There are four negative risk responses an organization can elect to use. Your organization is
completing a project where some electrical work is deemed too dangerous to be completed
internally. You advise that the project manager hire a licensed electrician to complete the
dangerous assignment. What type of risk response have you advised in this scenario?
Show answerHide answer
Correct answer: B
Transference
Explanation
Answer option B is correct.
Transference is a risk response that transfers the risk to a third party, usually for a fee.
Transference does not eliminate the risk event, but assigns ownership of the risk to someone else.
Answer option C is incorrect. Mitigation involves actions to reduce or eliminate the probability
and/or impact of the risk event.
Answer option A is incorrect. Avoidance involves actions to avoid the risk event, such as changing
the project scope to take the risky work out of the project.
Answer option D is incorrect. Acceptance, as its name implies, accepts the risk event and the
consequences the risk event may bring. Acceptance is usually for smaller risk events.
Reference: Professional in Human Resources Certification Guide, Sybex, ISBN: 978-0-470-43096-
5. Chapter 5: Human Resource Development. Official PHR and SPHR Certification Guide, HR
Certification Institute, ISBN: 978-1-586-44149-4, Section III, The US Body of Knowledge.
Chapter: Risk Management
Objective: Risk Management