IIA certification · Exam IIA-CIA-Part2

IIA-CIA-Part2 Mock Exam Page 15

Certified Internal Auditor Part 2 - Internal Audit Engagement

Free IIA-CIA-Part2 mock exam questions 141–150, each with the answer and an explanation.

20 questions · 24 minutes · free, no sign-up

Free IIA-CIA-Part2 questions

141–150 of 214 free
Question 141 Choose 1
Which of the following statements concerning workpapers is the most accurate?
Show answerHide answer

Correct answer: B The extent of what is included in workpapers is a matter of professional judgment

Explanation

Explanation:

Under IIA Standard 2330 (Documenting Information), the auditor must document information sufficient to support the engagement's conclusions and results. How much documentation is needed is a matter of professional judgment — the auditor decides the extent based on the engagement's objectives, the significance of findings, the complexity of the work, and the risk involved. There is no fixed formula; experienced auditors apply judgment to ensure workpapers are sufficient without being excessive.

Why the other options are incorrect:

A — The organization and format are the same for all engagements: Incorrect — workpaper organization and format vary by engagement, based on the nature of the activity, the engagement's objectives, and the audit methodology used. There is no single mandated format for every engagement.

C — Workpapers should be complete so that every conceivable question can be answered: Incorrect — this overstates completeness. Workpapers must be sufficient to support conclusions, not exhaustive enough to answer every conceivable question; excessive documentation is inefficient and unnecessary.

D — Copies of operational management records should not be included, but referenced: Incorrect — the Standards do not prohibit including copies of management records. Auditors may include copies, extracts, or references as appropriate; the choice depends on what best supports the finding. A blanket prohibition is not accurate.


Reference: IIA IPPF — Standard 2330 (Documenting Information) and the IIA Practice Guide on engagement workpapers (workpaper quality criteria: complete, accurate, relevant, understandable, timely).

Question 142 Choose 1
An internal auditor is assigned to validate calculations on the organization's billing application. As part of the test, the internal auditor is required to use an automated audit tool to simulate transactions for testing. Which of the following would most appropriately be used for this purpose?
Show answerHide answer

Correct answer: C Integrated test facilities.

Explanation

Explanation:

An integrated test facility (ITF) is a technique in which the auditor processes simulated (dummy) transactions through the client's live application to test whether the system's programmed controls and calculations work correctly. The auditor creates test transactions with known expected results and compares the system's output to expectations. This is exactly the scenario described — using automated tools to simulate transactions to validate calculations in the billing application (Standard 1220.A2 — technology-based audit techniques).

Why the other options are incorrect:

A — Generalized audit software: GAS is used to extract, read, sort, and analyze existing data from files and databases. It does not simulate transactions through the live application to test programmed calculations.

B — Utility software: These are vendor-supplied programs for system maintenance/housekeeping (backup, file reorganization); they are not designed for simulating test transactions and are not appropriate audit tools for this purpose.

D — Audit expert systems: These are decision-support tools that help auditors apply rules and reach conclusions; they do not process simulated transactions through the client's application.

Reference: IIA IPPF — Standard 1220.A2 (Due Professional Care — technology-based audit techniques) and Standard 2310 (Identifying Information); IIA GTAG series on computer-assisted audit techniques (ITF vs. GAS).

Question 143 Choose 1
For which of the following fraud engagement activities would it be most appropriate to involve a forensic auditor?
Show answerHide answer

Correct answer: D Preparing evidentiary documentation.

Explanation

Explanation:

A forensic auditor specializes in fraud investigation and the gathering, preservation, and documentation of evidence in a manner that will withstand legal scrutiny — including chain of custody, evidentiary standards, and documentation suitable for litigation or disciplinary proceedings. Preparing evidentiary documentation is therefore the activity where forensic expertise is most directly and appropriately applied during a fraud engagement.

Why the other options are less appropriate for a forensic auditor specifically:

A — Independently evaluating conflicts of interests: This is a governance/independence review typically performed by internal audit, compliance, or ethics functions — not a forensic specialty.

B — Assessing contracts for relevant terms and conditions: This is a contract review/legal activity, typically performed by legal counsel or contract specialists, not a forensic auditor.

C — Performing statistical analysis for data anomalies: This is a data analytics activity performed by internal auditors or data analysts; while forensic auditors may use analytics, the statistical anomaly analysis itself is not the forensic specialty.

Reference: IIA IPPF — Standard 1210 (Proficiency — obtaining specialized skills when needed), Standard 1220.A1 (Due Professional Care — exercising care in fraud-related work), and Standard 2310 (Identifying Information); IIA Practice Guide on fraud and forensic auditing.

Question 144 Choose 1
According to IIA guidance, which of the following is the most appropriate action to be taken by the chief executive (CAE) if management refuses to accept audit recommendations and implement corrective actions, Even after escalation to senior management?
Show answerHide answer

Correct answer: D The CAE should advise senior management of his intention to escalate the matter to the board.

Explanation

Explanation:

When management refuses to accept recommendations and take corrective action — even after escalation to senior management — the CAE has a duty to bring the matter to the attention of those charged with governance. Under IIA Standard 2600 (Communicating the Acceptance of Risks), when the CAE concludes that senior management has accepted a level of risk that may be unacceptable to the organization, the matter must be communicated to the board. The appropriate step is to advise senior management that the CAE intends to escalate the unresolved matter to the board, giving management a final opportunity to resolve it while ensuring the board is informed.

Why the other options are incorrect:

A — Continue to meet with management to obtain agreement: The CAE has already escalated to senior management without resolution; continuing to negotiate indefinitely fails to discharge the CAE's responsibility to communicate unacceptable risk to the board (Standard 2600).

B — Note in the final report that management has decided to accept the risk: Simply documenting that management accepted the risk does not fulfill the CAE's obligation — the CAE must escalate the acceptance of unacceptable risk to the board, not merely note it in a report.

C — Ask for additional testing to strengthen the case: The issue is not insufficient evidence — management has refused to act. More testing does not resolve a management decision to accept risk, and the matter still requires escalation to the board.


Reference: IIA IPPF — Standard 2600 (Communicating the Acceptance of Risks) and Standard 2500 (Monitoring Progress); Standards 2060 (Reporting to Senior Management and the Board).

Question 145 Choose 1
While conducting a review of the logistics department the internal audit team identified a crucial control weakness. The chief audit executive (CAE) decided to prepare an audit memorandum for management of the logistics department followed by an informal meeting What is the most likely reason the CAE decided to prepare the audit memorandum?
Show answerHide answer

Correct answer: C To allow management to address the identified weakness timely

Explanation

Explanation:

An audit memorandum (interim communication) followed by an informal meeting is used to communicate a significant control weakness promptly, before the final report is issued, so that management can begin addressing the issue without delay. When a *crucial* control weakness is identified, timely communication enables management to take corrective action early, reducing exposure. This is consistent with IIA Standard 2410.A2 (interim reporting) and the purpose of preliminary/interim communications — to facilitate timely management action.

Why the other options are less likely:

A — To report up-to-date audit progress: An audit memorandum focused on a specific critical weakness is not primarily a progress report; it is a targeted communication of a significant finding to prompt action.

B — To ensure the audit team and CAE are aligned: Internal alignment is achieved through supervision and review (Standard 2340), not through a memorandum issued to management. The memorandum is directed at management, not internal team alignment.

D — To obtain management's agreement with the finding: While agreement may be sought, the primary reason for prompt interim communication is to enable timely corrective action. Agreement is a means, not the main purpose — and the informal meeting provides the forum for discussion.

Reference: IIA IPPF — Standard 2410 (Criteria for Communicating) and Standard 2410.A2 (interim reporting for significant/time-sensitive matters); Standard 2440 (Disseminating Results).

Question 146 Choose 1
A bank uses customer departmentalization to categorize its departments. Which of the following groups best exemplifies this method of categorization?
Show answerHide answer

Correct answer: A Community, institutional, and agricultural banking

Explanation

Explanation:

Customer departmentalization groups activities and departments around types of customers or customer segments served. "Community, institutional, and agricultural banking" represents distinct customer groups — each department serves a different category of customer. This is the classic example of customer-based departmentalization in a bank.

Why the other options are incorrect:

B — Mortgages, credit cards, and savings: These are products/services, so this illustrates product departmentalization, not customer departmentalization.

C — South, southwest, and east: These are geographic regions, illustrating geographic (territorial) departmentalization.

D — Teller, manager, and IT specialist: These are job roles/functions, illustrating functional departmentalization (or simply job types), not customer groups.

Reference: IIA IPPF — Standard 2110 (Governance) and Standard 2130 (Control); COSO Internal Control — Integrated Framework (organizational structure and assignment of authority and responsibility).

Question 147 Choose 1
The internal auditors available to perform the engagement do not have sufficient skills related to the area under review. Which of the following iss an appropriate action for the chief audit executive to take?
Show answerHide answer

Correct answer: D Supplement the internal auditors assigned to the engagement by bringing onto the engagement team a consultant who is independent of the area under review and has the missing expertise

Explanation

Explanation:

Under IIA Standard 1210.A1 (Proficiency), when the internal audit activity lacks the knowledge, skills, or other competencies needed for an engagement, the CAE must obtain competent advice and assistance from outside the internal audit activity — for example, by engaging an external consultant or specialist. The key is that the supplement must be independent of the area under review to preserve objectivity. Option D does exactly this: it brings in the missing expertise while safeguarding independence.

Why the other options are incorrect:

A — Continue with available staff, providing more hands-on supervision: Supervision cannot substitute for technical expertise the staff simply do not possess. Proceeding without the required skills risks an inadequate engagement and violates Standard 1210.A1.

B — Limit the objectives and scope to match available skills: The engagement's objectives and scope should be driven by risk and the engagement's purpose, not artificially narrowed to fit staff limitations. Reducing scope to accommodate a skills gap improperly limits assurance and may fail to address the significant risks (Standard 2220 — Engagement Scope).

C — Cosource using personnel from the area under review: Using staff from the area being audited severely impairs objectivity and independence (Standards 1100 and 1130) — they would be evaluating their own work. This is inappropriate even if it fills the knowledge gap.


Reference: IIA IPPF — Standard 1210.A1 (Proficiency — obtaining competent advice and assistance when the activity lacks requisite knowledge/skills), Standards 1100/1130 (Independence and Objectivity), and Standard 2220 (Engagement Scope).

Question 148 Choose 1
During a review of the organization's waste management processes, the internal auditor discovered that wastewater is being disposed of inappropriately. The auditor's recommendations, suggested to mitigate the risk of regulatory sanctions and reputational damages, were accepted and timelines for implementation were agreed. However, during the internal audit activity's periodic follow-up exercise, management indicated that the recommendation was too expensive to implement and the current disposal method has been cost-effective. What should the chief audit executive do in this case?
Show answerHide answer

Correct answer: C Convene a meeting with senior management and discuss the issue and the potential impact it may have on the organization.

Explanation

Explanation:

Management has accepted a risk the CAE considers unacceptable — refusing to implement an agreed recommendation because of cost, while continuing inappropriate wastewater disposal that exposes the organization to regulatory sanctions and reputational damage. Under IIA Standard 2600 (Communicating the Acceptance of Risks), when the CAE concludes that management has accepted a level of risk that may be unacceptable to the organization, the CAE must discuss the matter with senior management. If the matter is not resolved, it must then be escalated to the board. Convening a meeting with senior management to discuss the issue and its potential impact is therefore the appropriate next step.

Why the other options are incorrect:

A — Do nothing because recommendations were provided: Incorrect — the CAE's responsibility does not end with issuing recommendations. Follow-up (Standard 2500) and escalation of unacceptable accepted risk (Standard 2600) are required. Simply having recommended is not enough.

B — Contact the regulatory agency to convince management: Internal audit should not report to external regulators to pressure its own management; this bypasses the governance structure and is inappropriate. Escalation is internal — to senior management and then the board.

D — Highlight the exposure to external auditors to pressure management: Using external auditors to apply pressure is not the proper escalation channel and inappropriately leverages an external party. The CAE must follow the internal escalation path (senior management → board).

Key principle: When management accepts what the CAE deems an unacceptable risk, the CAE must discuss it with senior management and, if unresolved, escalate to the board (Standard 2600). External regulators or auditors are not the appropriate channel for internal escalation.

Reference: IIA IPPF — Standard 2600 (Communicating the Acceptance of Risks), Standard 2500 (Monitoring Progress), and Standard 2060 (Reporting to Senior Management and the Board).

Question 149 Choose 1
The internal auditor and her supervisor are in dispute about a risk that was not tested during an audit of the procurement function. Which of the following tools would best support the auditor's decision not to test the risk?
Show answerHide answer

Correct answer: D An assurance map

Explanation

Explanation:

A heat map visually plots risks by likelihood and impact (or significance), allowing the auditor to show that the risk in question was assessed as low priority relative to other risks. This provides objective, documented support for the auditor's decision not to test it — the risk ranked low on the heat map, so resources were directed to higher-priority risks. This aligns with risk-based engagement planning (Standard 2010, 2201), where the scope of testing is justified by the risk assessment.

Why the other options are less supportive:

A — A spaghetti map: A process-flow diagram that traces the physical or logical path of people/materials through a process to identify inefficiencies or unnecessary steps. It does not rank or prioritize risks, so it cannot justify a decision not to test a risk.

C — A process map: A flowchart of process steps and responsibilities. It helps understand the process but does not assign risk ratings or priorities, so it does not directly support the decision to exclude a risk from testing.

D — An assurance map: An assurance map shows where assurance is obtained across the organization (who provides assurance over what — internal audit, management, compliance, external audit). It helps identify gaps and duplication in assurance coverage, but it does not, by itself, rate the likelihood/impact of an individual risk to justify not testing it.

Reference: IIA IPPF — Standard 2010 (Planning — risk-based), Standard 2201 (Planning Considerations), and Standard 2210/2220 (Engagement Objectives and Scope); COSO ERM (risk assessment and risk mapping/heat maps).

Question 150 Choose 1
During follow-up. the internal auditor discovered that operational management did not implement effective actions to address a significant control breach If the issue is left unresolved it may result in regulatory sanctions and damage the organization's reputation What is the most appropriate next step for the chief audit executive to lake?
Show answerHide answer

Correct answer: C Discuss the matter with senior management

Explanation

Explanation:

The follow-up revealed that management has not implemented effective corrective action for a significant control breach, leaving the organization exposed to regulatory sanctions and reputational damage. Under IIA Standard 2600 (Communicating the Acceptance of Risks), when the CAE concludes that a level of risk may be unacceptable to the organization, the CAE must first discuss the matter with senior management. Only if the matter is not resolved after that discussion should it be escalated to the board. The escalation path is therefore: operational management → senior management → board.

Why the other options are incorrect:

A — Report the matter to the board: Escalating directly to the board is premature. Standard 2600 requires discussion with senior management first; the board is the next step only if senior management fails to resolve the issue.

B — Implement the recommended control to address the exposure: Implementation is a management responsibility. Internal audit must not implement controls — doing so impairs independence and objectivity (Standards 1100 and 1130).

D — Ask the regulatory agency to persuade management: Internal audit should not involve external regulators to pressure its own management; this bypasses the governance structure. Escalation is internal — senior management, then the board.

Reference: IIA IPPF — Standard 2600 (Communicating the Acceptance of Risks), Standard 2500 (Monitoring Progress), Standard 2060 (Reporting to Senior Management and the Board), and Standards 1100/1130 (Independence and Objectivity).
Full mock exam

Sit the IIA-CIA-Part2 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real IIA-CIA-Part2 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full IIA-CIA-Part2 mock exam
  • 100questions per mock
  • 120 mintime limit
  • 716questions in the bank
  • Newmock on every attempt