Show answerHide answer
Correct answer: C Avoid releasing near peak business periods.
Explanation
ExplanationUniversal Containers is highly seasonal and approaching its busiest period. A major production release near peak business season introduces significant risk: if the release causes defects, performance issues, or downtime, the business could suffer lost revenue and customer impact during its most critical window.
The recognized ALM best practice is to freeze deployments / avoid major releases during peak business periods. Instead, schedule releases for a low-traffic window so that:
* Any issues can be detected and resolved without impacting peak business.
* Rollback/remediation can happen with minimal business disruption.
* Support and engineering teams are fully available (not consumed by peak operations).
This is a standard release governance recommendation in Salesforce ALM and enterprise change management.
Why Other Options Are Incorrect
A. Make declarative changes in production only
— This violates ALM best practice. Changes should flow through sandboxes and version control, never be made directly in production. Direct production changes bypass testing and audit trails, increasing risk — especially dangerous before peak season.
B. Bypass regression testing for minor changes
— Regression testing should never be bypassed, even for "minor" changes. Untested changes can break existing functionality, and before peak season the risk is magnified. Skipping regression testing contradicts quality governance.
D. Developers should conduct user acceptance testing
— UAT must be performed by business users/stakeholders, not developers. Developers testing their own work creates bias and misses business-level validation. This is a clear separation-of-duties violation.
References
Salesforce Trailhead – Application Lifecycle Management: Release management and deployment windows.