Question 31 Choose 1

What plan is created, and submitted for approval, during the Managing a Stage Boundary
process?

Show answerHide answer

Correct answer: B

Stage Plan

Question 32 Choose 1

Identify the missing word(s) in the following sentence. The Quality theme provides a set of
rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

Show answerHide answer

Correct answer: B

products

Question 33 Choose 1

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ]
with a Team Manager.

Show answerHide answer

Correct answer: C

Work Package cost tolerance

Question 34 Choose 1

Which is a purpose of the Risk Register?

Show answerHide answer

Correct answer: B

  Act as a central record of information relating to the identified risks for the project

Question 35 Choose 1

Which is an objective of the Starting up a Project process?

Show answerHide answer

Correct answer: A

Identify who will be responsible for creating the Project Plan

Question 36 Choose 1

Which is a purpose of the Starting up a Project process?

Show answerHide answer

Correct answer: A

Provide information so a decision can be made as to whether a project is viable and
worthwhile to initiate

Question 37 Choose 1

Which of the following refers to the actions identified to bring a situation to a level where
exposure to a risk is acceptable?

Show answerHide answer

Correct answer: C

 Risk response

Question 38 Choose 1

Which describes risk probability?

Show answerHide answer

Correct answer: D

 A measure of the likelihood of the risk occurring

Question 39 Choose 1

Which process provides the Project Board with sufficient information for it to review the
success of a completed stage and confirm continued business justification?

Show answerHide answer

Correct answer: D

 Managing a Stage Boundary

Question 40 Choose 1

Which describes a risk event?

Show answerHide answer

Correct answer: A

The area of uncertainty in terms of the threat or opportunity

Full mock exam

Sit the PRINCE2 Foundation exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PRINCE2 Foundation exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PRINCE2 Foundation mock exam
  • 65questions per mock
  • 105 mintime limit
  • 150questions in the bank
  • Newmock on every attempt