this credit. Option A. Three years of
free parking for green vehicles is not sufficient because it is not permanent and may not be
attractive enough for drivers to switch to green vehicles. Option B. Preferred parking decals
for 5% of occupants utilizing carpool vehicles is not relevant because it does not address
green vehicles, but rather carpool vehicles, which are covered by a different credit
(Location and Transportation Credit, Reduced Parking Footprint)4. Option D. An annual
maintenance voucher for at least 5% of occupants driving green vehicles is not sufficient
because it is not directly related to parking and may not be a significant incentive for
drivers.
Full mock exam
Sit the LEED-AP-BD+C exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real LEED-AP-BD+C exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.