SAP certification · Exam C_TS422_2023

C_TS422_2023 Mock Exam Page 2

SAP Certified Associate - SAP S/4HANA Cloud Private Edition, Production Planning and Manufacturing

Free C_TS422_2023 mock exam questions 11–13, each with the answer and an explanation.

13 questions · 30 minutes · free, no sign-up

Free C_TS422_2023 questions

11–13 of 13 free
Question 11 Choose 2
You are a consultant on an SAP S/4HANA Cloud Greenfield project. Which of the following aspects should you focus on to achieve maintain clean core data quality? Note: There are 2 correct answers to this question.
Show answerHide answer

Correct answer: B, C AccuracyTimeliness

Explanation

Explanation:

The Clean Core Data dimension is one of the five pillars of SAP's Clean Core strategy (alongside Code, Process, Integration, and Extensibility). Achieving high-quality data in a Greenfield project involves:

1. Accuracy (Option B)
Accuracy is the most fundamental aspect of data quality. In an S/4HANA environment, the "Single Source of Truth" (Universal Journal) and simplified data models rely on precisely defined master and transactional data.

2. Timeliness (Option C)
S/4HANA is designed for real-time business processing. Therefore, data must not only be accurate but also current.

Why the Other Options are Incorrect

A. Efficiency:
While efficiency is a primary goal of the project and the processes you design, it is not considered a core "dimension" of data quality itself. Efficiency is the result of having high-quality data, but it doesn't define the quality of the data record.

D. Stability:
Stability generally refers to the Software/Technical Stack or the Infrastructure (ensuring the system doesn't crash and that the core code remains unmodified). While stable systems are important, "Stability" is not a standard metric used to measure the quality of a specific piece of data.

References

SAP Learning: Managing Clean Core for SAP S/4HANA Cloud – Unit on Clean Core Data.
SAP White Paper: Clean Core Data for SAP S/4HANA Cloud – Defines the metrics for data health, including accuracy and timeliness.
Question 12 Choose 2
What are the advantages of collective orders? Note: There are 2 correct answers to this question.
Show answerHide answer

Correct answer: A, C To perform availability checks across the entire collective orderTo show the flow of batches across the entire collective order

Explanation

Explanation :

A collective order in SAP S/4HANA links a header order with its subordinate orders for semi-finished materials. This structure allows integrated planning and execution across multiple levels of production. The main advantages are related to availability checks and batch traceability.

A. Perform availability checks across the entire collective order:
When collective orders are used, the system can execute availability checks not only for the header material but also for all subordinate orders. This ensures that required components and capacities are available across the entire production chain. It improves reliability in planning and execution because shortages or constraints are identified early at any level of the order network.

C. Show the flow of batches across the entire collective order:
Collective orders enable batch traceability across multiple production levels. This means that the flow of batches from raw materials through semi-finished goods to the final product can be tracked seamlessly. Such visibility is critical for industries with strict compliance requirements (e.g., pharmaceuticals, food, automotive), where batch genealogy must be documented for quality assurance and regulatory audits.

Why the other options are not correct

B. Coordinate orders in the planning board:
The planning board is primarily used in PP/DS (Production Planning and Detailed Scheduling) scenarios. Collective orders in standard PP do not provide direct coordination in the planning board. Hence, this is not a recognized advantage.

D. Post confirmations for the entire collective order:
Confirmations (such as yield, scrap, or activity postings) are executed at the level of each individual order. Collective orders do not allow a single confirmation posting across all linked orders. Therefore, this option is incorrect.

References:
SAP Help Portal – Collective Orders (help.sap.com in Bing)
SAP Community – Collective Orders and Batch Traceability 【source】
Question 13 Choose 2
Which of the following questions do you have to answer before you start creating a bill of material (BOM)? Note: There are 2 correct answers to this question.
Show answerHide answer

Correct answer: B, C Is the material type allowed in the BOM?Which base unit of measure does the material have?

Explanation

Explanation:

Before creating a Bill of Material (BOM) in SAP S/4HANA Cloud, certain foundational questions must be answered to ensure the BOM is valid and accurately reflects production requirements.

Material Type Allowed (B):
Not all material types can have BOMs. For example, finished goods (FERT) and semi-finished goods (HALB) are typically allowed, whereas raw materials (ROH) or services (DIEN) cannot be the main item in a BOM.
Checking the material type ensures that the BOM can be created and used in production planning, costing, and material requirement planning (MRP).

Base Unit of Measure (C):
The base unit of measure of the material determines how component quantities are calculated in the BOM.
For example, if the finished product’s base unit is “EA” (each), the component quantities must align with this unit.
This is critical for accurate material planning, procurement, and production execution.

Why other options are incorrect:

A. In which storage location is the BOM required?
Incorrect. BOMs are created at the plant level, not at the storage location level. Storage location information is relevant for stock and inventory management, but not a prerequisite for BOM creation.

D. What status does the BOM have?
Incorrect. The BOM status (e.g., released, in preparation) is assigned after creating the BOM, not before. It controls usage and modifications but is not a prerequisite for creation.

References:

SAP Help Portal – Bill of Material in SAP S/4HANA Cloud:
“Before creating a BOM, the system checks whether the material type allows BOM creation and the base unit of measure to ensure correct component quantities.”

That's the last free question

You've seen the free 30% (13 of 44 questions). Full access unlocks every question and full-length C_TS422_2023 mock exams (80 questions, 180 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the C_TS422_2023 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real C_TS422_2023 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full C_TS422_2023 mock exam
  • 80questions per mock
  • 180 mintime limit
  • 44questions in the bank
  • Newmock on every attempt