Question 41 Choose 1
A process capability study would be necessary in a laboratory when:
Show answerHide answer

Correct answer: B frequent failures are occurring.

Explanation

Explanation: A process capability study is a method of evaluating how well a process can produce outputs that meet the specifications or requirements. A process capability study involves collecting data from a sample of the process output, calculating the process mean and standard deviation, and comparing them with the specification limits1. A process capability study can help identify the sources and causes of variation, measure the performance and quality of the process, and determine the potential for improvement2. A process capability study would be necessary in a laboratory when frequent failures are occurring. Frequent failures indicate that the process is not capable of producing reliable and consistent results, and that there may be some problems or defects in the process. A process capability study can help diagnose the issues and suggest corrective actions to reduce or eliminate the failures. For example, a laboratory that performs blood tests may conduct a process capability study to find out why some of the test results are inaccurate or invalid, and what factors affect the accuracy and validity of the test results.
The other options are not situations that would require a process capability study, because they are either unrelated or irrelevant to the process performance or quality. A test results are consistently late (A) is a problem of timeliness, not capability. A new technician is hired © is a change of personnel, not process. Hours of operation are to be extended (D) is a change of schedule, not process.

References:
Process Capability Analysis Cp, Cpk, Pp, Ppk - A Guide - 1factory What is Process Capability? Capability Estimates & Studies | ASQ
Question 42 Choose 1
Which of the following situations is most likely to occur when using a push system?
Show answerHide answer

Correct answer: A Work centers receive work even if capacity is not available.

Explanation

Explanation: A push system is a production system that operates based on planned or forecasted demand, rather than actual or current demand. In a push system, work orders or tasks are released to the work centers according to a predetermined schedule, regardless of the availability of capacity or resources at the work centers. This means that work centers may receive work even if they are already overloaded or have no idle time, which can result in long lead times, high inventory levels, and poor customer service1.

The other options are more likely to occur when using a pull system, which is a production system that operates based on actual or current demand, rather than planned or forecasted demand. In a pull system, work orders or tasks are released to the work centers only when there is a need or a request from the downstream work centers or customers. This means that work centers are scheduled using finite capacity planning, which is a method of allocating capacity and resources based on the actual availability and constraints of the work centers2. Work centers also operate using decentralized control, which means that each work center has the autonomy and authority to make decisions based on the local conditions and signals from the environment3. Work centers also signal previous work centers when they are ready for more work, which is a way of synchronizing the flow of materials and information along the production process4.

References: Push System vs. Pull System: Adopting A Hybrid Approach To MRP; Push Systems vs. Pull System: Definitions and Differences; JUST-IN-TIME MANUFACTURING | SpringerLink; 9 Just-In-Time and Lean Systems - Seneca College.
Question 43 Choose 1
Which of the following outcomes is a benefit of mixed-model scheduling?
Show answerHide answer

Correct answer: B Improved demand response

Explanation

Explanation: Mixed-model scheduling is a production technique that allows for the simultaneous production of different products or features on the same production line or system. Mixed-model scheduling can help reduce lead times, inventory levels, setup times, and material shortages by increasing the flexibility and responsiveness of the production process. One of the benefits of mixed-model scheduling is improved demand response, which means the ability to meet customer demand without delay or stockout. Improved demand response can enhance customer satisfaction and loyalty, as well as reduce the need for safety stock or buffer inventory. By using mixed-model scheduling, a company can produce products or features according to the actual or forecasted customer demand, rather than producing large batches of standardized products or features. This can help avoid overproduction or underproduction, which can result in excess inventory or lost sales.
Mixed-model scheduling can also help adjust the production output quickly and easily when there are changes or fluctuations in demand, by using flexible automation, lean production techniques, or quick response methods.

The other options are not benefits of mixed-model scheduling. Increased inventory is not a benefit of mixed-model scheduling, but rather a drawback. Increased inventory can increase inventory costs, such as holding costs, transportation costs, or obsolescence costs. It can also reduce inventory visibility and control, as well as increase the risk of quality issues or spoilage. Mixed-model scheduling can help reduce inventory by producing products or features in small batches or single units that match customer demand. Fewer setups are not a benefit of mixed-model scheduling, but rather a requirement. Fewer setups mean less time and resources spent on changing or adjusting the production system to produce different products or features. Fewer setups can increase the efficiency and productivity of the production process, as well as reduce the setup costs and waste. Mixed-model scheduling requires fewer setups to enable the simultaneous production of different products or features on the same production line or system. Fewer material shortages are not a benefit of mixed-model scheduling, but rather an outcome. Fewer material shortages mean less disruption or delay in the production process due to the lack of materials or components needed for production. Fewer material shortages can improve the quality and reliability of the production process, as well as reduce the material costs and waste. Mixed-model scheduling can result in fewermaterial shortages by reducing the lead times and inventory levels of materials or components, as well as by improving the communication and coordination with suppliers.

References := Mixed Model Scheduling - Mountain Home Academy, Reduce Lot Sizes, Mixed Model Scheduling - Academic library, Introduction To Mixed Model Production …{Strategos}
Question 44 Choose 1
Manufacturing flexibility can be measured by using:
Show answerHide answer

Correct answer: C changeover time.

Explanation

Explanation: Manufacturing flexibility can be measured by using changeover time. Changeover time is the time it takes to go from the last good part of one product run to the first good part of the next product run1. Manufacturing flexibility is the ability of a system to handle a range of products or variants with fast setups2. By using changeover time as a measure of manufacturing flexibility, we can assess how quickly and efficiently a system can switch from one product to another, and how well it can respond to changes in customer demand, product mix, quality standards, and delivery schedules3.
Some of the benefits of reducing changeover time and increasing manufacturing flexibility are4:
Lower manufacturing costs: More value-added capacity can be unlocked because the equipment is idle for less time.
Higher customer satisfaction: Customers can get their products faster and with more variety.
Greater competitive advantage: The system can adapt to market changes and offer more customized products or services.
Improved quality and productivity: The system can avoid defects, waste, and errors that may occur during long or complex changeovers.
Some of the methods or tools that can help reduce changeover time and increase manufacturing flexibility are5:
Single-minute exchange of die (SMED): A technique that aims to reduce changeover time to less than 10 minutes by converting internal setup activities (those that can only be done when the machine is stopped) to external setup activities (those that can be done while the machine is running), and streamlining both types of activities.
Total productive maintenance (TPM): A technique that involves maintaining and improving the equipment performance and reliability by involving all employees in preventive maintenance, autonomous maintenance, focused improvement, and quality management.
Quick response manufacturing (QRM): A technique that focuses on reducing lead times throughout the entire organization by applying the principles of time-based competition, cellular manufacturing, system dynamics, and enterprise-wide application.
Therefore, changeover time is a measure that can be used to evaluate the manufacturing flexibility of a system.

References: 1: What is Changeover? (Lean terminology) - Velaction 5 2: FLEXIBILITY IN MANUFACTURING | SpringerLink 3 3: How to Reduce Changeover Time - MachineMetrics 6 4: The Tradeoff Between Inventory Costs And Transportation Costs 5: Changeover [Manufacturing Definition] | Creative Safety Supply
Question 45 Choose 1
Compared to traditional supplier relationships, a more strategic view of supplier relationships would require:
Show answerHide answer

Correct answer: A maintaining communication based on trust.

Explanation

Explanation: Compared to traditional supplier relationships, a more strategic view of supplier relationships would require maintaining communication based on trust. Trust is a key factor that enables effective collaboration, information sharing, problem solving, and innovation between supply chain partners12. Trust can also reduce transaction costs, conflicts, and opportunism, and increase commitment, loyalty, and performance34.
Therefore, maintaining communication based on trust is essential for developing and sustaining strategic supplier relationships that can create value and competitive advantage for both parties.
The other options are not necessarily required for a more strategic view of supplier relationships, because they are either insufficient or irrelevant. Offering the supplier more business may increase the volume or frequency of transactions, but it does not guarantee a more strategic or long-term relationship. Adopting electronic data interchange (EDI) may improve the efficiency or accuracy of information exchange, but it does not ensure a more collaborative or innovative relationship. Implementing concurrent engineering may enhance the product design or development process, but it does not address the other aspects of a strategic relationship, such as quality, delivery, or risk management.

That's the last free question

You've seen the free 30% (45 of 151 questions). Full access unlocks every question and full-length CPIM-Part-2 mock exams (65 questions, 105 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the CPIM-Part-2 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CPIM-Part-2 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CPIM-Part-2 mock exam
  • 65questions per mock
  • 105 mintime limit
  • 151questions in the bank
  • Newmock on every attempt