Show answerHide answer
Correct answer: D Amount of resources required to conduct the follow-up activities.
Explanation
Explanation:This question evaluates the internal auditor's understanding of the key criteria for determining the need to follow up on audit recommendations. According to IIA guidance, the decision should be based on the significance of the risk and the nature of the corrective action, not on the internal audit activity's administrative capacity. The focus should remain on the importance of the issue, as resource constraints should not undermine the follow-up of critical findings .
✔️ Correct Option:
D. Amount of resources required to conduct the follow-up activities.
This is not a primary consideration when deciding whether to follow up. The IIA guidance emphasizes that resource limitations should not be the determining factor for a necessary follow-up; the significance of the issue and potential risks take precedence. Therefore, resource availability should not be a reason to forgo monitoring progress .
❌ Incorrect Options:
A. Degree of effort and cost needed to correct the reported condition.
This is a valid consideration. The effort and cost required by management to implement a corrective action directly influence the need for follow-up to ensure the agreed-upon actions are indeed taken. This factor is specifically listed in the IIA guidance .
B. Complexity of the corrective action.
This is a valid consideration. More complex corrective actions are more likely to encounter unforeseen problems or implementation delays, thus warranting a more diligent and structured follow-up to verify their effectiveness .
C. Impact that may result should the corrective action fail.
This is a valid consideration. The potential severity of the impact if a recommendation is not implemented is fundamental to the IIA risk-based approach. The higher the risk of failure, the greater the need for follow-up to ensure the risk is mitigated .
🔧 Reference:
→ IIA Standard 2500: Monitoring Progress: Confirms that the CAE must establish a follow-up process to monitor management actions; the determination of which recommendations to follow up on is based on their significance.
→ IIA Practice Advisory 2500.A1-1: Details the specific factors for scheduling follow-up, including degree of effort, complexity, and potential impact.