Question 1 Choose 2

You have been nominated audit team leader for the second recertification to ISO 14001 of ABC, a public transport organisation in a big city. The audit is planned to take place in two months'time. The audit program manager asks you to review the answer provided by ABC to a nonconformity raised during the last surveillance audit carried out eight months ago. The nonconformity reads as follows: " ABC does not always communicate its relevant environmental requirements to external providers. Evidence: A two-month contract signed with a new external provider of the maintenance for ABC's buses did not contain any relevant environmental requirements. "

Which two would you consider to be the best acceptable corrections from ABC?

Show answerHide answer

Correct answer: A, E We identified environmental aspects related to the external provider's activitiesWe revised the contract signed with the external provider to include environmental requirements

Explanation

In accordance with ISO 14001:2015 Clause 10.2 (Nonconformity and corrective action) and ISO 19011 Clause 6.6, a clear technical distinction exists between a correction (action taken to eliminate a detected nonconformity or mitigate its immediate effect) and a corrective action (action taken to eliminate the root cause and prevent recurrence).

In this scenario, the specific nonconformity is that relevant environmental requirements were not communicated in the bus maintenance contract, and the aspects of that provider were not systematically evaluated:

Option A: Identifying the environmental aspects associated with the external provider's maintenance activities immediately corrects the technical gap regarding operational knowledge under Clause 6.1.2 and Clause 8.1.

Option E: Directly revising the contract signed with the maintenance provider to incorporate specific environmental requirements corrects the immediate contractual omission specified in the audit finding.

Conversely, Option B (developing procurement procedures) and Option C (retraining personnel) represent corrective actions aimed at root causes to prevent future recurrence across procurement operations. Option D is unnecessary as policy commitments already encompass operational controls. Option F is an improper commercial action that does not fix the underlying documentation gap.

References: ISO 14001:2015 Clause 8.1 (Operational planning and control), Clause 10.2 (Nonconformity and corrective action), ISO 19011:2018 Clause 6.6, and CQI-IRCA ISO 14001 Lead Auditor Curriculum (Distinguishing Corrections from Corrective Actions).

Question 2 Choose 3

An internal auditor of a manufacturer of aluminium products for the car industry raised a nonconformity against section 6.2.2 of ISO 14001 in Report IA202. The nonconformity (NC3) stated:

" Top management has not analysed why none of the environmental objectives set for the last year have been met. "

A third-party auditor reviewing the internal audit process came across the nonconformity and found that no corrective action was documented. The EMS Manager confirmed no action had been taken, but added he expected a number of objectives to be achieved in the next three months, so there was no need for further action. He explained in confidence that the organisation was fighting a takeover bid and resources for environmental projects had been cut.

From the information, select three nonconformities that the auditor could raise to ISO 14001.

Show answerHide answer

Correct answer: E, F, H 10.2.a - Management failed to take corrective action to deal with the audit nonconformity.7.1 - The top management failed to provide the resources needed to meet the objectives.6.2.2 - Actions were not planned to achieve environmental objectives set by management.

Explanation

In accordance with ISO 14001:2015, audit findings must reflect direct, verifiable evidence demonstrating a failure to fulfill explicit standard requirements across resource provision, objective management, and corrective action execution.

Option E (Clause 10.2.a Nonconformity and corrective action): When an internal audit nonconformity is formally identified and reported (such as NC3 in Report IA202), Clause 10.2.a mandates that the organization react to the nonconformity and take action to control, correct, or deal with its consequences. The EMS Manager explicitly confirmed that no corrective action was taken or documented, constituting a clear nonconformity.

Option F (Clause 7.1 Resources): Top management is obligated under Clause 7.1 to determine and provide the resources necessary for the establishment, implementation, maintenance, and continual improvement of the EMS. Cutting budget and resources for environmental projects, directly causing a total failure to achieve established environmental targets, constitutes a nonconformity against resource allocation obligations.

Option H (Clause 6.2.2 Planning actions to achieve environmental objectives): Clause 6.2.2 dictates that when planning how to achieve environmental objectives, the organization must determine what will be done, what resources will be required, and how results will be evaluated. Failing to carry out planned actions to achieve objectives represents a direct failure under this clause.

The remaining options suggest speculative or overly prescriptive measures (such as notifying takeover bidders or setting new takeover-related objectives) that are not required by ISO 14001.

References: ISO 14001:2015 Clauses 6.2.2 (Planning actions to achieve environmental objectives), 7.1 (Resources), 10.2 (Nonconformity and corrective action), and CQI-IRCA ISO 14001 Lead Auditor Curriculum (Grading Audit Findings and Corrective Action Verification).

Question 3 Choose 3

You are conducting a Stage 2 certification audit of Fitalot, a pharmaceutical organisation manufacturing vitamins and other healthcare medicines. In a separate area at the centre of their large site, a supplier produces oxygen that is piped directly into the manufacturing processes of Fitalot. They also deliver oxygen in bulk tankers to other customers. When you review the environmental aspects register, you find that the only environmental aspect recorded for this arrangement relates to the heavy goods vehicles of the supplier transiting the site.

You ask the EMS Manager about the environmental consequences of this arrangement for Fitalot and are told that they are not significant, since the supplier provides its own services for water, sewage, waste, and energy. The EMS Manager tried unsuccessfully to communicate with the supplier, who is located inside the Fitalot site. He said they were outside the scope of the EMS and therefore never audited.

After gathering more evidence, you note down findings against several clauses of ISO 14001. Determine which three of the findings stated are major nonconformities.

Show answerHide answer

Correct answer: B, D, H The organisation has failed to include in the EMS scope the activities, products and services associated with suppliers and contractors performing their activities on its own site. (Clause 4.3)The internal audit programme does not cover the on-site supplier. (Clause 9.2.2)Documentation of environmental impacts was missing for the supplier of oxygen. (Clause 6.1.2)

Explanation

In accordance with ISO 14001:2015 and ISO/IEC 17021-1 requirements, a major nonconformity represents a total breakdown or significant absence of a required management system process that compromises the integrity or capability of the EMS to achieve its intended outcomes.

Option B (Clause 4.3 Scope of the EMS): Artificially excluding a core, high-risk production activity operating physically within the center of the organization's site boundary directly violates Clause 4.3 boundaries and authority requirements, constituting a systemic scope omission (Major Nonconformity).

Option D (Clause 9.2.2 Internal Audit Programme): Completely excluding on-site supplier operations directly supplying critical raw materials from the internal audit programme represents a breakdown in monitoring and evaluation governance under Clause 9.2 (Major Nonconformity).

Option H (Clause 6.1.2 Environmental Aspects): Failing to identify and document environmental aspects and associated impacts for on-site chemical manufacturing operations that Fitalot controls or influences constitutes a total absence of aspect risk evaluation for primary processes (Major Nonconformity).

Conversely, Option A is factually false per the scenario (truck transit aspects were recorded). Option C is invalid because ISO 14001 does not mandate that contractor policies mirror the host company's policy. Options F and G reflect localized operational communication issues rather than major systemic breakdowns.

References: ISO 14001:2015 Clauses 4.3 (Determining scope), 6.1.2 (Environmental aspects), 9.2.2 (Internal audit programme), ISO/IEC 17021-1 Clause 9.4.5, and CQI-IRCA ISO 14001 Lead Auditor Curriculum (Grading Nonconformities).

That's the last free question in Closing an ISO 14001 Audit

You've seen the free 30% (3 of 11 questions). Full access unlocks every question and full-length ISO-14001-Lead-Auditor mock exams, a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the ISO-14001-Lead-Auditor exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real ISO-14001-Lead-Auditor exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full ISO-14001-Lead-Auditor mock exam
  • —questions per mock
  • —time limit
  • 95questions in the bank
  • Newmock on every attempt