Show answerHide answer
Correct answer: A Option A
Explanation
Explanation:To minimize traffic impact during an ACI fabric upgrade with 3 APIC controllers and servers dual-homed to vPC leaf switch pairs, the correct sequence must address both the APIC cluster and the leaf switches in a way that maintains fabric operations and avoids vPC domain disruption. Option A follows the recommended Cisco upgrade workflow.
Correct Option:
A. Option A: The sequence is:
Create two maintenance groups for the leaf switches: VPC left and VPC right.
Upgrade the APIC controllers.
Upgrade the first group of leaf switches.
Upgrade the second group of leaf switches.
This is correct because:
The APIC controllers should be upgraded first to ensure the new software version is running on the management plane before upgrading the switches. With 3 APICs, the cluster can maintain quorum during the rolling upgrade.
The leaf switches are divided into vPC left and vPC right groups. This ensures that when one group is upgraded, the other group remains active, so vPC pairs are not disrupted simultaneously. Servers dual-homed to vPC pairs maintain connectivity through the non-upgraded side.
Upgrading leaf switches in separate vPC groups minimizes traffic impact because at least one path remains available at all times.
Incorrect Option:
B. Option B:
This option upgrades the first group of switches before the APIC controllers. Upgrading switches before the APIC cluster is not recommended because the APIC must be running the target version to manage the upgraded switches properly. This can cause compatibility issues and management plane disruption.
C. Option C:
This option creates maintenance groups for the APIC controllers (VPC left and VPC right), which is incorrect. The vPC concept applies to leaf switch pairs, not APIC controllers. APIC controllers form a cluster and do not use vPC. Additionally, upgrading leaf switches before APIC controllers is not the recommended order.
D. Option D:
This option also creates maintenance groups for APIC controllers (VPC left and VPC right), which is invalid. The upgrade sequence also places APIC controller upgrades before leaf switches, but the grouping is wrong. vPC groups are for leaf switches, not APICs.
Reference:
Cisco APIC Upgrade and Downgrade Guide — "Upgrade Sequence": Cisco recommends upgrading the APIC cluster first, then upgrading leaf switches in maintenance groups that respect vPC pairing (e.g., vPC left and vPC right) to avoid simultaneous disruption of both sides of a vPC domain.



correct descriptions on the right.
<