An energy-saving project costs $540,000. The project will have maintenance costs of
$25,000 per year. The energy savings from the project are $160,000 per year. What is the
simple payback of the project?
Show answerHide answer
Correct answer: C4.0 years
Question 2Choose 1
If the initial design process includes group relamping, how can this reduce the number of
lamps required to illuminate a space?
Show answerHide answer
Correct answer: AGroup relamping reduces factors that contribute to light loss, which means fewer lamps
are required to illuminate a space
Question 3Choose 1
A 3 MW rated wind-powered turbine has a rotor diameter of 113 meters. What is the
efficiency of the wind turbine at rated power if it is operating in wind power calculated at 8.6
MW? Assume an air density of 1.225 kg/m³.
Show answerHide answer
Correct answer: B34.9%
Question 4Choose 1
How much fuel is required to heat 50 kg water from 20°C water to 200°C saturated steam?
Assume the boiler is 80% efficient (based on the higher-heating value of the fuel).
Show answerHide answer
Correct answer: B169.3 MJ
Question 5Choose 1
Which pump system listed below is most likely the best application for converting to
variable-speed drive?
Show answerHide answer
Correct answer: DPump system with throttle fully open circulating liquid in a closed loop cooling system
Question 6Choose 1
Which of the following steam turbines will likely not provide steam output at a useable
temperature for industrial processes?
Show answerHide answer
Correct answer: CCondensing turbine
Question 7Choose 1
A facility has a monthly peak power demand of 1,000 kW and an average power factor of
80%. The facility pays a demand charge of $7.50/kVA-month. What is the additional cost
per month because the power factor is less than 100%?
Show answerHide answer
Correct answer: C$1,875/month
Question 8Choose 1
You are using a performance contract to finance the added cost of using more-efficient
equipment in the construction of a new building. Which of the following International
Performance Measurement and Verification Protocol (IPMVP) options would you use to
verify annual energy savings?
Show answerHide answer
Correct answer: COption C - Whole facility measurement
Question 9Choose 1
A building is conditioned by an air-conditioning and heating system. What technology can
directly prevent simultaneous heating and cooling of the space?
Show answerHide answer
Correct answer: CVariable air volume control
Question 10Choose 1
Thermal scans of electrical equipment are useful for:
Show answerHide answer
Correct answer: CLocating a loose electrical connection