The head of customer service wants to identity potential bottlenecks in the support
workflow of her teams in the last three months. Which report provides this information?
Show answerHide answer
Correct answer: CCumulative Flow Diagram
Explanation
Explanation: The Cumulative Flow Diagram is the report that provides the information that
the head of customer service wants. The Cumulative Flow Diagram is a tool that visualizes
the quantity and distribution of work items along different stages of a process. The report
shows how many work items are in each stage at any given time, and how they flow from
one stage to another. The report can help identify potential bottlenecks in the support
workflow by showing where work items accumulate or stagnate over time. For example, if
the report shows a sudden increase or a wide band of work items in the “Waiting for
Customer” stage, it may indicate that the customers are not responding quickly enough or
that the support team is not following up effectively. The report can also help monitor the
overall progress and performance of the support teams by showing the total number of
work items created, resolved, and remaining over time.
Question 12Choose 1
Paul and Tessa are in the Auditors role of every project.
You need to write a JQL query that shows Issues reported by either of them that are still
unassigned.
Select the correct JQL query.
Show answerHide answer
Correct answer: AReporter IN (Paul, Tessa) AND Assignee IS EMPTY
Explanation
Explanation: The correct JQL query to find issues reported by either Paul or Tessa that
are still unassigned is: Reporter IN (Paul, Tessa) AND Assignee IS EMPTY. This query
uses the IN operator to specify a list of values for the Reporter field, and the IS EMPTY
operator to check if the Assignee field has no value. The other options are incorrect
because they use invalid syntax or operators, such as “-”, NULL, or Unassigned. For more
information on JQL syntax and operators, see JQL operators and Use advanced search
with Jira Query Language (JQL). References: JQL operators, Use advanced search with Jira Query Language (JQL)
Question 13Choose 1
All projects use a shared permission scheme.
The Browse Projects permission needs to be updated so that projectadministratorscan
manage access to their own projects.
What entry must be added to the Browse Projects permission?
Show answerHide answer
Correct answer: BProject Lead
Question 14Choose 2
You need to find all issues that were not competed in some past sprint, and that are now
part of an active sprint. Identify two functions that you need to use in your JQL query.
(Choose two.)
Show answerHide answer
Correct answer: A, EclosedSprints()openSprints()
Explanation
Explanation: The two functions that are needed to use in the JQL query to find all issues
that were not completed in some past sprint, and that are now part of an active sprint are
closedSprints() and openSprints(). The closedSprints() function returns all issues that are
assigned to a completed sprint. The openSprints() function returns all issues thatare
assigned to an incomplete sprint. By combining these two functions with the NOT operator,
we can filter out the issues that belong to both a completed sprint and an incomplete sprint,
and only get the issues that were not completed in some past sprint, and that are now part
of an active sprint. For example, the JQL query could be:
project = XYZ AND issuekey NOT IN (closedSprints() AND openSprints())
This query will return all issues in project XYZ that are not in both a closed sprint and an
open sprint, meaning they are either in a closed sprint only or an open sprint only. Since we
are looking for issues that are now part of an active sprint, we can assume they are in an
open sprint only. References: Advanced search reference - JQL functions, Modifying
closedSprints() to return previous two Sprints, JQL - Explanation of what closedSprints()
does
Question 15Choose 1
The team wants to flag issues using a category. Their requirements are:
• more than one category value can be selected on an issue
• new category values can be added by any user
• category values can be selected via a dropdown menu
• category values can be re-used across all projects
Which field meets their requirements?
Show answerHide answer
Correct answer: Dlabel
Explanation
Explanation: The label field meets the team’s requirements for flagging issues using a
category. Labels are a type of custom field that allow users to add one or more descriptive
tags to issues. Users can add new labels on the fly, and select existing labels from a
dropdown menu. Labels can be re-used across all projects, and can be searched and
filtered easily. A text field does not allow multiple values or a dropdown menu. A
component does not allow multiple values or adding new values by any user. A user picker
does not allow multiple values or adding new values byany user. Checkboxes do not allow
adding new values by any user.
Question 16Choose 1
Depending on the project configuration, a project administrator might be able to perform
some tasks, instead of escalating them to the Jira administrator. Identic one such task.
Show answerHide answer
Correct answer: ARemove Watchers from project notifications.
Explanation
Explanation: A project administrator can remove watchers from project notifications, if they
have the Manage Watchers permission. This is a task that does not require Jira
administrator access, and can be done by the project administrator from the issue view.
Removing a priority value used by the project, updating permissions for a project user, and
limiting who can bulk edit project issues are all tasks that require Jira administrator access,
and cannot be done by the project administrator.
Question 17Choose 2
Your team uses Story Points for estimation and tracking.
You performed several actions in the active sprint.
Which two actions are reflected as scope change? (Choose two.)
Show answerHide answer
Correct answer: C, DDragged on estimated story from the backlog to the sprint.Modified the estimate value on a committed story.
Explanation
Explanation: The two actions that are reflected as scope change are dragging an
estimated story from the backlog to the sprint and modifying the estimate value on a
committed story. Scope change is a measure of how much work was added or removed
from a sprint after it started. It is calculated by comparing the total story points committed at
the start of the sprint and the total story points completed at the end of the sprint. If you add
or remove issues from a sprint, or change their estimates, you are changing the scope of
the sprint. The other actions mentioned in the question do not affect the scope of the sprint,
as they do not change the amount of work planned or done in the sprint.
Question 18Choose 1
Gen prioritizes and triages support requests as soon as they come in. She now wants to
use drag-and-drop to:
• quicklyassign and transition them to in Progress
• instantly associate them with Epics
Which board view will meet these requirements?
Show answerHide answer
Correct answer: BKanban board
Question 19Choose 1
You want to remove some epics from your personal Scrum board, without impacting any
other boards. Identify the correct solution.
Show answerHide answer
Correct answer: DExclude them via the board sub filter.
Question 20Choose 1
You are reviewing the Velocity Chart for your team and notice that they completed more
story points than they committed in their last sprint. You are definitely the only person who
can add issues to sprints in your project. How did your learn complete more story points
than they committed?
Show answerHide answer
Correct answer: CSomeone increased the story point value on an issue mid-sprint.
Explanation
Explanation: The reason why your team completed more story points than they committed
in their last sprint is that someone increased the story point value on an issue mid-sprint.
This will increase the total story points completed at the end of the sprint, but not affect the
total story points committed at the start of the sprint. Therefore, it will result in a positive
scope change. The other reasons mentioned in the question do not explain why your team
completed more story points than they committed, as they either do not affect story points
at all, or affect both committed and completed story points equally.