Show answerHide answer
Correct answer: A Back up configurations, schedule upgrades during off-peak hours, and use a phased approach rather than attempting a network-wide rollout.
Explanation
Explanation:To maintain continuity and security during a Prisma Access data plane software upgrade, Palo Alto Networks recommends a phased and cautious approach:
Best Practices:
Back up configurations before initiating the upgrade to prevent data loss.
Schedule upgrades during off-peak hours (typically weekends) to minimize user impact.
Use a phased rollout:
Upgrade selected locations first (Phase #1).
Monitor for issues.
Proceed with remaining locations (Phase #2) after validation.
This approach ensures:
Minimal disruption to business operations.
Time to detect and resolve any upgrade-related issues.
Flexibility to roll back if necessary.
Why Other Options Are Incorrect
B. Use SCM to perform dynamic upgrades simultaneously
SCM supports upgrade scheduling, but simultaneous upgrades across all locations increase risk and reduce control.
C. Disable all security features during the upgrade
This compromises network protection and is not recommended.
D. Perform the upgrade during peak business hours
This risks major disruption and user complaints.