What did the business analyst fall to do during sprint planning'?
Show answerHide answer
Correct answer: A Prioritize the sprint backlog with stakeholders
Explanation
Explanation:In an Agile environment using Scrum (implied by "sprint," "sprint demo," and "backlog"), the contents of a sprint are determined during sprint planning. During this meeting, the entire team, guided by the Product Owner and Business Analyst, decides which items from the prioritized backlog can be completed within the sprint's capacity.
A. Prioritize the sprint backlog with stakeholders: The fact that an "important" item requested by a key stakeholder (marketing team) was missed from the deliverables indicates a breakdown in the prioritization process. The BA likely failed to ensure that the marketing team's needs were accurately prioritized, clearly communicated as critical, and successfully included in the sprint commitment. The BA should have ensured all stakeholders were aligned on the sprint goals and the committed deliverables, making the missing automation a visible gap during planning or the demo itself.
Why other options are incorrect
B. Calculate the sprint capacity correctly: While capacity planning is essential, incorrect calculation of capacity would lead to incomplete work or scope creep, not necessarily the omission of a known, important feature from the sprint plan altogether.
C. Create a burndown list of sprint tasks: A burndown chart is a tracking mechanism used during the sprint to monitor progress. It does not affect which items are selected during sprint planning or how they are prioritized.