Question 21 Choose 2
A government project plans to implement an AI-based fraud detection system and the project team needs to define the success criteria. They identified potential improvements in detection accuracy, reduction in investigation time, and cost savings as key performance indicators (KPIs). However, they are unsure how to effectively quantify these KPIs.

Which two approaches should be used? (Choose 2)
Show answerHide answer

Correct answer: B, D Implement a continuous performance monitoring systemEstablish a baseline using historical data comparisons

Question 22 Choose 1
A financial services firm is operationalizing an AI-driven fraud detection system. The project manager needs to ensure the tool complies with relevant data privacy laws while providing secure data access to only authorized personnel.

What is an effective technique to address these requirements?
Show answerHide answer

Correct answer: B Utilizing role-based access control (RBAC) to limit data access

Question 23 Choose 1
A manufacturing company is operationalizing an AI-driven quality control system. The project manager needs to ensure data privacy and regulatory compliance due to the critical nature of protecting sensitive operational data.

What is an effective technique that addresses these requirements?
Show answerHide answer

Correct answer: C Applying data anonymization to the dataset

Question 24 Choose 1
A government agency is using an AI system to analyze public data for policymaking decisions. The project manager needs to address risks related to data accuracy, privacy, and misuse. What represents the highest risk to the agency?
Show answerHide answer

Correct answer: C User data is stored in an unsecured database.

Question 25 Choose 1
A company plans to operationalize an AI solution. The project manager needs to ensure model performance is meeting selected thresholds before release.

What is an effective way to confirm these thresholds before this release?
Show answerHide answer

Correct answer: A Testing against validation datasets

Question 26 Choose 1
An AI project team has prepared the data and is ready to proceed with model development.

Which action should the project manager perform next?
Show answerHide answer

Correct answer: B Document the performance metrics for the model

Question 27 Choose 1
A hospital system has been using a chatbot and has received complaints from end users. The end users believe they are speaking to a person but are frustrated when answers do not make sense.

To help ensure end users know that they are engaging with an AI chatbot, what should be considered to support transparency?
Show answerHide answer

Correct answer: C Disclosure notice with each use

Question 28 Choose 1
In an IT services firm, the AI project team is tasked with developing a virtual assistant to support customer service operations. The assistant must integrate seamlessly with existing customer relationship management (CRM) systems and handle a variety of customer queries.

Which necessary initial task should the project manager take?
Show answerHide answer

Correct answer: B Conducting a comprehensive data audit

Question 29 Choose 1
A company is evaluating whether to implement AI for a project. They have defined their business objectives and determined the AI capability they want to use.

Which action will enable the project manager to move forward with the project?
Show answerHide answer

Correct answer: C Conducting a go/no-go assessment

Question 30 Choose 1
An AI team is defining success criteria for a customer support chatbot. Leadership wants to approve the project but needs objective measures that reflect both business value and risk. Which set of metrics is most appropriate?
Show answerHide answer

Correct answer: B User satisfaction, containment rate, escalation accuracy, and privacy/compliance incidents

Full mock exam

Sit the PMI-CPMAI exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PMI-CPMAI exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PMI-CPMAI mock exam
  • —questions per mock
  • —time limit
  • 134questions in the bank
  • Newmock on every attempt