Correct answer: A
Risk Acceptance
Explanation
A deviation from an organization-wide security policy requires you to manage
the risk. If you deviate from the security policy then you are required to accept the risks that
might occur.
In some cases, it may be prudent for an organization to simply accept the risk that is
presented in certain scenarios. Risk acceptance is the practice of accepting certain risk(s),
typically based on a business decision that may also weigh the cost versus the benefit of
dealing with the risk in another way.
The OIG defines Risk Management as: This term characterizes the overall process.
The first phase of risk assessment includes identifying risks, risk-reducing measures, and
the budgetary impact of implementing decisions related to the acceptance, avoidance, or
transfer of risk.The second phase of risk management includes the process of assigning priority to,
budgeting, implementing, and maintaining appropriate risk-reducing measures.
Risk management is a continuous process of ever-increasing complexity. It is how we
evaluate the impact of exposures and respond to them. Risk management minimizes loss
to information assets due to undesirable events through identification, measurement, and
control. It encompasses the overall security review, risk analysis, selection and evaluation
of safeguards, cost–benefit analysis, management decision, and safeguard identification
and implementation, along with ongoing effectiveness review.
Risk management provides a mechanism to the organization to ensure that executive
management knows current risks, and informed decisions can be made to use one of the
risk management principles: risk avoidance, risk transfer, risk mitigation, or risk
acceptance.
The 4 ways of dealing with risks are: Avoidance, Transfer, Mitigation, Acceptance
The following answers are incorrect:
Risk assignment. Is incorrect because it is a distractor, assignment is not one of the ways
to manage risk.
Risk reduction. Is incorrect because there was a deviation of the security policy. You could
have some additional exposure by the fact that you deviated from the policy.
Risk containment. Is incorrect because it is a distractor, containment is not one of the ways
to manage risk.
Reference(s) used for this question:
Hernandez CISSP, Steven (2012-12-21). Official (ISC)2 Guide to the CISSP CBK, Third
Edition ((ISC)2 Press) (Kindle Locations 8882-8886). Auerbach Publications. Kindle
Edition.
and
Hernandez CISSP, Steven (2012-12-21). Official (ISC)2 Guide to the CISSP CBK, Third
Edition ((ISC)2 Press) (Kindle Locations 10206-10208). Auerbach Publications. Kindle
Edition.