Show answerHide answer
Correct answer: A Readiness assessment.
Explanation
Explanation:A readiness assessment is the best choice for providing overall assurance on the likelihood of a software implementation's success. It is a forward-looking evaluation conducted before the system goes live to determine whether the organization is prepared for the change.
Why the other options are incorrect:
B. Project risk assessment
. This focuses on identifying potential risks during the implementation process, but it does not provide an overarching evaluation of the organization's overall preparedness or a direct conclusion on the likelihood of success.
C. Post-implementation review.
This is a backward-looking assessment conducted after the system is live. It evaluates whether the project met its goals and whether benefits were realized. It cannot provide assurance on the likelihood of success before the fact.
D. Key phase review.
This is a point-in-time check at a specific project milestone. While useful for tracking progress, it does not provide the "overall assurance" across all the interconnected elements required for success, which is the hallmark of a readiness assessment.
References:
IIA GTAG – Auditing IT Projects: This guide emphasizes that "readiness assessments" are a key component of a comprehensive project audit strategy, designed to independently verify that the project is set up for success before final implementation.
IIA GTAG – Auditing Business Applications: This guidance highlights that internal auditors should evaluate applications across their entire lifecycle. Assessing readiness for a new application (like an ERP) is a critical step to ensure the organization is prepared to realize its objectives.