Question 11 Choose 1

The entire objectives-risks-controls infrastructures of an organization are subject to greater
monitoring and continuous improvements due to:

Show answerHide answer

Correct answer: D

Self-assessment methodology

Question 12 Choose 1

In traditional approach, evaluating risks and controls were done by auditors and in control
self-assessment approach it is done by work teams.

Show answerHide answer

Correct answer: A

True

Question 13 Choose 1

In traditional approach, objectives used were of management’s and in control
selfassessment approach it is of work teams’.

Show answerHide answer

Correct answer: B

False

Question 14 Choose 1

A process affected by an entity’s board of directors, management and other personnel
designed to provide reasonable assurance regarding the achievement of objectives is
called:

Show answerHide answer

Correct answer: C

Internal control

Question 15 Choose 1

Operations control is related to the:

Show answerHide answer

Correct answer: D

Effective and efficiency use of the entity’s resources.

Question 16

__________ is relating to the entity’s fulfillment with applicable laws and regulations.

Show answerHide answer

Correct answer: A

Question 17 Choose 1

Who identified internal control components including Control environment, Information &
communication, risk assessment, control activities and Monitoring?

Show answerHide answer

Correct answer: B

The American Institute of Certified Professional Accountants (AICPA)

Question 18 Choose 1

In traditional approach, final report is issued by management and in control selfassessment
approach it is issued by work teams’.

Show answerHide answer

Correct answer: B

False

Question 19 Choose 1

The policy statement that defines the objectives for and commitment to risk management
within the organization’s strategic and operational context is called:

Show answerHide answer

Correct answer: B

Enterprise risk management

Question 20 Choose 1

New employees, consultants and contractors must receive security awareness training and
supporting documentation at the time of employment refers to:

Show answerHide answer

Correct answer: C

Both A & B

Full mock exam

Sit the IIA-CCSA exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real IIA-CCSA exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full IIA-CCSA mock exam
  • 65questions per mock
  • 105 mintime limit
  • 235questions in the bank
  • Newmock on every attempt