A network security team observes phishing attacks on a user machine from a remote location. The organization has a policy of saving confidential data on two different systems using different types of authentication. What is the next step to control such events after the security team verifies all users in Zero Trust modeling?
Show answerHide answer
Correct answer: AEnforce risk-based and adaptive access policies.
Explanation
Explanation:
Why Risk-Based & Adaptive Access Policies?
Phishing Attack Context:
Even with Zero Trust user verification, attackers can compromise credentials.
Risk-based policies dynamically adjust access based on:
User behavior anomalies (e.g., login from a new country).
Device security posture (e.g., missing patches).
PCI DSS Alignment (Confidential Data Protection):
Adaptive policies limit access to sensitive systems if risk is detected (e.g., block access to financial data post-phishing).
Why Other Options Are Secondary?
B) Device health checks: Part of Zero Trust but reactive—adaptive policies act proactively.
C) Context-based NAC: Too static—doesn’t address real-time risk scoring.
D) Device trustworthiness: Covered under risk assessment (Option A).
PCI DSS v4.0: Requires dynamic access controls for sensitive data.
Question 42Choose 2
A network design includes a long signaling delay in notifying the Layer 3 control plane that an interface has failed. Which two of these actions would reduce that delay? (Choose two.)
Show answerHide answer
Correct answer: B, DReduce the time for the network to reconverge.Enable lower data link layer recovery systems to have an opportunity to restore the interface.
Explanation
Explanation:
1. Reduce Reconvergence Time (B)
Why?
Faster Layer 3 protocol timers (e.g., BGP keepalives, OSPF dead intervals) minimize delays in detecting failures and recalculating routes.
Example: Adjust OSPF timers to hello=1s, dead=3s for sub-second failure detection.
2. Enable Data Link Layer Recovery (D)
Why?
Lower-layer mechanisms (e.g., Ethernet OAM, BFD for L2) can detect and restore links before Layer 3 protocols react.
Example: BFD microsecond-level detection for LAG member failures.
Why Other Options Are Incorrect?
A) Increase stability: Generic and doesn’t address delay reduction.
C) Increase flap notifications: Counterproductive—flaps add instability without fixing root causes.
Reference:
RFC 5880 (BFD): Fast failure detection at L2/L3.
Cisco OSPF Optimization Guide: Recommends aggressive timers for critical networks.
Question 43Choose 1
Company XYZ branch offices connect to headquarters using two links, MPLS and Internet. The company wants to design traffic flow so voice traffic uses MPLS and all other traffic uses either link, avoiding process switching. Which technique can be used?
Show answerHide answer
Correct answer: APolicy-based routing
Explanation
Explanation:
Why Policy-Based Routing (PBR)?
Traffic Steering Requirements:
Voice traffic must use MPLS: PBR can override the routing table to force voice packets (e.g., DSCP EF) onto the MPLS link.
Other traffic uses either link: PBR can load-balance remaining traffic across MPLS/Internet.
Avoids Process Switching:
PBR is CEF-switched (hardware-accelerated) when configured properly, unlike process switching.
How PBR Works:
Match traffic (e.g., VoIP with ACL or DSCP).
Why Other Options Fail?
B) Virtual links: Used for OSPF connectivity, not traffic engineering.
C) Visualization: Irrelevant to routing decisions.
D) Floating static routes: Cannot selectively route voice vs. data.
Various teams in different organizations within an enterprise are preparing low-level design documents using a Waterfall project model. Input from relevant stakeholders was captured at the start of the project, and the scope has been defined. What impact will it have if stakeholders ask for changes before documentation is complete?
Show answerHide answer
Correct answer: CSignificant effort and time are required.
Changes after the design phase force revisiting prior stages, causing:
Rework: Redesign documents, update dependencies.
Delays: Reapprovals, retesting.
Impact on Stakeholder Requests:
Unlike Agile, Waterfall lacks flexibility for mid-project changes.
Example: A new compliance requirement could invalidate completed designs, adding weeks of effort.
Why Other Options Are Less Accurate?
A) "Think outside the box": Waterfall discourages creativity post-requirements.
B) "Rework is expected": True but secondary—the core issue is time/cost impact.
D) "Flexible approach": Waterfall is inflexible by design.
Reference:
IEEE 1074 (SDLC): Waterfall’s linear constraints.
PMBOK 6th Ed.: Highlights change management challenges in predictive models..
Question 45Choose 1
Cost is often one of the motivators for a business to migrate from a traditional network to a software-defined network. Which design decision is directly influenced by CAPEX drivers?
Show answerHide answer
Correct answer: AScalability
Explanation
Explanation:
Why Scalability is a CAPEX Driver in SDN?
CAPEX Reduction via SDN:
Traditional Networks: Scaling requires expensive hardware upgrades (e.g., bigger routers, more licenses).
Cisco SAFE Architecture: Contrasts fate-sharing with redundancy.
Question 48Choose 1
An enterprise solution team is analyzing multilayer architecture and multicontroller SDN solutions for multisite deployments. The analysis focuses on the ability to run tasks on any controller via a standardized interface. Which requirement addresses this ability on a multicontroller platform?
Show answerHide answer
Correct answer: BUse the East-West API to facilitate replication between controllers within a cluster.
Explanation
Explanation:
Why East-West APIs Enable Task Distribution?
Multicontroller Coordination:
East-West APIs allow SDN controllers in a cluster to sync state (e.g., network topology, flow rules) and distribute tasks.
Example: If Controller A fails, Controller B takes over its workloads seamlessly.
Standardized Interface Requirement:
APIs like OpenDaylight’s clustering RPCs or ONOS Gossip Protocol ensure controllers share a unified view, enabling any controller to execute tasks.
Why Other Options Are Incorrect?
A) Root controller: Centralizes control (opposite of distributed tasking).
C) Physical connectivity: Necessary but doesn’t standardize logical coordination.
D) OpenFlow: Manages switches, not inter-controller communication.
Reference:
OpenDaylight Clustering Guide: East-West APIs for state sync.
ONOS Distributed Architecture: Uses gossip protocols for task distribution.
Question 49Choose 2
Which two features control multicast traffic in a VLAN environment? (Choose two)
Show answerHide answer
Correct answer: A, E
IGMP snooping
pruning
Explanation
Explanation:
1. IGMP Snooping (A)
Purpose:
Listens to IGMP (Internet Group Management Protocol) messages between hosts and routers to track multicast group memberships.
Prevents switches from flooding multicast traffic to all ports (limits traffic to only ports with interested receivers).
VLAN Impact:
Operates per-VLAN to isolate multicast domains.
2. Pruning (E)
Purpose:
Blocks multicast traffic from being forwarded to VLANs with no active receivers.
Example: Cisco’s VLAN pruning for VTP (VLAN Trunking Protocol) or manual pruning on trunks.
Why Other Options Are Incorrect?
B) MLD snooping: For IPv6 multicast (not IPv4/VLAN-centric).
C) RGMP: Rarely used; coordinates multicast between routers/switches.
D) PIM snooping: Tracks PIM routing in L3 switches, not VLAN traffic control.
Reference:
IEEE 802.1D (IGMP Snooping Standard)
Cisco VLAN Pruning Configuration Guide
Question 50Choose 2
Which two types of planning approaches are used to develop business-driven network designs and to facilitate the design decisions? (Choose two)
Show answerHide answer
Correct answer: B, D
strategic planning approachtactical planning approach
Explanation
Explanation:
1. Strategic Planning Approach (B)
Purpose:
Focuses on long-term business goals (e.g., 3–5 years) and aligns network design with organizational vision.
Rolling out VoIP QoS policies in the next quarter.
Migrating a branch office to a new firewall.
Why Other Options Are Less Relevant?
A) Cost optimization: A goal, not a planning methodology.
C) Modular approach: A design technique (e.g., breaking networks into blocks), not business-driven planning.
E) Business optimization: Vague—strategic/tactical planning are structured methods to achieve this.
Reference:
ITIL 4 (Strategic vs. Tactical Planning)
Cisco Business-Driven Network Design Guide
Full mock exam
Sit the 400-007 exam before exam day
Full-length mocks with the same number of questions and the same time limit as the real 400-007 exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.