Question 21 Choose 1
An important benefit of an effective work cell layout is:
Show answerHide answer

Correct answer: B improved space utilization.

Explanation

Explanation: A work cell layout is a type of process layout that arranges equipment and workers according to the sequence of operations performed on a product or service. A work cell layout can improve space utilization by reducing the amount of floor space needed for production, eliminating unnecessary material handling and storage, and increasing the flexibility of the layout. A work cell layout can also reduce cycle time, improve quality, and enhance worker motivation.

References: CPIM Exam Content Manual
Version 7.0, Domain 6: Plan, Manage, and Execute Detailed Schedules, Section 6.2:
Implement Detailed Schedules, Subsection 6.2.3: Describe the principles of work center design and layout (page 58).
Question 22 Choose 1
When deciding what to report externally regarding sustainability performance, a company should disclose:
Show answerHide answer

Correct answer: C past results and future strategies.

Explanation

Explanation: When deciding what to report externally regarding sustainability performance, a company should disclose its past results and future strategies. This will help the company to demonstrate its progress, achievements, challenges, and commitments in relation to its environmental, social, and governance (ESG) goals. Disclosing past results and future strategies will also enhance the company’s transparency, accountability, and credibility with its stakeholders, such as investors, customers, employees, regulators, and the public.

Disclosing results of poor performance or acceptable performance alone is not sufficient, as it does not provide a complete picture of the company’s sustainability performance. Moreover, disclosing only poor performance may damage the company’s reputation and trust, while disclosing onlyacceptable performance may raise doubts about the company’s honesty and reliability. Disclosing why current regulations are too costly is irrelevant and inappropriate, as it does not reflect the company’s sustainability performance or efforts. It may also imply that the company is not willing or able to comply with the regulations or improve its sustainability practices.

References : A Comprehensive Guide on How to Write a Sustainability Report; Designing Your Company’s Sustainability Report; What to Include in a Sustainability Report.
Question 23 Choose 1
Long lead-time items with stable demand would best be supported by a supply chain:
Show answerHide answer

Correct answer: D positioning inventory close to the consumer.

Explanation

Explanation: Long lead-time items are items that take a long time to procure, produce, or deliver. Stable demand means that the demand for these items is predictable and does not fluctuate much over time. A supply chain that supports long lead-time items with stable demand would best be designed to position inventory close to the consumer, because this would reduce the delivery time and improve the customer service level. Positioning inventory close to the consumer also reduces the transportation costs and risks associated with long-distance shipments. A supply chain that uses a pull system, which is based on actual customer orders rather than forecasts, may not be suitable for long lead-time items, because it may not be able to meet the customer demand in a timely manner. A supply chain that is linked through an enterprise resources planning (ERP) system, which is a software system that integrates various business functions and processes, may improve the visibility and coordination of the supply chain, but it does not necessarily reduce the lead time or position inventory close to the consumer. A supply chain that is designed to be responsive, which means that it can quickly adapt to changes in demand or other variables, may not be necessary for long lead-time items with stable demand, because these items have low demand uncertainty and variability.

References:
Inventory Positioning | Supply Chain Resource Cooperative
Push System vs. Pull System: Adopting A Hybrid Approach To MRP
What Is Inventory Positioning in Supply Chain Management?
Question 24 Choose 1
A machine is suddenly having excessive downtime. Which of the following tools would be used in a root cause correctiveaction process to determine the problem?
Show answerHide answer

Correct answer: D A3 method

Explanation

Explanation: A3 method is a tool that can be used in a root cause corrective action process to determine the problem of a machine that is suddenly having excessive downtime. A3 method is a structured problem-solving approach that follows the Plan-Do- Check-Act (PDCA) cycle and uses a single sheet of paper (A3 size) to document the problem, analysis, countermeasures, and results1. A3 method can help identify the root cause of a problem by using tools such as the 5 Whys or the fishbone diagram, and then develop and implement effective corrective actions to prevent recurrence2. A3 method can also help communicate the problem and the solution to stakeholders, as well as monitor and evaluate the outcomes3.

The steps of the A3 method are4:
Step 1: Define the problem and its impact. Describe the current situation, the gap between the actual and the desired state, and the scope and magnitude of the problem.
Step 2: Identify the root cause of the problem. Use tools such as the 5 Whys or the fishbone diagram to analyze the factors that contribute to the problem and drill down to its root cause.
Step 3: Propose countermeasures to address the root cause. Generate possible solutions that can eliminate or reduce the root cause, and evaluate their feasibility, effectiveness, and costs.
Step 4: Implement countermeasures. Select the best solution and plan how to execute it. Define the roles, responsibilities, resources, timeline, and expected outcomes of the implementation.
Step 5: Check results and process. Measure and compare the results before and after the implementation, and verify if the problem has been solved or improved.
Also check if the process has been followed correctly and document any deviations or issues.
Step 6: Standardize successful processes or identify unresolved issues. If the results are satisfactory, standardize the new process and ensure that it is sustained. If not, identify the remaining or new issues and repeat the A3 method.
Therefore, A3 method is a tool that can be used in a root cause corrective action process to determine the problem of a machine that is suddenly having excessive downtime.

References: 1: What is an A31 2: How to Use an A3 Report for Problem Solving 2 3: The A3 Problem Solving Method 4 4: The A3 Report – A Simple Tool for Complex Problems 5
Question 25 Choose 1
Which of the following forms of data is required for rough-cut capacity planning (RCCF)?
Show answerHide answer

Correct answer: C Critical work center availability

Explanation

Explanation: Rough-cut capacity planning (RCCP) is a long-term capacity planning technique that validates the master production schedule (MPS) by comparing the required capacity and the available capacity of critical resources. Critical resources are those that have the most impact on the production process, such as machines, labor, or materials.
RCCP helps to identify any potential imbalances or bottlenecks in the production system and to adjust the MPS or the resource availability accordingly.
To perform RCCP, one of the forms of data that is required is critical work center availability. A work center is a location where one or more resources perform a specific operation or a group of operations. A critical work center is a work center that has a high utilization rate, a low flexibility, or a high influence on the production output. Critical work center availability is the amount of time or capacity that a critical work center can offer for production activities. Critical work center availability can be affected by factors such as shifts, holidays, maintenance, breakdowns, or setups. RCCP uses critical work center availability to determine whether there is enough capacity to meet the planned production. Current work in process (WIP) is not a form of data that is required for RCCP. WIP is the inventory of partially finished goods that are waiting for further processing or assembly.
WIP is not relevant for RCCP, as RCCP focuses on the future demand and capacity, not the current inventory status.
Resource requirements plan is not a form of data that is required for RCCP. Resource requirements plan is the output of RCCP, not the input. Resource requirements plan is a report that shows the projected load and capacity of each critical resource over a planning horizon. Resource requirements plan can help to identify any gaps or surpluses in capacity and to take corrective actions.
Work center queues are not a form of data that is required for RCCP. Work center queues are the waiting lines of jobs or orders at a work center. Work center queues are an indicator of short-term capacity issues, such as delays, backlogs, or congestion. Work center queues are not relevant for RCCP, as RCCP focuses on the long-term capacity planning, not the short-term scheduling.

References := Guide to Rough-Cut Capacity Planning | Smartsheet, Guide to Rough Cut Capacity Planning - Definition and Example, ROUGH-CUT CAPACITY PLANNING - Operations Management: An Integrated …, Rough-cut Capacity Planning - Infor Documentation Central
Question 26 Choose 1
The approved output of the distribution requirements planning (DRP) process is an input to which of the following planningprocesses?
Show answerHide answer

Correct answer: C Master production 0

Explanation

Explanation: The approved output of the distribution requirements planning (DRP) process is an input to the master production planning (MPS) process. The DRP process determines the quantity and timing of finished goods to be delivered to each distribution center or warehouse to meet customer demand1. The output of the DRP process is a distribution schedule that specifies the planned delivery dates and quantities of products2. The distribution schedule is then used as an input to the MPS process, which determines the quantity and timing of end items to be produced at each manufacturing facility3. The MPS process balances the demand from the distribution schedule with the available capacity and resources of the production system3. The output of the MPS process is a master production schedule that specifies the planned production dates and quantities of end items3.

References: CPIM Part 2 Exam Content Manual, Domain 4: Plan and Manage Supply, Section 4.1: Supply Management Concepts and Tools, p. 33-34.
Question 27 Choose 1
The production plan relates to a firm's financial planning because it is used to:
Show answerHide answer

Correct answer: D identify future cash needs.

Explanation

Explanation: The production plan is a statement of the resources needed to meet the aggregate demand plan over a medium-term horizon. The production plan is the output of the supply planning step in the sales and operations planning (S&OP) process. The production plan relates to a firm’s financial planning because it is used to identify future cash needs. Cash needs are the amount of money that a firm requires to operate and grow its business. Cash needs can be influenced by various factors, such as sales revenue, cost of goods sold, operating expenses, capital expenditures, inventory levels, accounts receivable, accounts payable, and taxes. The production plan can help to estimate the cash inflows and outflows associated with these factors, and to determine the optimal balance between them. The production plan can also help to identify the potential sources and uses of cash, such as borrowing, investing, or paying dividends. By identifying future cash needs, the production plan can help to improve the firm’s liquidity, profitability, and solvency.

References: CPIM Exam Content Manual Version 7.0, Domain 4: Plan and Manage Supply, Section 4.1: Develop Supply Plans, Subsection 4.1.2: Describe how to develop a production plan (page 36).
Question 28 Choose 1
An advantage of activity-based costing (ABC) is:
Show answerHide answer

Correct answer: B it uses cost drivers to allocate costs to products.

Explanation

Explanation: Activity-based costing (ABC) is a method of allocating costs to products or services based on the activities that consume resources in the production or delivery process. ABC identifies the cost drivers, which are the factors that cause or influence the amount of resources used for each activity. ABC then assigns costs to products or services based on the amount of cost drivers they use. An advantage of ABC is that it uses cost drivers to allocate costs to products, which provides a more accurate and realistic picture of the cost structure and profitability of each product or service. ABC helps to identify the value-added and non-value-added activities, and to eliminate or reduce the waste and inefficiency in the process. ABC does not allow raw material costs to be allocated on a per unit basis, as raw material costs are usually considered as direct costs that can be traced to each product or service. ABC does not make it easier to establish standard costs, which are the predetermined or expected costs of producing or delivering a product or service.
ABC does not enable overhead costs to be allocated evenly across all products, as overhead costs are the indirect costs that cannot be traced to each product or service. ABC allocates overhead costs based on the cost drivers, which may vary for different products or services. References: CPIM Exam Content Manual Version 7.0, Domain 8: Manage Quality, Continuous Improvement, and Technology, Section 8.2: Continuous Improvement Concepts, p. 46; Activity-Based Costing (ABC) Definition; Activity-based costing.
Question 29 Choose 1
Given the information below, reducing which measure by 10% would contribute most to shortening the cash-to-cash cycletime?
Show answerHide answer

Correct answer: A Accounts receivable

Explanation

Explanation: The cash-to-cash cycle time is a financial metric that measures the time it takes for a company to convert its cash outflows into cash inflows. The cash-to-cash cycle time is calculated by adding the days of inventory outstanding (DIO), the days of sales outstanding (DSO), and the days of payablesoutstanding (DPO), and then subtracting the days of payables deferred (DPD). The cash-to-cash cycle time can be shortened by reducing any of the components, except for DPD, which should be increased. Reducing which measure by 10% would contribute most to shortening the cash-to-cash cycle time depends on the relative values of each component.
Question 30 Choose 1
Marketing has requested a significant change in the mix for a product family. The requested change falls between thedemand and the planning time fences. The most appropriate action by the master scheduler is to:
Show answerHide answer

Correct answer: C forward the request to senior management.

Explanation

Explanation: The most appropriate action by the master scheduler is to forward the request to senior management. According to the Time Fence Control (MRP and Supply Chain Planning Help) - Oracle, the demand time fence is a period within which the planning process does not consider forecast demand when calculating actual demand, and the planning time fence is a period within which the planning process does not alter the current material plan or master schedule. The master scheduler can make changes to the master schedule within the planning time fence, but only with approval from senior management.
The request from marketing falls between the demand and the planning time fences, which means that it may affect the current material plan or master schedule, as well as the capacity and resource requirements of the production system. Therefore, the master scheduler should forward the request to senior management, who can evaluate the impact and feasibility of the request, and decide whether to approve or reject it.
Full mock exam

Sit the CPIM-Part-2 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real CPIM-Part-2 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full CPIM-Part-2 mock exam
  • 65questions per mock
  • 105 mintime limit
  • 151questions in the bank
  • Newmock on every attempt