Question 11 Choose 1
What document, when saved, creates a commitment for an internal order?
Show answerHide answer

Correct answer: D Purchase order

Explanation

Explanation:

In SAP S/4HANA, a commitment is a financial obligation created when a purchase requisition is converted into a purchase order. If the purchase order is assigned to an internal order (as a real or statistical object), the system automatically records a commitment against that internal order. This commitment represents the expected cost before the actual goods receipt or invoice is posted, allowing for budget monitoring and control.

Why Other Options are Incorrect:

A. Maintenance order / B. Production order:
These manufacturing orders can create actual costs but do not typically generate commitments against internal orders when saved. Commitments are specific to external procurement documents.

C. Goods receipt:
This updates actual inventory and posts an actual cost (inventory receipt), reducing the existing commitment from the purchase order. It does not create a new commitment.

Reference:
SAP S/4HANA Controlling (CO) with Internal Orders: Purchase orders assigned to internal orders create commitments for budget consumption and availability control.
Question 12 Choose 3
A goods issue is posted against a production order. What are the results? Note. There are 3 correct answers to this question.
Show answerHide answer

Correct answer: B, D, E The material reservation is reduced.A material ledger document is createdActual costs are updated in the production order.

Explanation

Explanation:

B. The material reservation is reduced:
When a production order is created, the system "reserves" the necessary components in the warehouse to ensure they aren't used elsewhere. Once the Goods Issue (GI) is posted, the physical stock is consumed, and the system automatically reduces or "clears" the reservation because the requirement has been fulfilled.

D. A material ledger document is created:
In SAP S/4HANA, the Material Ledger is mandatory. Any movement of goods that impacts inventory valuation triggers the creation of a Material Ledger document alongside the standard Material Document and Accounting Document. This ensures granular tracking of material costs and valuations.

E. Actual costs are updated in the production order:
The production order serves as a cost object. When components are issued, the system calculates their value (Quantity × Price) and posts this as an actual cost to the order. This allows for variance analysis later—comparing these actual costs against the original "planned" costs.

Why the other options are incorrect:

A. A warehouse task is created:
A warehouse task is a document in Extended Warehouse Management (EWM). While a GI might be the result of a warehouse task being confirmed, the GI posting itself does not create the task; the task must usually exist before the goods can be moved and issued.

C. Internal labor costs are posted:
Labor costs (secondary costs) are posted during the Order Confirmation step (recording time spent), not the Goods Issue step (recording materials used).

References:
SAP Course TS410: Unit: Manufacturing Execution (Production Order Processing).
SAP S4200: Business Processes in SAP S/4HANA Manufacturing.
SAP Help Portal: Goods Issue for Production Orders (PP-SFC).
Question 13 Choose 3
Which of the following are business partner categories in SAP S/4HANA? Note: There are 3 correct answers to this question
Show answerHide answer

Correct answer: B, C, E GroupPersonOrganization

Explanation

Explanation:

In SAP S/4HANA, every entity you do business with must be assigned to one of exactly three categories. This category is defined at the moment of creation and cannot be changed later because it determines which fields (like First Name vs. Legal Name) are available in the master record.

C. Person:
This category represents a private individual. Data fields are specific to a human being, such as First Name, Last Name, Academic Title, and Gender.
Example: A retail customer or an internal employee.

E. Organization:
This represents a legal entity or a subdivision of a legal entity. It uses fields like Name 1, Name 2, Legal Form, and Industry.
Example: A company (LLC, Corp), a subsidiary, or a department.

B. Group:
This is used to represent a less formal association or a collective of persons/entities. It is often used for specific business scenarios like a Shared Living Arrangement or a Married Couple where they act as a single unit in a business process.

Why the other options are incorrect:

A. Individual:
While a "Person" is an individual, "Individual" is not a technical term or category used in the SAP S/4HANA Business Partner master data.

D. Corporation:
A corporation is a type of Organization, but it is not a standalone category. You would select the category "Organization" and then specify the "Legal Form" as a Corporation within the data fields.

References:
SAP Course TS410: Unit: Introduction to SAP S/4HANA (Business Partner Concept).
SAP S4500: Business Processes in Management of Material Procurement.
SAP Help Portal: Business Partner Categories (CA-BP).
Question 14 Choose 3
Which of the following are selection modes for running MRP? Note: There are 3 correct answers to this question
Show answerHide answer

Correct answer: A, C, D MRP LiveClassical MRPRegenerative MRP

Explanation

Explanation:

The MRP run is the engine that calculates the "net requirements" by comparing available stock and receipts against existing demands.

A. MRP Live (MD01N):
This is the optimized version for S/4HANA. It runs directly on the HANA database (in-memory). It is significantly faster than previous versions because it reads data and calculates requirements in a single step, making it ideal for large volumes of data. +1

C. Classical MRP:
This refers to the traditional MRP run used in SAP ERP (ECC). While S/4HANA encourages MRP Live, Classical MRP is still available (and sometimes necessary) for specific complex planning scenarios or when using certain BAdIs (custom enhancements) that aren't yet compatible with the HANA-optimized run.

D. Regenerative MRP (NEUPL):
This is a "planning mode" or scope. When you run MRP in Regenerative mode, the system plans all materials in a plant, regardless of whether they have had any changes since the last run. This is usually done periodically (like weekends) to ensure total data consistency across the entire plant.

Why the other options are incorrect:

B. Predictive MRP (pMRP):
While this is a feature in S/4HANA, it is a simulative tool used to identify potential capacity bottlenecks before they happen. It is not a standard "execution mode" for the actual production MRP run.

E. Backorder Processing (BOP):
This is a tool within Global Available-to-Promise (gATP) or Advanced ATP. It is used to re-allocate confirmed quantities to sales orders when supply is short, but it does not calculate material requirements like MRP does.

References:
SAP Course TS410: Unit: Material Requirements Planning.
SAP S4200: Business Processes in SAP S/4HANA Manufacturing.
SAP Help Portal: MRP Live and Planning Execution.
Question 15 Choose 3
What elements are recorded during an overall completion confirmation of a maintenance order? Note: There are 3 correct answers to this question
Show answerHide answer

Correct answer: A, B, D Time entryMeasuring documentsMaterials

Question 16 Choose 2
What are some of the functions of SAP Extended Warehouse Management? Note: There are 2 correct answers to this question
Show answerHide answer

Correct answer: B, C Mobile device integrationStorage-bin-level determination for incoming goods

Question 17 Choose 3
Which business process activities create a Financial Accounting (FI) document? Note: There are 3 correct answers to this question
Show answerHide answer

Correct answer: B, C, E Post goods issue to a production orderExecute a depreciation runTransfer stock to another company code

Question 18 Choose 2
What transactions credit a production order? Note: There are 2 correct answers to this question.
Show answerHide answer

Correct answer: A, D Goods receiptOrder settlement

Question 19 Choose 1
What planning tool prioritizes sales order forecasting and strategically plans inventory buffers?
Show answerHide answer

Correct answer: B Demand-driven MRP (DDMRP)

Question 20 Choose 2
What are the benefits of using a business partner in SAP S/4HANA? Note: There are 2 correct answers to this question
Show answerHide answer

Correct answer: B, C Redundant data is reduced.Data architecture is harmonized

Full mock exam

Sit the C_TS410_2022 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real C_TS410_2022 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full C_TS410_2022 mock exam
  • 80questions per mock
  • 180 mintime limit
  • 80questions in the bank
  • Newmock on every attempt