If a project is said to be on a "fast track program/' the fast track method is:
Show answerHide answer
Correct answer: ASimultaneous working engineering, procurement, and construction, with appropriate
overlap from each phase of work so that delays are eliminated and all the work is
streamlined into a correct plan of logic/sequence and duration for all of the work
Question 52Choose 1
A major theme park is expanding the existing facility over a five-year period. The design
phase will be completed one year after the contract is awarded. Major engineering
drawings will be finalized two years after the design contract is awarded and construction
will begin three years after the award of the design contract. New, unique ride technology
will be used and an estimate will need to be developed to identify these costs that have no
historical data. Which of the following is least likely to improve a large earthmoving contractor's
productivity?
Show answerHide answer
Correct answer: AUsing apprentice operators to save labor costs
Question 53Choose 1
The latest allowable end time minus the earliest allowable end time on a schedule activity
is referred to as:
Show answerHide answer
Correct answer: ATotal float
Question 54Choose 1
Which of the following is used for measuring productivity loss?
Show answerHide answer
Correct answer: CEarned formula
Question 55Choose 1
Two of the most important things to know when planning a speech or lecture are the
______________and______________ of your audience.
Show answerHide answer
Correct answer: BBackground, attitude
Question 56Choose 1
A used concrete pumping truck can be purchased for $125,000. The operation costs are
expected to be $65,000 the first year and increase 5% each year thereafter. As a result of
the purchase, the company will see an increase in income of $100,000 the first year and
5% more each subsequent year. The company uses straight-line depreciation. The truck
will have a useful life of five (5) years and no salvage value. Management would like to see
a 10% return on any investment. The company's tax rate is 28%.
The compound interest factor used to determine Present Value in year number 5 is:
Show answerHide answer
Correct answer: B0.6209
Question 57Choose 1
SCENARIO: A can manufacturing company requested you to provide data for their decision
making The unit prices of the can varies but an average selling price of $0.55 cents and
average cost of S45 cents is estimated.
The monthly fixed costs are:
Rant-$1,500
Wages - $4.000
Miscellaneous fixed expenses - $500
If the rent increases by 100% and the unit sales/other costs remain unchanged, the new
break even amount is?
Show answerHide answer
Correct answer: B$41,250
Question 58Choose 1
If you deposit $100 per month for two (2) years and earn interest at 12% APR (Annual
Percentage Rate) compounded monthly, how much will you have at the end of the period?
Show answerHide answer
Correct answer: B $2,976
Question 59Choose 1
The following question requires your selection of CCC/CCE Scenario 2 (2.3.50.1.2) from
the right side of your split screen, using the drop down menu, to reference during your
response/choice of responses.
9,375 hours have been expended to date. Planned completion at this time is 75%. The
project is determined to be 66% complete. Based on current trends, how many hours will
be expended at project completion?
Show answerHide answer
Correct answer: B14,201
Question 60Choose 1
Which of the lol owing comparisons is commonly used in forensics schedule analysis
(FSA)?
Show answerHide answer
Correct answer: DAs-planned vs as-built