When preparing for an audit, which of the following statements is false?
Show answerHide answer
Correct answer: BThe audit checklists are shared and agreed with the auditee in advance of the audit
Question 72Choose 2
Which two of the following statements are true?
Show answerHide answer
Correct answer: D, EThe benefits of implementing an ISMS primarily result from a reduction in information
security risks.The purpose of an ISMS is to apply a risk management process for preserving
information security.
Question 73Choose 1
Scenario 7: Webvue. headquartered in Japan, is a technology company specializing in the development, support, and maintenance of computer software. Webvue provides solutions across various technology fields and business sectors. Its flagship service is CloudWebvue, a comprehensive cloud computing platform offering storage, networking, and virtual computing services. Designed for both businesses and individual users. CloudWebvue is known for its flexibility, scalability, and reliability.
Webvue has decided to only include CloudWebvue in its ISO/IEC 27001 certification scope. Thus, the stage 1 and 2 audits were performed simultaneously Webvue takes pride in its strictness regarding asset confidentiality They protect the information stored in CloudWebvue by using appropriate cryptographic controls. Every piece of information of any classification level, whether for internal use. restricted, or confidential, is first encrypted with a unique corresponding hash and then stored in the cloud
The audit team comprised five persons Keith. Sean. Layla, Sam. and Tina. Keith, the most experienced auditor on the IT and information security auditing team, was the audit team leader. His responsibilities included planning the audit and managing the audit team. Sean and Layla were experienced in project planning, business analysis, and IT systems (hardware and application) Their tasks included audit planning according to Webvue’s internal systems and processes Sam and Tina, on the other hand, who had recently completed their education, were responsible for completing the day-to-day tasks while developing their audit skills
While verifying conformity to control 8.24 Use of cryptography of ISO/IEC 27001 Annex A through interviews with the relevant staff, the audit team found out that the cryptographic keys have been initially generated based on random bit generator (RBG) and other best practices for the generation of the cryptographic keys. After checking Webvue's cryptography policy, they concluded that the information obtained by the interviews was true. However, the cryptographic keys are still in use because the policy does not address the use and lifetime of cryptographic keys.
As later agreed upon between Webvue and the certification body, the audit team opted to conduct a virtual audit specifically focused on verifying conformity to control 8.11 Data Masking of ISO/IEC 27001 within Webvue, aligning with the certification scope and audit objectives. They examined the processes involved in protecting data within CloudWebvue. focusing on how the company adhered to its policies and regulatory standards. As part of this process. Keith, the audit team leader, took screenshot copies of relevant documents and cryptographic key management procedures to document and analyze the effectiveness of Webvue's practices.
Webvue uses generated test data for testing purposes. However, as determined by both the interview with the manager of the QA Department and the procedures used by this department, sometimes live system data are used. In such scenarios, large amounts of data are generated while producing more accurate results. The test data is protected and controlled, as verified by the simulation of the encryption process performed by Webvue's personnel during the audit
While interviewing the manager of the QA Department, Keith observed that employees in the Security Training Department were not following proper procedures, even though this department fell outside the audit scope. Despite the exclusion in the audit scope, the non conformity in the Security Training Department has potential implications for the processes within the audit scope, specifically impacting data security and cryptographic practices in CloudWebvue. Therefore, Keith incorporated this finding into the audit report and accordingly informed the auditee.
Based on the scenario above, answer the following question:
Question:
Based on Scenario 7, which audit procedure was used to verify conformity to the use of test data?
Show answerHide answer
Correct answer: CTechnical verification
Question 74Choose 3
You are conducting a third-party surveillance audit when another member of the audit team
approaches you seeking clarification. They have been asked to assess the organisation's
application of control 5.7 - Threat Intelligence. They are aware that this is one of the new
controls introduced in the 2022 edition of ISO/IEC 27001, and they want to make sure they
audit the control correctly.
They have prepared a checklist to assist them with their audit and want you to confirm that
their planned activities are aligned with the control's requirements.
Which three of the following options represent valid audit trails?
Show answerHide answer
Correct answer: A, D, FI will review the organisation's threat intelligence process and will ensure that this is fully
documented
I will check that threat intelligence is actively used to protect the confidentiality, integrity
and availability of the organisation's information assets
I will determine whether internal and external sources of information are used in the
production of threat intelligence
Question 75Choose 1
Scenario 9: UpNet, a networking company, has been certified against ISO/IEC 27001. It
provides network security, virtualization, cloud computing, network hardware, network
management software, and networking technologies.
The company's recognition has increased drastically since gaining ISO/IEC 27001
certification. The certification confirmed the maturity of UpNefs operations and its
compliance with a widely recognized and accepted standard.
But not everything ended after the certification. UpNet continually reviewed and enhanced
its security controls and the overall effectiveness and efficiency of the ISMS by conducting
internal audits. The top management was not willing to employ a full-time team of internal
auditors, so they decided to outsource the internal audit function. This form of internal
audits ensured independence, objectivity, and that they had an advisory role about the
continual improvement of the ISMS.
Not long after the initial certification audit, the company created a new department
specialized in data and storage products. They offered routers and switches optimized for data centers and software-based networking devices, such as network virtualization and
network security appliances. This caused changes to the operations of the other
departments already covered in the ISMS certification scope.
Therefore. UpNet initiated a risk assessment process and an internal audit. Following the
internal audit result, the company confirmed the effectiveness and efficiency of the existing
and new processes and controls.
The top management decided to include the new department in the certification scope
since it complies with ISO/IEC 27001 requirements. UpNet announced that it is ISO/IEC
27001 certified and the certification scope encompasses the whole company.
One year after the initial certification audit, the certification body conducted another audit of
UpNefs ISMS. This audit aimed to determine the UpNefs ISMS fulfillment of specified
ISO/IEC 27001 requirements and ensure that the ISMS is being continually improved. The
audit team confirmed that the certified ISMS continues to fulfill the requirements of the standard. Nonetheless, the new department caused a significant
impact on governing the management system. Moreover, the certification body was not
informed about any changes. Thus, the UpNefs certification was suspended.
Based on the scenario above, answer the following question:
UpNet outsourced the internal audit function, as provided in scenario 9. Does it impact the
internal audit process?
Show answerHide answer
Correct answer: CYes, it increases the independence and impartiality of the internal audit because
auditors do not have operational roles related to the ISMS
Question 76Choose 1
Which situation presented below represents a threat?
Show answerHide answer
Correct answer: CHackers compromised the administrator's account by cracking the password
Question 77
Select the words that best complete the sentence below to describe audit resources:
Show answerHide answer
Explanation
Question 78Choose 4
You are an experienced ISMS audit team leader guiding an auditor in training. You are
testing her understanding of follow-up audits by asking her a series of questions to which
the answer is either "true* or 'false'. Which four of the following questions should the
answer be true"'
Show answerHide answer
Correct answer: A, B, C, FA follow-up audit may be carried out where nonconformities are major
A follow-up audit may be carried out where nonconformities are minor
The outcomes of a follow-up audit should be reported to top management and the audit team leader who carried out the audit where the nonconformities were initially identified
The outcomes of a follow-up audit should be reported to the individual managing the
audit programme and the audit client
Question 79Choose 1
Three auditors were assigned to conduct a certification audit in Company X. Before the
audit commenced, the certification body provided the auditors' names and background
information to Company X. Company X requested the replacement of one of the
auditors because they are a former employee. Is this acceptable?
Show answerHide answer
Correct answer: BNo, the auditee can request the replacement of the auditor only if a valid reason is
presented such as unprofessional conduct or situations with real conflict of interest
Question 80Choose 2
Which two of the following actions are the individual(s) managing the audit programme
responsible for?
Show answerHide answer
Correct answer: A, DDetermining the resources necessary for the audit programme
Keping informed the accreditation body on the progress of the audit programme
Full mock exam
Sit the ISO-IEC-27001-Lead-Auditor exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real ISO-IEC-27001-Lead-Auditor exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.