Note: There are 2correct answers to this question.
Show answerHide answer
Correct answer: C, D Operating hoursWorking calendar
Explanation
Explanation:The calculation of a due date is not a simple linear count of hours; it is a "net" calculation based on business availability:
Operating Hours (C):
These define the time intervals during a day when the service team is active (e.g., 08:00 to 17:00). If a case with a 4-hour resolution target is created at 16:00, the SLA engine uses the Operating Hours to calculate that only 1 hour remains today, pushing the final "Due Date" to 11:00 the following morning.
Working Calendar (D):
This provides the "Holiday" context. It identifies specific dates (e.g., Christmas, National Holidays) where the organization is closed. The SLA engine automatically excludes these dates from the duration calculation, ensuring that deadlines do not expire during periods when no one is working.
Why the Other Options are Incorrect:
A (Maintenance Plan):
These are used for proactive service (preventative maintenance) and scheduling recurring tasks. While they define when a service should occur, they do not provide the time-logic variables (hours/holidays) required by the SLA engine to calculate reactive deadlines.
B (Service Contract):
A contract determines the entitlement (e.g., "Bronze" vs. "Gold" support). It acts as a pointer to which SLA should be applied, but the contract itself does not perform the mathematical calculation of the due date.
References:
SAP Help Portal (Service Level Agreements): Documentation states that milestones are calculated based on the "Operating Hours" and "Holiday Calendar" assigned to the SLA or the Service Territory.