LEED AP Building Design + Construction (LEED AP BD+C)
Find out if you're ready for LEED-AP-BD+C. Take the free timed mock exam and get your score in minutes, or study the free LEED-AP-BD+C questions below with answers and explanations.
Which rating system is appropriate for a new mixed-use building with 300,000 ft2 (27 871
m2) of residential units, 150,000 ft2 (13 935 m2) hotel and 50,000 ft2 (4 645 m2) of retail
space?
Show answerHide answer
Correct answer: DNew Construction
Explanation
New Construction is the appropriate rating system for a new mixed-use building with
300,000 ft2 (27 871 m2) of residential units, 150,000 ft2 (13 935 m2) hotel and 50,000 ft2
(4 645 m2) of retail space. According to the LEED rating system selection guidance1, the
New Construction rating system applies to buildings that are being newly constructed or
going through a major renovation, and that include any of the following use types: office,
retail, hospitality, education, residential, warehouse and distribution centers, or data
centers2. The New Construction rating system can also be used for mixed-use buildings
that have more than one use type3. Since the project involves new construction of a mixed use
building with residential, hospitality, and retail uses, the New Construction rating
system is the most suitable option. The other rating systems are not applicable because
they are either specific to one use type (Retail and Hospitality) or to buildings that are not
complete at the time of certification (Core and Shell Development).
Question 2Choose 1
LEED project boundaries that include multiple similar buildings which are all eligible for
certification can be registered as which of the following?
Show answerHide answer
Correct answer: BGroup project
Explanation
Explanation:
LEED project boundaries that include multiple similar buildings which are all eligible for
certification can be registered as a group project. A group project allows multiple buildings
(or interior spaces within multiple buildings) on a shared site to be certified as a single
LEED project. These projects must meet the criteria outlined in the LEED Campus
Guidance for Projects on a Shared Site, such as having the same construction contract,
ownership, management, space type, rating system, and compliance paths. A group
project will receive one certification and rating for the entire group.References: Group
Projects (previously Multiple Building Projects), CAGBC News, September 1, 2020.
Question 3Choose 1
A project elects to pursue Location and Transportation Credit, Surrounding Density and
Diverse Uses, Option 2. Diverse Uses because of the project's location in an amenity-rich
area. The project features 18 uses overall, including at least four uses in three of the five
use type categories. What threshold must the project surpass in order to demonstrate
exemplary performance for Option 2?
Show answerHide answer
Correct answer: AExemplary Performance is not available for Option 2
Explanation
Explanation:
Exemplary Performance is not available for Option 2 of Location and Transportation Credit,
Surrounding Density and Diverse Uses. According to the LEED v4 BD+C Reference Guide,
this credit has two options: Option 1. Surrounding Density (5 points) and Option 2. Diverse
Uses (1 point). Exemplary Performance is only available for Option 1, and it requires
achieving a surrounding density of at least 405,000 square feet per acre (100,000 square
meters per hectare)1. Option 2 does not have any Exemplary Performance criteria, and it
only requires locating the project within a 1/2-mile (800-meter) walking distance of at least
seven diverse uses2.
Question 4Choose 1
Which of the following will contribute to reducing the heat island effect?
Show answerHide answer
Correct answer: BIntensive vegetated roof
Explanation
Explanation:
An intensive vegetated roof is a roof that has a thick layer of soil and plants that provide
shade, evapotranspiration, and stormwater management. It can reduce the heat island
effect by lowering the surface and air temperature of the roof and the surrounding area.
Artificial turf grass does not reduce the heat island effect because it is not a living plant and
does not provide cooling benefits. A steep sloped roof with initial SRI of 35 does not meet
the minimum requirement of 39 for Option 1 or 32 for Option 2 of the Heat Island Reduction
credit. A low sloped roof with initial SRI of 64 exceeds the minimum requirement of 82 for
Option 1 or 64 for Option 2, but it is not the best option among the choices because it only
reflects solar radiation and does not provide other benefits such as shading,
evapotranspiration, and stormwater management.
Question 5Choose 1
The scope of analysis in Materials and Resources Credit, Building Life-Cycle Impact
Reduction, Option 4.
Whole-Building Life-Cycle Assessment is a
Show answerHide answer
Correct answer: Ccradle-to-grave assessment
Explanation
Explanation:
The scope of analysis in Materials and Resources Credit, Building Life-Cycle Impact
Reduction, Option 4. Whole-Building Life-Cycle Assessment is a cradle-to-grave
assessment. This means that the life cycle assessment (LCA) covers all stages of the
building’s life cycle, from the extraction of raw materials (cradle) to the disposal or reuse of
the building components at the end of their service life (grave)1. The LCA must include the
following life cycle stages: product stage, construction process stage, use stage, and endof-
life stage2. The LCA must also account for the environmental impacts of the building’s
structure and enclosure, as well as any other building elements that are permanently
attached to and share service systems with the building2.
Question 6Choose 1
Which of the following project types is required to consider the perimeter floor area instead
of the regularly occupied floor area under the Indoor Environmental Quality Credit, Daylight
calculations?
Show answerHide answer
Correct answer: CHealthcare
Explanation
Explanation:
Healthcare projects are required to consider the perimeter floor area instead of the
regularly occupied floor area under the Indoor Environmental Quality Credit, Daylight
calculations. This is because healthcare projects have different daylighting needs and
challenges than other project types, and the perimeter area is more likely to have access to
natural light and views. The perimeter floor area is defined as the regularly occupied
spaces within 15 feet (4.5 meters) of the exterior wall that meets the minimum glazing
requirements.
Question 7Choose 1
A Photovoltaic (PV) system was installed on a 35,000 ft2 (3 252 m2) project. What actions
need to take place in order to meet compliance for Energy and Atmosphere Prerequisite,
Fundamental Commissioning (Cx) and Verification?
Show answerHide answer
Correct answer: CThe Cx agent for the project must conduct or oversee the Cx of the PV system
Explanation
Explanation:
The correct answer is C, the Cx agent for the project must conduct or oversee the Cx of the
PV system. According to the LEED v4 Reference Guide for Building Design and
Construction, the Energy and Atmosphere Prerequisite, Fundamental Commissioning and
Verification, requires that all energy-related systems, including renewable energy systems
such as PV, be commissioned by an independent commissioning agent (CxA) or a qualified
member of the project team who reports to the owner. The CxA or the qualified team
member must perform or oversee all commissioning activities, including developing a
commissioning plan, reviewing design documents and submittals, verifying installation and
performance, and preparing a commissioning report12 References: 1: LEED v4 Reference
Guide for Building Design and Construction, Energy and Atmosphere Prerequisite:
Fundamental Commissioning and Verification, page 562. 2: LEED v4 Reference Guide for
Building Design and Construction, Glossary, page 1020.
Question 8Choose 1
A project in a cold climate does not want a highly reflective roof because they want the heat
absorption. How can this
project comply with Sustainable Sites Credit, Heat Island Reduction?
Show answerHide answer
Correct answer: BThe credit may be achieved by using nonroof measures only
Explanation
Explanation:
The credit may be achieved by using nonroof measures only, such as shading, paving, and
vegetation, to reduce the heat island effect on the site. The credit does not require a highly
reflective roof for all projects, but allows for flexibility and trade-offs depending on the
climate and design conditions. The project can use the Heat Island Reduction 1 to
demonstrate compliance with the credit requirements. The credit is feasible and applicable
for this project, and does not need an alternative compliance path. References: SS Credit
Heat Island Reduction, LEED v4 Reference Guide for Building Design and Construction234
Question 9Choose 1
What are the requirements of commercial projects for long-term bicycle storage under
Location and
Transportation, Bicycle Facilities - Bicycle Storage and Shower Rooms?
Show answerHide answer
Correct answer: BProvide for at least 10% of all regular building occupants, with no less than five storage
spaces per building
Explanation
Explanation: The correct answer is B. Provide for at least 10% of all regular building
occupants, with no less than five storage spaces per building.
According to the LEED v4.1 Bicycle Storage Requirements1, commercial projects must
provide long-term bicycle storage for at least 10% of all regular building occupants, with no
less than five storage spaces per building. Long-term bicycle storage is defined as secure,
enclosed, and weather-protected spaces that are intended for use by occupants who make
regular trips to the project building. Examples of long-term bicycle storage include lockers,
cages, rooms, or dedicated areas within buildings1. The purpose of this requirement is to
encourage the use of bicycles as a sustainable mode of transportation and reduce greenhouse gas emissions and fossil fuel consumption.
Question 10Choose 1
Which of the following products are eligible for a WaterSense label?
Show answerHide answer
Correct answer: DPrivate lavatory faucets
Explanation
Explanation: Private lavatory faucets are eligible for a WaterSense label, provided they
meet EPA’s specifications for water efficiency and performance, and are backed by
independent, third-party certification. Tankless toilets, waterless urinals, and public lavatory
faucets are not eligible for a WaterSense label because they are not included in the product
categories that WaterSense covers. WaterSense currently labels products in the following
categories: tank-type toilets, water-using urinals, private lavatory faucets, showerheads,
irrigation controllers, spray sprinkler bodies, and pre-rinse spray valves.
Full mock exam
Sit the LEED-AP-BD+C exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real LEED-AP-BD+C exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.