Question 1 Choose 2
Your organization always stresses the importance of on-time delivery and reliability. A manager has detected that your team's progress is too slow. They feel that your team's velocity needs to be 10% higher. The organization expects you, as the Scrum Master, to make it happen. How do you respond? (choose two answers)
Show answerHide answer

Correct answer: B, C You inform management of organizational impediments that prevent the Scrum Team from being more productive. You enlist their help to remove these impediments.You explain how a Scrum Team uses the velocity of a Sprint primarily to forecast work for the next Sprint, not to perfectly predict future productivity. You refer management to the Product Owner for all information concerning the progress of development.

Question 2 Choose 1
You are a Scrum Master helping to establish five Scrum Teams that will be building a product. You discuss with them the high level of integration that the product Increment will require by the end of their first Sprint. It is a highly anticipated product, both by consumers and by the organization. Of the options raised by the future Scrum Team members, which option do you encourage?
Show answerHide answer

Correct answer: D All Scrum Teams agree on a shared Definition of Done that describes all work needed to deliver an Increment that is the integrated sum of the work from all Scrum Teams.

Question 3 Choose 2
During the Sprint Review the Product Owner introduces the functionality that is likely to be done over the next Sprints. The Chief Security Officer reminds everyone that through the envisioned functionality, sensitive personal user data will be stored. This might be the subject of external security audits. He reminds everyone of important non-functional requirements with regards to security. These were not applicable and not considered previously What are two effective ways the Scrum Team can manage these high-security concerns? (choose two answers)
Show answerHide answer

Correct answer: C, D They are added to the Product Backlog and addressed throughout the next Sprints, combined with creating the business functionality in those Sprints, no matter how small that business functionality.

During the Sprint Retrospective, the Scrum Team assesses how to add these expectations to the Definition of Done so every future Increment will live up to these requirements. If needed they can work with external specialists to better understand the requirements.

Question 4 Choose 2
You are a Scrum Master employed by the IT department. The IT manager considers adopting Scrum tor a new project He wonders however, what the value is in having all team members attend this meeting called "Daily Scrum" every day. The organization already has its employees attending so many mandatory meetings. What are two outcomes of the Daily Scrum you inform him about, to express the importance of the Daily Scrum? (choose two answers)
Show answerHide answer

Correct answer: A, C During the Daily Scrum the Developers will bring up problems that are hindering their progress, and tor which they nave no means to resolve, this provides an opportunity to resolve those impediments.Through the snort, daily alignment of the Daily Scrum the Developers build and improve a shared understanding of the most important work to be undertaken in the next 24 hours, to achieve the best possible progress toward the Sprint Goal. This daily opportunity to inspect and adapt Will enable the Developers to tackle any unforeseen circumstances that might otherwise disrupt the team's progress.

Explanation




Explanation:

The Daily Scrum is a 15-minute event for the Developers of the Scrum Team to inspect progress toward the Sprint Goal and adapt the Sprint Backlog as necessary, adjusting the upcoming planned work. The Daily Scrum is not a status meeting, but a way for the Developers to collaborate and self-organize around the most important work for the next 24 hours. The Daily Scrum also provides an opportunity for the Developers to identify and communicate any impediments that are hindering their progress, and request help from the Scrum Master or other team members to resolve them.

References:
What is a Daily Scrum?| Scrum.org
What Is the Daily Scrum?| A Guide to the Daily Event - Scrum Alliance
Question 5 Choose 1
In an environment where user acceptance testing is required before the Increment can be put into production, a development manager proposes to have user acceptance testing done every third Sprint, because the feedback from the user acceptance tests are disrupting work in Sprints. Is this a good idea?
Show answerHide answer

Correct answer: B No, the Increment will not be transparent and the feedback loop is too long.

Explanation




User acceptance testing is a process of verifying that the product meets the user's needs and expectations. It is an important feedback mechanism that helps the Scrum Team validate their assumptions, inspect the value and quality of the Increment, and adapt their plans accordingly. Scrum requires that the Increment be transparent, meaning that it is observable and understandable by anyone with a stake in the outcome. Scrum also requires that the feedback loop be short, meaning that the Scrum Team can receive and respond to feedback quickly and frequently.

Therefore, it is not a good idea to have user acceptance testing done every third Sprint, because:

The Increment will not be transparent (B), meaning that the Scrum Team and the stakeholders will not have a clear and shared understanding of what has been done and what remains to be done. This may lead to misalignment, confusion, or conflict over the product vision, scope, and quality.

The feedback loop is too long (B), meaning that the Scrum Team will not be able to inspect and adapt based on the user's feedback in a timely manner. This may lead to wasted effort, missed opportunities, or reduced value delivery.

The other options are not correct because:

It does not depend on what is stated in their Definition of Done (A), which is a formal description of the state of the Increment when it meets the quality standards required for the product. The Definition of Done does not dictate how or when user acceptance testing should be done, but rather what criteria must be met for the Increment to be considered ''Done''.

The Scrum Team is a self-managing team , which means that they have the autonomy and authority to organize and manage their own work within the boundaries of Scrum. However, this does not mean that they can ignore or postpone user feedback, which is essential for delivering value and satisfying customer needs.

The Scrum Team needs stability in the Sprint (D), which means that they need to have a clear and consistent Sprint Goal, Sprint Backlog, and Definition of Done throughout the Sprint. However, this does not mean that they need to avoid or resist user feedback, which is a source of learning and improvement for the product and the process.
Question 6 Choose 2
You are a Scrum Master entering an organization that wants to "evolve" their product development to Scrum. The organization's teams are organized into component teams. This means that teams address one single application layer only (for example, front end, middle tier, back end, and interfaces).

You introduce the concept of feature teams, where teams have the skills to work on multiple layers throughout a Sprint and deliver working software every Sprint. What are two things you take into consideration when moving away from component teams toward feature teams? (choose two answers)
Show answerHide answer

Correct answer: B, C Productivity, in terms of lines of code or story points, will probably suffer during the transition, although even then delivery of business value is still likely to Increase.Feature teams will require time to become productive as people from the different layers and components become accustomed to working and delivering unified functionality together, as one Scrum Team.

Explanation




Explanation:

B: Productivity, in terms of lines of code or story points, will probably suffer during the transition, although even then delivery of business value is still likely to increase. This is a realistic expectation, as the teams will need to learn new skills, collaborate more effectively, and adapt to changing requirements. However, the benefit of feature teams is that they can deliver working software that provides value to the customers and stakeholders every Sprint, rather than waiting for the integration of different components.

C: Feature teams will require time to become productive as people from the different layers and components become accustomed to working and delivering unified functionality together, as one Scrum Team. This is a natural consequence of changing the team structure and culture, as the teams will need to overcome some challenges and conflicts, build trust and rapport, and establish a shared vision and goal. The Scrum Master can help the teams with this transition by facilitating communication, coaching, and mentoring.
Question 7 Choose 2
During a Sprint Review, the Product Owner determines that she is going to release the current Increment to production. The stakeholders ask to stop the Sprint to react more quickly to the user feedback that is expected after this release. The Product Owner prefers to continue the Sprint to make progress with the next release. You facilitate a discussion on how to proceed. What are two acceptable results of this discussion? (choose two answers)
Show answerHide answer

Correct answer: A, C Continue sprinting but shorten the Sprint length to allow for shorter feedback loops.Continue sprinting and include the customer feedback in the Product Backlog.

Explanation




Explanation:

The Sprint Review is an event that inspects the outcome of the Sprint and determines future adaptations. The Product Owner has the authority to release the Increment to production at any time, but this does not mean that the Sprint has to be stopped or changed. The stakeholders can provide feedback and suggestions for the product, but they cannot interfere with the Sprint Goal or the Sprint Backlog within the Sprint.

The Scrum Team can decide to:

Continue sprinting but shorten the Sprint length to allow for shorter feedback loops (A), which is a valid option if the Scrum Team agrees that this will improve their agility and value delivery. However, this should not be done frequently or arbitrarily, as it may disrupt the rhythm and focus of the team.

Continue sprinting and include the customer feedback in the Product Backlog©, which is the most appropriate option as it respects the empirical nature of Scrum and allows the Product Owner to prioritize and order the Product Backlog based on new insights and stakeholder needs.
Question 8 Choose 1
Where should the Daily Scrum be held according to the Scrum Guide?
Show answerHide answer

Correct answer: C Wherever the Developers think is best.

Explanation




Explanation:

According to the Scrum Guide 2020, the Developers can choose the location and structure of their Daily Scrum, as long as it is consistent and conducive to inspection and adaptation. The Daily Scrum is an event for the Developers, not for the Scrum Master, the Product Owner, or the management. The Developers are responsible for planning their work for the next 24 hours and synchronizing their progress toward the Sprint Goal.
Question 9 Choose 2
You are the Scrum Master for three Scrum Teams working on the same product. There is a single Product Backlog that all three Scrum Teams select from. Management is eager to improve the productivity of the teams and wants to standardize velocity across all three teams so that they can see how each team is delivering value. When responding to management, which two statements are appropriate? (choose two answers)
Show answerHide answer

Correct answer: C, D Velocity has no direct relationship with value.Velocity is the amount of business functionality that a Scrum Team creates in a Sprint. It is unique to that team and used as an input to Sprint Planning.

Explanation




Explanation:

C: Velocity has no direct relationship with value. This is a true statement, as velocity is a measure of the amount of work done by a Scrum Team in a Sprint, not the value or quality of that work. Velocity can vary depending on many factors, such as the size, complexity, and priority of the Product Backlog items, the skills and experience of the Developers, the Definition of Done, and the Sprint length. Therefore, velocity is not a reliable indicator of value creation or team performance.

D: Velocity is the amount of business functionality that a Scrum Team creates in a Sprint. It is unique to that team and used as an input to Sprint Planning. This is a true statement, as velocity is a team-specific metric that reflects how much business functionality the Scrum Team can deliver in a Sprint. Velocity can help the Scrum Team to forecast how many Product Backlog items they can select for the next Sprint, based on their past performance and current capacity. However, velocity is not a goal or a target for the Scrum Team, and it should not be compared across teams.

That's the last free question

You've seen the free 30% (9 of 30 questions). Full access unlocks every question and full-length PSM-II mock exams (65 questions, 105 minutes), a different mock on every attempt.

Unlock full mock exam
Full mock exam

Sit the PSM-II exam before exam day

Full-length mocks with the same number of questions and the same time limit as the real PSM-II exam. Every attempt draws a new set of questions from the full bank, so you can keep going until you pass comfortably.

Get full PSM-II mock exam
  • 65questions per mock
  • 105 mintime limit
  • 30questions in the bank
  • Newmock on every attempt