Which of the following is required by Scrum? (Choose all that apply.)
Show answerHide answer
Correct answer: A
Sprint Retrospective.
Professional Scrum Master I
Free PSM-I mock exam questions 11–20, each with the answer and an explanation.
20 questions · 33 minutes · free, no sign-up
Which of the following is required by Scrum? (Choose all that apply.)
Correct answer: A
Sprint Retrospective.
What is the purpose of a Sprint Review?
Correct answer: B
To inspect the product increment with the stakeholders and collect feedback on next steps.
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
Correct answer: B
The Development Team.
Who must attend the Daily Scrum?
Correct answer: B
The Development Team.
When do Development Team members take ownership of a Sprint Backlog item?
Correct answer: C
Never. All Sprint Backlog Items are “owned” by the entire Development Team, even though each
one may be done by an individual Development Team member.
The purpose of a Sprint is to produce a done Increment of product.
Correct answer: A
True
Who creates the definition of “Done”?
Correct answer: D
The development organization (or Development Team if none is available from the development
Five new Scrum Teams have been created to build one product. A few of the developers on one of
the Development Teams ask the Scrum Master how to coordinate their work with the order teams.
What should the Scrum Master do?
Correct answer: C
Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a
consolidated plan for the entire Sprint.
Which two things should the Development Team do during the first Sprint? (Choose two.)
Correct answer: C, E
Develop at least one piece of functionality. Create an increment of potentially releasable software.
What are three ways Scrum promotes self-organization? (Choose three.)
Correct answer: B, D, E
By the Development Team deciding what work to do in a Sprint. By removing titles for Development Team members. By being a lightweight framework.