Question 11 Choose 1

Scenario: Mobile Telco
Please read this scenario prior to answering the Question.
Mobile Telco is a mobile telecommunications company formed through a series of mergers and
acquisitions. They are yet to fully integrate the customer service systems for the most recent
acquisitions, and as result, customer service has been a major concern for the Chief Technology
Officer. Results for the last two quarters have shown that Average Revenue Per User (ARPU) and
the customer retention (Churn) rate have fallen below the industry average.
The Corporate Marketing group has published some new findings about customer satisfaction.
The customers appear to be switching to AirLight, a competitor, because of superior customer
service. Mobile Telco actually has better coverage in nearly all markets than AirLight, and good
roaming agreements that keep rates low for business travelers. But, customer satisfaction has
remained low. The Business Strategy group and the Enterprise Architecture group have
conducted a high-level project to develop the enterprise-wide strategic plan.
They have developed a business scenario which contains a good conceptual model of what needs
to be done, and also identifies the key requirements. This was used in preparing the proposal
presented to the Executive Council and the Corporate Board. The planning for the program has
been underway for several months. Mobile Telco has selected TOGAF 9 as the basis for its
Enterprise Architecture. The Corporate Board has approved funding for a multi-million Euro
conversion to transition to a packaged Customer Service System. It is anticipated that the overall
program will take five years to complete, but there are some tactical projects that can commence
immediately to address the situation.
The Executive Council has stated that the program should define specific initiatives to enable each
regional business unit to create an implementation of the Customer Service System. The
implementation must meet the needs of the business unit and still provide the information needed
to enable major improvements to the customer.
Refer to the Mobile Telco Scenario
You are serving as the Lead Architect for the Performance and Integrity project of the Customer
Service System program.
The project has been chartered to address the architecture(s) required to support the Customer
Service System from an infrastructure perspective. At the present time, the project team is
conducting an architecture development project that is focused on the customer self-service
capability, which was defined as part of the earlier strategic planning activities. This capability will
enable customers to access their accounts, pay bills, request account reviews, and provision
services from any web-enabled device.
The project team has gathered information about the self-service capability, developed a business
scenario, and used the results to define an Architecture Vision for achieving the capability.
You have been asked to recommend the course of action to complete the project.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: D

The remaining architecture definition work should be focused en mapping out the technology
and infrastructure capability in the Technology domain. In Phases E and F, the capability should
be broken down into a set of Solution Building Blocks that will be implemented to realize the
Target Architecture.
The Solution Building Blocks will provide the basis for the completed Architecture Definition
Document that will be submitted for approval. Upon approval, the implementation team will
conduct Compliance Assessments to ensure that the self-service capability is compliant with the
overall Enterprise Architecture

Question 12 Choose 1

Scenario: Reveille Bugle
Please read this scenario prior to answering the question
For over 100 years, Reveille Bugle has been manufacturing brass bugles and other musical
instruments. North America has been the primary market for Reveilles products. However, the
firm has now expanded into European markets and will soon establish a market in Latin America.
A future expansion into the Asia Pacific region is also planned.
The firm is organized into several business units that each focus on manufacturing particular
families of instruments such as brass, woodwind, and percussion. Each business unit has
acquired other producers to create its manufacturing capacity. This has resulted in a complex
environment with a high diversity of business and manufacturing systems.
The Enterprise Architecture (EA) program at Reveille Bugle has been functioning for several
years. It has made significant progress in consolidating the technology portfolio and establishing
key standards. The CIO and the COO are joint sponsors of the EA program. By all measures, the
EA program is mature, with an active Architecture Board and a well-defined architecture process
and standard content templates based on the TOGAF 9 Architecture Content Framework. The EA
process framework is well coordinated with the PMO, Systems Development, and Operations
functions.
The firm has completed a strategic plan to reorganize its Sales & Marketing organization
according to four geographic market sectors: North America; Europe, Africa, and Middle East;
Latin America; and Asia-Pacific. One of the goals of this reorganization is to improve the ability of
Marketing to collect more meaningful market analytics that will enable each sector to better
address market needs with effective marketing campaigns and global product presence.
A Request for Architecture Work has been approved. As the architecture team commences its
work, the CIO has expressed a concern about whether the firm will be able to adapt to the
proposed architecture and how to manage the associated risks.
Refer to the Reveille Bugle Scenario
Your role is consultant to the Lead Architect.
You have been asked how to address the concerns of the CIO.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: C

In Phase A the team should analyze their risk by completing an Implementation Factor
Assessment and Deduction Matrix to identify the particular risks associated with the
implementation and deployment. These factors can then used to assess the initial risks associated
with the proposed architecture.

Question 13 Choose 1

Scenario: Global Traders Inc.
Please read this scenario prior to answering the question
Global Traders is a large, global commodities trading company which has been growing rapidly
through a series of acquisitions. Each new business is performing well in its markets. However,
the lack of integration between headquarters and the business units has increasingly caused
problems in the handling of customer and financial information. The inability to share information
across businesses has resulted in lost opportunities to "leverage the synergies" that had been
intended when the businesses were acquired. At present, each business unit maintains its own
applications. Despite an earlier initiative to install a common application to manage customer,
products, supplier, and inventory information, each business unit has different ways of defining
each of these core elements and has customized the common application to the point where the
ability to exchange information is difficult, costly, and error-prone.
As a result, Global Traders has begun implementing a single Enterprise Resource Planning (ERP)
system to consolidate information from several applications that exist across the lines of business.
The Corporate Board is concerned that the new ERP system must be able to manage and
safeguard customer information in a manner that meets or exceeds the legal requirements of the
countries in which the company operates. This will be an increasingly important capability as the
company expands its online services offered to clients and trading partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its
charter is to coordinate efforts between the ERP implementation team and the business unit
personnel who will be involved in the migration process. The CIO has also formed a crossfunctional
Architecture Review Board to oversee and govern the architecture.
After reviewing the available alternatives, and based on recommendations from the ERP vendor,
Global Traders has selected TOGAF 9 as the basis for its Enterprise Architecture program. The
CIO has endorsed this choice with the full support of top management.
Refer to the Global Traders Inc. Scenario
You are serving as the Chief Architect.
As part of the process for establishing the Enterprise Architecture department, you have decided
to create a set of principles to guide the activities.
You have been asked to recommend the best approach for this work.
Based on TOGAF 9, which of the following is the best answer

Show answerHide answer

Correct answer: B

You examine the mission statements for Global Traders and each of its businesses, together
with the corporate value statements. Based on that, you work with the Architecture Review Board
to define the principles.
When developing the principles you ensure that they actively promote the alignment of IT with the
Global Traders business strategies. You then run a series of reviews with all the relevant
stakeholders, including senior management, ensuring their support.

Question 14 Choose 1

Scenario: Mansfield Bearing
Please read this scenario prior to answering the question
Mansfield Bearing Inc. manufactures ball bearings used in industrial equipment applications. They
have manufacturing operations in several cities in the United States, Germany, and the United
Kingdom.
The firm has traditionally allowed each manufacturing plant to drive its own production planning
systems. Each plant has its own custom Materials Requirements Planning, Master Production
Scheduling, Bill of Materials, and Shop Floor Control systems. Mansfield employs "Just In Time"
techniques to minimize wastes caused by excessive inventory and work in process. The
increasingly competitive business environment has compelled the firm to improve its business
capability to be more responsive to the needs of industrial customers. To support this capability,
the firm has decided to implement an Enterprise Resource Planning (ERP) solution that will enable
Mansfield to better coordinate its manufacturing capacity to match the demands for its products
across all plants. In addition, there are also new European regulations coming into force to which
their manufacturing processes must conform in the next six months.
As part of the implementation process, the Enterprise Architecture (EA) department has begun to
implement an architecture process based on TOGAF 9. The CIO is the sponsor of the activity. The
Chief Architect has directed that the program should include formal modeling using the
Architecture Content Framework and the TOGAF Content Metamodel. This will enable support for
the architecture tooling that Mansfield utilizes for its EA program.
The Chief Architect has stated that in order to model the manufacturing process it will be
necessary to model processes that are event-driven. Also, in order to consolidate applications
across several data centers it will be necessary to model the location of IT services. In particular,
the end goal is to have the single ERP application running in a single data center. Currently the
project is in the Preliminary Phase, and the architects are tailoring the Architecture Development
Method (ADM) and Architecture Content Framework to fit into the Mansfield Bearing environment.
Refer to the Global Traders Inc. Scenario
You are serving as the Chief Architect.
As part of the process for establishing the Enterprise Architecture department, you have decided
to create a set of principles to guide the activities.
You have been asked to recommend the best approach for this work.
Based on TOGAF 9, which of the following is the best answer?
Refer to the Mansfield Bearing Scenario
Your role is the Lead Architect.
You have been asked to recommend a response to the Chief Architects request to tailor the
TOGAF Content Metamodel.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: B

You recommend that the architecture team incorporate the Process Modeling and Governance
extensions into their tailored Content Metamodel. This is suitable as this is a significant IT change
that will impact its operational governance models. This will ensure that they include specific
entities and attributes that will allow them to model the event-driven nature of the manufacturing
processes more precisely

Question 15 Choose 1

Scenario:
Please read this scenario prior to answering the question
Your role is consultant to the Lead Architect within a company that manufactures a variety of small
electromechanical devices. As part of a corporate-wide Lean Manufacturing initiative, the company
has defined a strategic architecture to improve its ability to meet consumer demand and improve
its ability to manage its supply chain. The strategic architecture called for the consolidation of
multiple Enterprise Resource Planning (ERP) applications that have been operating independently
in several of the divisions production facilities. The goal is to replace the functionality of the
existing applications with a new ERP product running as a single instance in the companys
primary data center.
The company has a mature enterprise architecture practice and uses TOGAF 9 for the basis of its
architecture framework. In addition to the EA program, the company has a number of
management frameworks in use, including business planning, portfolio/project management, and
operations management. The EA program is sponsored by the CIO.
Each division has completed the Architecture Definition documentation required to tailor and
configure the environment to meet its own specific manufacturing requirements.
The enterprise architects have analyzed the key corporate change attributes and implementation
constraints. A consolidated gap analysis has been completed which has identified the gaps across
the Business, Data, Application, and Technology domains. Based on the results of the gap
analysis, the architects have reviewed the requirements, dependencies and interoperability
requirements needed to integrate the new ERP environment into the existing environment. The
architects have completed the Business Transformation Readiness Assessment started in Phase
A. Based on all of these factors they have produced a risk assessment.
Because of the risks posed by the complexity of the current environment, it has been determined
that a phased approach is needed to implement the target architectures. The overall
implementation process is estimated to take several years.
Refer to the Scenario
The Implementation and Migration Plan v0.l, the draft Architecture Roadmap, and the Capability
Assessment deliverables are now complete. You have been asked to recommend the next steps
to prepare the final Implementation and Migration Plan.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: A

You would apply the Business Value Assessment Technique to prioritize the implementation
projects and project increments. The assessment should focus on return on investment and
performance evaluation criteria that can be used to monitor the progress of the architecture
transformation. You would confirm the Transition Architecture phases using an Architecture
Definition Increments Table to list the projects. You would then document the lessons learned and
generate the final plan

Explanation

Explanation: Business Value Technique usually follows BTRA, and will fufil the requirement to
phase approach by prioritizing projects and listing their execution using ADI table.

Question 16 Choose 1

Scenario:
Please read this scenario prior to answering the Question
You are serving as the Lead Architect for the enterprise architecture team at the prime contractor
for the Dreadnought Unmanned Aircraft System program.
Over the course of this contract, the company has grown rapidly by acquisition and has inherited
numerous different procurement processes and related IT systems. The decision has been made
to consolidate and reduce redundant procurement processes and systems. The CEO has
announced that the company will seek to leverage higher volume discounts and lower related IT
support costs by instituting a preferred supplier program.
TOGAF 9 Is used for internal Enterprise Architecture activities, with an iterative approach for
executing Architecture Development Method (ADM) projects.
At present, there are no particularly useful architectural assets related to this initiative, so all
assets need to be acquired and customized or created from scratch. The company prefers to
implement commercial off the shelf package applications with little customization. The CIO, who is
the project sponsor, has stated that she is not concerned about preserving existing processes or
systems.
The architect-re development project has put in place Its Architecture Capability for this project
and has started a number of iteration cycles to develop the Architecture. Some tasks to address
concerns related to the Business Architecture have been completed. The next immediate task is to
address the Information Systems Architectures.
The Information Systems Architectures must address stakeholder concerns such as:
1. Which procurement-related business processes are supported by zero, one, or many existing
applications?
2. What non-procurement applications will need to be integrated with any new procurement
applications?
3. What data will need to be shared?
Refer to the Scenario
[Note: You may need to refer to TOGAF 9 Chapter 35 in order to answer this question.]
You have been asked to identify the most appropriate catalogs, matrices, and diagrams for this
situation.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: C

In the early iterations of Architecture development, you would describe the Target Application
Architecture with Application Communication diagrams and an Application Interaction matrix, and
describe the Target Data Architecture with a Data Entity/Business Function matrix and a
System/Data matrix. In the later iterations of Architecture development, you would describe the
Baseline Application Architecture with a System/Function matrix, and describe the Baseline Data
Architecture with a Data Entity/Data Component catalog.

Explanation

Explanation: In this the company prefers to implement commercial off the shelf package
application with little customization and not concerned about preserving existing processes or
systems.
Reference: 19.4 Approaches to Architecture Development.

Question 17 Choose 1

Scenario:
Please read this scenario prior to answering the Question
You have been appointed as a consultant to the Lead Enterprise Architect of an international
agricultural company that exports bulbs, flowers and seeds worldwide. The company has its
headquarters in the Netherlands, and has sales and distribution centers in over 30 countries
worldwide. Several of these centers include administrative, manufacturing, and research facilities.
To achieve full integration of their research capabilities with their development centers located in
various climate zones, the company wants to develop strong self-directed teams in each location.
It also wants to define new business models that are profitable while reducing their impact on the
environment. The management team is deeply committed to ensuring that the company is a world
leader in socially responsible seed development with a business strategy that focuses on
profitability through environmentally friendly operating processes.
The international operations of the company are subject to legal and regulatory requirements for
each country where they operate. The production of genetically modified seeds has governmental
controls that are strictly enforced and compliance is critical. Recently a competitor was heavily
fined for violating the regulations in a country where it was developing pest-resistant seeds.
The Governing Board is concerned about the risks posed in this complex global environment, and
as a result has approved the expenditure of resources to establish an Enterprise Architecture
program. They have requested to be informed about the status of projects that could impact
regulatory compliance. They also want to enable the corporate legal staff and auditors to analyze
proposed architectures to ensure that they are within the legal guidelines for a given location. In
addition, the research organization should be able to see that the architecture is appropriate for its
needs.
TOGAF 9 has been mandated as the framework for the development and evolution of the
Enterprise Architecture practice. The Preliminary Phase has been completed to establish the
enterprise architecture capability for this project.
Refer to the Scenario
You have been asked to recommend an approach that would enable the development of an
architecture that addresses the needs of the Governing Board, legal staff, auditors and the
research organization.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: A

You recommend that each project architecture activity is developed using a consistent
modeling approach that is uniform across all architecture projects. Each architecture should be
defined based on this fixed set of models so that all concerned parties can examine the models to
ensure that their issues and concerns have been addressed.

Question 18 Choose 1

Scenario:
Please read this scenario prior to answering the question
You are the Lead Enterprise Architect in a company that specializes in the development of wind
turbine blades for use in large-scale commercial wind energy production systems. The company
has manufacturing facilities located in Illinois, Nebraska, and Manitoba. Each of these plants
supplies a different manufacturer that builds and sells complete systems. The turbine blades are
custom engineered to meet each manufacturers design specifications.
Until recently, most turbine blades were fabricated manually using molded fiber-reinforced plastics.
However, recent improvements in composite materials, coupled with enhanced automated
methods for precision application of materials during the molding process, have led to significant
reduction in weight, increase in strength, and improved blade longevity. The company has
pioneered the development of a proprietary automated process for continuous extrusion of the
turbine blades. Patents have been filed to protect the process, but certain trade secrets must be
closely guarded.
The company has a mature Enterprise Architecture organization that is supported by a crossfunctional
Architecture Board. The Chief Information Officer and the Chief Operating Officer cosponsor
the Enterprise Architecture program.
TOGAF 9 and its Architecture Development Method (ADM) are used to develop the automated
manufacturing processes and systems that are used to design, manufacture, and test the blade
assemblies.
Recently, a pilot architecture project was completed at a single location that defined a standard
approach for controlling the Automated Test System that is used at each plant to perform final
quality assurance tests on each completed blade assembly. The Architecture Board approved the
plan for immediate implementation at each plant.
Architecture Contracts have been developed that detail the work needed to implement and deploy
the new Automated Test System controller for each location. The Chief Engineer, sponsor of the
activity, has expressed concern that a uniform process be employed at each location to ensure
consistency.
Refer to the Scenario
You have been asked to recommend the best approach to address the Chief Engineer's concern.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: D

You use the issued Architecture Contracts to manage the architecture governance processes
for the project across the locations. You deploy monitoring tools to assess the performance of the
completed blade assembly at each location and develop change requirements if necessary.
You recommend that if a deviation from the contract is detected, the Architecture Board should
modify the Architecture Contract to allow the implementation organization the ability to customize
the process to meet their local needs. As a result, you then issue a new Request for Architecture
Work to implement the modified Architecture Definition

Question 19 Choose 1

Scenario:
Please read this scenario prior to answering the Question
You are serving as the Chief Architect for a large, global commodities trading company which has
been growing rapidly through a series of acquisitions.
Each business is performing well in its markets. However, the lack of integration between
headquarters and the business units has increasingly caused problems in the handling of
customer and financial information. The inability to share information across businesses has
resulted in lost opportunities to "leverage the synergies" that had been intended when the
businesses were acquired. At present, each business unit maintains its own applications. Despite
an earlier initiative to install a common application to manage customer, products, supplier, and
inventory information, each business unit has different ways of defining each of these core
elements and has customized the common application to the point where the ability to exchange
information is difficult, costly, and error-prone.
As a result, the company has made the decision to introduce a single enterprise-wide application
to consolidate information from several applications that exist across the lines of business. The
application will be used by all business units and accessed by suppliers through well defined
interfaces.
The Corporate Board is concerned that the new application must be able to manage and
safeguard confidential customer information in a secure manner that meets or exceeds the legal
requirements of the countries in which the company operates. This will be an increasingly
important capability as the company expands its online services in cooperation with its trading
partners.
The CIO has formed an Enterprise Architecture department, and one of the primary goals in its
charter is to coordinate efforts between the implementation team and the business unit personnel
who will be involved in the migration process. The CIO has also formed a cross-functional
Architecture Board to oversee and govern the architecture. The company has an existing team of
security architects.
TOGAF 9 has been selected for use for the Enterprise Architecture program. The CIO has
endorsed this choice with the full support of top management.
Refer to the Scenario
In the Preliminary Phase you need to define suitable policies and ensure that the company has the
appropriate capability to address the concerns of the Corporate Board.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: B

You evaluate the implications of the Board's concerns by examining the security and regulatory
impacts on business goals, business drivers and objectives. Based on your understanding, you
then update the current security policy to include an emphasis on the concerns. You define
architecture principles to form constraints on the architecture work to be undertaken in the project.
You then allocate a security architect to ensure that security considerations are included in the
architecture planning for all domains.

Explanation

Incorrect:
Not C: Implied that solution needs be developed to address the concern, instead of address the
concern in the ERP solution itself.

Question 20 Choose 1

Scenario:
Please read this scenario prior to answering the Question
Your role is that of Lead Enterprise Architect within a vacation property management firm that has
been growing through acquisition. The firm manages over 200 resort properties across North
America. Many of the resort properties use the same internal IT systems that they used before
they were acquired. Until recently, the only requirement that has been placed on each property is
that they use a standard financial reporting system to report their financial results to the
headquarters on a weekly basis.
The CEO has stated his concerns about the inefficiencies of the current approach and identified
the need to change. He has defined a new strategic vision that will enhance the business by
standardizing its operations across the network to provide consolidated financial, human
resources, logistics, sales and marketing, and yield management. He has also stated that he
expects results by the end of the current fiscal year.
These changes will provide the company with improved utilization of its capacity and more efficient
operations. The addition of a corporate-wide data warehouse will provide analytics that will enable
the marketing group to improve its ability to target advertising into key markets to improve yields.
The firm has a mature enterprise architecture practice and uses TOGAF 9 as the method and
guiding framework. The CIO is the sponsor of the activity.
In planning this change, the Chief Architect engaged the services of a well-known consulting firm
that specializes in business strategy. An initial study has been conducted to identify the strategic
changes needed to implement the CEOs vision. This recently completed with approval of a
strategic architecture encompassing the entire firm, including detailed requirements and
recommendations.
Based on the recommendations from the initial study, the firm has taken the decision to adopt a
packaged suite of integrated applications that is tailored to the needs of the hospitality industry.
Refer to the scenario
You have been asked by the Chief Architect to justify the best approach for architecture
development to realize the CEOs vision.
Based on TOGAF 9, which of the following is the best answer?

Show answerHide answer

Correct answer: D

You recommend that this engagement define the baseline Technology Architecture first in order
to assess the current infrastructure capacity and capability. Then the focus should be on transition
planning and architecture deployment. This will identify retirements to ensure that the projects are
sequenced in an optimal fashion so as to realize the vision.

Full mock exam

Sit the OG0-093 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real OG0-093 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full OG0-093 mock exam
  • 65questions per mock
  • 105 mintime limit
  • 360questions in the bank
  • Newmock on every attempt