Production Accounting (F2261, F2262, F2271) questions

1–6 of 6 free
Question 1 Choose 3
You have just performed the final goods issue and final activity confirmation for a production order. What are the implications in accounting?
Note: There are 3 Correct Answers to this question.
Show answerHide answer

Correct answer: B, C, E Increased direct material costs Increased work in progress (WIP) costs Increased overhead costs

Question 2 Choose 3
You plan to use process orders in a Lot-based make-to-stock (MTS) scenario. Which master data is required?
Note: There are 3 Correct Answers to this question.
Show answerHide answer

Correct answer: A, B, E Bill of Materials Master recipe Resources

Question 3 Choose 1
In your system, event-based revenue recognition and COGS split are active. Which accounting documents are created at goods issue for a sales order?
Show answerHide answer

Correct answer: D One for goods issue, one for COGS split, and one for event-based revenue recognition.

Question 4 Choose 2
What can be the cause for a remaining variance on a production order?
Note: There are 2 Correct Answers to this question.
Show answerHide answer

Correct answer: C, D The standard cost price of an input material has changed after calculating the standard price of the produced material The overhead calculation rate is different than that used for the calculation of the standard price

Question 5 Choose 3
Which of the following are examples of postings triggered by event-based?
Note: There are 3 Correct Answers to this question.
Show answerHide answer

Correct answer: A, B, E Work in progress (WIP) calculation Overhead calculation Final goods receipt

Question 6 Choose 1
In SAP S/4HANA Cloud Public Edition, which object is used to collect costs in the context of a project make to order for services?
Show answerHide answer

Correct answer: C WBS element

That's the last free question in Production Accounting (F2261, F2262, F2271)

You've seen the free 30% (6 of 21 questions). Full access unlocks every question and full-length C_S4CCO_2506 mock exams, a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the C_S4CCO_2506 exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real C_S4CCO_2506 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full C_S4CCO_2506 mock exam
  • —questions per mock
  • —time limit
  • 80questions in the bank
  • Newmock on every attempt